LEVEL - The Residences

by M/s Siroya Keystone · Oshiwara, MumbaiAlso near Jogeshwari West, Andheri West, Goregaon West

Possession date of LEVEL - The Residences: 30 April 2027, moved from 30 December 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800011428, and currently active. Its completion date has moved from December 2023 to April 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 13 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about LEVEL - The Residences?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of LEVEL - The Residences has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51800016646)

    Reason the builder gave MahaRERA:
    “This extension is sought for the flats to be constructed on the floors from 32nd till 35th which the promoter has not sold to any of the purchaser till date. The Promoter undertake that they shall inform the prospective purchaser of the fla…” Read the full reason“This extension is sought for the flats to be constructed on the floors from 32nd till 35th which the promoter has not sold to any of the purchaser till date. The Promoter undertake that they shall inform the prospective purchaser of the flats to be constructed on floors 32nd till 35th about the extended date i.e. 29/12/2024. As far as the delivery of the flat below 32nd floor is concerned, the Promoters are determined to deliver the possession of the flat in the manner as mentioned in the Agreement for Sale executed by and between the Promoter and prospective purchaser.”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51800027187)

    Reason the builder gave MahaRERA:
    “Impact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a s…” Read the full reason“Impact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these mat…”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: LEVEL - The Residences’s extension records on MahaRERA (P51800011428), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on LEVEL - The Residences

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 13 complaints and 8 court cases, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800011428
Status
Registered and active
Builder
M/s Siroya Keystone
Location
Oshiwara, Mumbai · 400102
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
December 2023
Latest completion date
April 2027
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
1
Complaints on MahaRERA
13
Court cases listed
8
Title report on file
Not found

Construction progress of LEVEL - The Residences, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
LEVEL - The Residences100%100%100%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on LEVEL - The Residences every month.

LEVEL - The Residences: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of LEVEL - The Residences →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

LEVEL - The Residences: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about LEVEL - The Residences

What is the possession date of LEVEL - The Residences?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for LEVEL - The Residences in Oshiwara, Mumbai is 30 April 2027 — 36 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for LEVEL - The Residences?

Builders and listing sites often quote an earlier "target" date for handover. The completion date LEVEL - The Residences's builder has filed on MahaRERA, the official one, is 30 April 2027, already 36 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of LEVEL - The Residences extended?

According to GharKundli's check of MahaRERA records (updated October 2026), LEVEL - The Residences's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "This extension is sought for the flats to be constructed on the floors from 32nd till 35th which the promoter has not sold to any of the purchaser till date. The Promoter undertake that they shall inform the prospective purchaser of the flats to be constructed on floors 32nd till 35th about the extended date i.e. 29/12/2024. As far as the delivery of the flat below 32nd floor is concerned, the Promoters are determined to deliver the possession of the flat in the manner as mentioned in the Agreement for Sale executed by and between the Promoter and prospective purchaser."; to 31 December 2026, giving the reason "Impact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these mat…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of LEVEL - The Residences?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of LEVEL - The Residences in Oshiwara, Mumbai is P51800011428.

Is LEVEL - The Residences registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), LEVEL - The Residences is registered as P51800011428 and its status is "Registered and active".

What is the construction status of LEVEL - The Residences?

According to GharKundli's check of MahaRERA records (updated October 2026), LEVEL - The Residences's status on MahaRERA is "Registered and active". As filed by the builder, slab work on LEVEL - The Residences is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does LEVEL - The Residences have complaints on MahaRERA?

13 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is LEVEL - The Residences safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), LEVEL - The Residences is registered on MahaRERA as P51800011428, its completion date has moved 36 months since registration and 13 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if LEVEL - The Residences's possession date changes?

The latest dates are on LEVEL - The Residences's MahaRERA page (P51800011428). GharKundli's Kundli Watch sends a free WhatsApp update on LEVEL - The Residences every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does LEVEL - The Residences have?

According to GharKundli's check of MahaRERA records (updated October 2026), LEVEL - The Residences has one building filed: LEVEL - The Residences with 43 floors.

How big is the land of LEVEL - The Residences?

According to GharKundli's check of MahaRERA records (updated October 2026), LEVEL - The Residences stands on 5,451 sq m of land (about 1.3 acres), with 12,304 sq m of sanctioned built-up area and 247 sq m of recreational open space.

Where can I read reviews of LEVEL - The Residences?

Google Maps has reviews of LEVEL - The Residences written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 13 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is LEVEL - The Residences?

LEVEL - The Residences by M/s Siroya Keystone is in Oshiwara, Mumbai (pincode 400102), near Jogeshwari West, Andheri West, Goregaon West, Maharashtra, and is registered on MahaRERA as P51800011428, per GharKundli's check of MahaRERA records.

When was LEVEL - The Residences registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), LEVEL - The Residences was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on LEVEL - The Residences?

8 court cases are listed for LEVEL - The Residences on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of LEVEL - The Residences?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s Siroya Keystone.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400102

All 115 projects in Jogeshwari West (400102) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.