NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED
by SWAMI SHRIHARI DEVELOPERS PVT LTD · Simpoli, MumbaiAlso near Borivali West, Kandivali West, Magathane
Possession date of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED: 1 January 2028, moved from 9 June 2019 (103 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800012629, and currently active. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED?
How the possession date of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED has moved
9 June 2019
Completion date given when the project was registered
31 December 2021
Extended at the builder's request (MahaRERA application EXT51800002210)
Reason the builder gave MahaRERA: “DUE TO DELAY IN DP RULES, delay in tdr loading due to New DCR 2034 AND NEW RULE OF TDR INDEXING METHOD”
1 January 2028
Extended at the builder's request (MahaRERA application EA27082622409)
Reason the builder gave MahaRERA:
“The delay in completion of the project was caused by circumstances beyond the reasonable control of the Promoter. During the crucial period of execution of the project, the entire country was severely affected by the outbreak of the COVID-1…” Read the full reason
“The delay in completion of the project was caused by circumstances beyond the reasonable control of the Promoter. During the crucial period of execution of the project, the entire country was severely affected by the outbreak of the COVID-19 pandemic and the consequent lockdowns, restrictions on movement, suspension of construction activities, shortage of labour, disruption in transportation and supply of construction materials, and other restrictions imposed by the Govemment and local authorities. Owing to these unprecedented circumstances, the construction and allied activities of the pro…”
Source: NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED’s extension records on MahaRERA (P51800012629), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the January 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800012629
- Status
- Registered and active
- Builder
- SWAMI SHRIHARI DEVELOPERS PVT LTD
- Location
- Simpoli, Mumbai · 400092
- Project type
- Residential / Group Housing
- Registered on
- 6 Sep 2017
- Completion date at registration
- June 2019
- Latest completion date
- January 2028
- Delay so far
- 103 months
- Homes
- 56
- Sold or booked
- 43%
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BTE NIRDHAR CHSL | 70% | 20% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BTE NIRDHAR CHSL: covers A Wing- Ground +Stilt Floor+1st to 7TH Floor and Wing B- Stilt floor+1st Floor
Want to know when this changes? Kundli Watch sends a free WhatsApp update on NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED every month.
NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED: buildings, flats and land, as filed on MahaRERA
- Buildings: BTE NIRDHAR CHSL (8 floors, 61 units)
- Land: 919 sq m (about 0.2 acres) · sanctioned built-up 709 sq m
- Boundaries filed include: KASTUR PARK ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Swami Shrihari Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 89 months late); 1 lapsed. 4 complaints on MahaRERA across 2 projects.
Read Google reviews of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED
What is the possession date of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED in Simpoli, Mumbai is 1 January 2028 — 103 months later than 9 June 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED's builder has filed on MahaRERA, the official one, is 1 January 2028, already 103 months later than the 9 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED extended?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2021, giving the reason "DUE TO DELAY IN DP RULES, delay in tdr loading due to New DCR 2034 AND NEW RULE OF TDR INDEXING METHOD"; to 1 January 2028, giving the reason "The delay in completion of the project was caused by circumstances beyond the reasonable control of the Promoter. During the crucial period of execution of the project, the entire country was severely affected by the outbreak of the COVID-19 pandemic and the consequent lockdowns, restrictions on movement, suspension of construction activities, shortage of labour, disruption in transportation and supply of construction materials, and other restrictions imposed by the Govemment and local authorities. Owing to these unprecedented circumstances, the construction and allied activities of the pro…".
What is the RERA number of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED in Simpoli, Mumbai is P51800012629.
Is NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED is registered as P51800012629 and its status is "Registered and active".
What is the construction status of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BTE NIRDHAR CHSL is 20% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED is registered on MahaRERA as P51800012629, its completion date has moved 103 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED's possession date changes?
The latest dates are on NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED's MahaRERA page (P51800012629). GharKundli's Kundli Watch sends a free WhatsApp update on NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED have?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED has one building filed: BTE NIRDHAR CHSL with 8 floors and 61 units.
How big is the land of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED stands on 919 sq m of land (about 0.2 acres), with 709 sq m of sanctioned built-up area.
What is the track record of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Swami Shrihari Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 89 months late); 1 lapsed. 4 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED?
Google Maps has reviews of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED?
NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED by SWAMI SHRIHARI DEVELOPERS PVT LTD is in Simpoli, Mumbai (pincode 400092), near Borivali West, Kandivali West, Magathane, Maharashtra, and is registered on MahaRERA as P51800012629, per GharKundli's check of MahaRERA records. Its boundaries filed there include KASTUR PARK ROAD.
How many homes are in NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED has 56 homes in 1 tower registered on MahaRERA, and 43% of them are sold or booked.
When was NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED was registered on MahaRERA on 6 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED?
No court cases are listed for NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SWAMI SHRIHARI DEVELOPERS PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of NIRDHAR CO OPERATIVE HOUSING SOCIETY LIMITED
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Borivali
- SAFFRONWOODS CHSL
- AVIRAHI ELEGANCE
- PARSHURAM HEIGHTS
- L&T Realty Ahana Tower B
- L&T Realty Ahana Tower A
- MARU MANSION
- SHRADDHA SKYLINE
- RASHMI ICON
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.