ELEGANZIA ROYALE
by ANMOL ALLIANCE · andheri w, MumbaiAlso near Andheri East, Marol, J.B. Nagar
Possession date of ELEGANZIA ROYALE: 31 March 2024, moved from 30 June 2021 (33 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800004209. Status: Lapsed (registration period ended). 22 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (March 2024) has passed.
What do you want to know about ELEGANZIA ROYALE?
How the possession date of ELEGANZIA ROYALE has moved
30 June 2021
Completion date given when the project was registered
30 June 2023
Extended at the builder's request (MahaRERA application EXT51800010050)
Reason the builder gave MahaRERA:
“1. Stop of Work on site due to Status Quo Order passed by the Hon.ble Bombay High Court on 19.10.2018 and modified on 09.07.2019 ,which result in no construction work on site for 263 days . 2. Lock down due to the pandemic 3. shortage of ma…” Read the full reason
“1. Stop of Work on site due to Status Quo Order passed by the Hon.ble Bombay High Court on 19.10.2018 and modified on 09.07.2019 ,which result in no construction work on site for 263 days . 2. Lock down due to the pandemic 3. shortage of manpower /work due to pandemic.”31 March 2024
Extended at the builder's request (MahaRERA application EXT51800016737)
Reason the builder gave MahaRERA: “Due to some Legal dispute we are not able to complete the project in time. Hence we request you to grant extension up to 30.03.2024”
Source: ELEGANZIA ROYALE’s extension records on MahaRERA (P51800004209), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ELEGANZIA ROYALE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 22 complaints and 10 court cases, and how it ended
- Construction pace against the March 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800004209
- Status
- Lapsed (registration period ended)
- Builder
- ANMOL ALLIANCE
- Location
- andheri w, Mumbai · 400053
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- March 2024
- Delay so far
- 33 months
- Homes
- 88
- Towers
- 1
- Complaints on MahaRERA
- 22
- Court cases listed
- 10
- Appeals at the tribunal
- 3
- Title report on file
- Not found
Construction progress of ELEGANZIA ROYALE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Eleganzia Royale | 100% | 100% | 90% | 82% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ELEGANZIA ROYALE every month.
ELEGANZIA ROYALE: buildings, flats and land, as filed on MahaRERA
- Buildings: Eleganzia Royale (28 floors)
- Land: 4,514 sq m (about 1.1 acres) · sanctioned built-up 7,511 sq m · recreational space 2,419 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ELEGANZIA ROYALE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ELEGANZIA ROYALE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ELEGANZIA ROYALE
What is the possession date of ELEGANZIA ROYALE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ELEGANZIA ROYALE in andheri w, Mumbai is 31 March 2024 — 33 months later than 30 June 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for ELEGANZIA ROYALE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ELEGANZIA ROYALE's builder has filed on MahaRERA, the official one, is 31 March 2024, already 33 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ELEGANZIA ROYALE extended?
According to GharKundli's check of MahaRERA records (updated November 2026), ELEGANZIA ROYALE's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2023, giving the reason "1. Stop of Work on site due to Status Quo Order passed by the Hon.ble Bombay High Court on 19.10.2018 and modified on 09.07.2019 ,which result in no construction work on site for 263 days . 2. Lock down due to the pandemic 3. shortage of manpower /work due to pandemic."; to 31 March 2024, giving the reason "Due to some Legal dispute we are not able to complete the project in time. Hence we request you to grant extension up to 30.03.2024".
What is the RERA number of ELEGANZIA ROYALE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ELEGANZIA ROYALE in andheri w, Mumbai is P51800004209.
Is ELEGANZIA ROYALE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ELEGANZIA ROYALE is registered as P51800004209 and its status is "Lapsed (registration period ended)".
What is the construction status of ELEGANZIA ROYALE?
According to GharKundli's check of MahaRERA records (updated November 2026), ELEGANZIA ROYALE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Eleganzia Royale is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does ELEGANZIA ROYALE have complaints on MahaRERA?
22 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ELEGANZIA ROYALE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), ELEGANZIA ROYALE is registered on MahaRERA as P51800004209, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 33 months since registration and 22 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ELEGANZIA ROYALE's possession date changes?
The latest dates are on ELEGANZIA ROYALE's MahaRERA page (P51800004209). GharKundli's Kundli Watch sends a free WhatsApp update on ELEGANZIA ROYALE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ELEGANZIA ROYALE have?
According to GharKundli's check of MahaRERA records (updated November 2026), ELEGANZIA ROYALE has one building filed: Eleganzia Royale with 28 floors.
How big is the land of ELEGANZIA ROYALE?
According to GharKundli's check of MahaRERA records (updated November 2026), ELEGANZIA ROYALE stands on 4,514 sq m of land (about 1.1 acres), with 7,511 sq m of sanctioned built-up area and 2,419 sq m of recreational open space.
Where can I read reviews of ELEGANZIA ROYALE?
Google Maps has reviews of ELEGANZIA ROYALE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 22 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ELEGANZIA ROYALE?
ELEGANZIA ROYALE by ANMOL ALLIANCE is in andheri w, Mumbai (pincode 400053), near Andheri East, Marol, J.B. Nagar, Maharashtra, and is registered on MahaRERA as P51800004209, per GharKundli's check of MahaRERA records.
How many homes are in ELEGANZIA ROYALE?
According to GharKundli's check of MahaRERA records (updated November 2026), ELEGANZIA ROYALE has 88 homes in 1 tower registered on MahaRERA.
When was ELEGANZIA ROYALE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ELEGANZIA ROYALE was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on ELEGANZIA ROYALE?
10 court cases are listed for ELEGANZIA ROYALE on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of ELEGANZIA ROYALE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ANMOL ALLIANCE.
Check it yourself on MahaRERA
- How to check the possession date of ELEGANZIA ROYALE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400053
- Parinee i
- Sunbeam Heights
- Tru Gardenia
- Gayatri Enclave
- ESTO ARKIS
- Naman Fifty Eight
- AMAHA SUNFLOWER
- FAME GARDEN
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.