by Richa Realtors Private Ltd. · Kalina, MumbaiAlso near Santacruz East, Chembur, Bandra East

Possession date of Bougainvillea: 31 December 2026, moved from 30 April 2019 (92 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800010842, and currently active. 12 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Bougainvillea?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Bougainvillea has moved

  1. 30 April 2019

    Completion date given when the project was registered

  2. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT51800002220)

    Reason the builder gave MahaRERA:
    “Wherein we have submitted revised completion date of the project as 1st April, 2020. We hereby regretfully, inform you that we will not be able to complete the said project Till April,2019. The said delay is not deliberate butsome unavoidab…” Read the full reason“Wherein we have submitted revised completion date of the project as 1st April, 2020. We hereby regretfully, inform you that we will not be able to complete the said project Till April,2019. The said delay is not deliberate butsome unavoidable circumstances are forced us to delay the project. Following are the chronological events which will explain the said delay details uploaded We have received Commencement Certificate on dated 27th May 2019 We have also initiated process of construction”
  3. 31 May 2021

    Extended at the builder's request (MahaRERA application EXT51800008565)

    Reason the builder gave MahaRERA:
    “We have taken extension from 30.04.2019 to 30.04.2020 due to different circumstances and details of the same was also uploaded while taking extension considering previous circumstances along with pandemic situation we request you to give us…” Read the full reason“We have taken extension from 30.04.2019 to 30.04.2020 due to different circumstances and details of the same was also uploaded while taking extension considering previous circumstances along with pandemic situation we request you to give us extension 31st May, 2021. Even in this situation we have completed 75% of work and putting our efforts to complete prior to extension date.”
  4. 31 March 2023

    Extended at the builder's request (MahaRERA application EXT51800012254)

    Reason the builder gave MahaRERA: “Due to COVID-19”
  5. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51800017740)

    Reason the builder gave MahaRERA: “Due to Financial issue Project was delayed now we are completed 90% please find the consent”
  6. 30 August 2024

    Extended at the builder's request (MahaRERA application EXT51800018894)

    Reason the builder gave MahaRERA: “Due to non-corporation of some existing customers”
  7. 31 August 2025

    Extended at the builder's request (MahaRERA application EXT51800025975)

    Reason the builder gave MahaRERA: “financial issues”
  8. 31 December 2026

    Extended at the builder's request (MahaRERA application EA02122518500)

    Reason the builder gave MahaRERA:
    “Initially, the progress of the project was severely affected by the COVID-19 pandemic, which caused restrictions on labour availability, material supply, and overall construction activity. Subsequently, the project faced financial constrain…” Read the full reason“Initially, the progress of the project was severely affected by the COVID-19 pandemic, which caused restrictions on labour availability, material supply, and overall construction activity. Subsequently, the project faced financial constraints. Further, certain clients stopped making their scheduled payments, which directly impacted the project cash flow. Due to these combined challenges, the project execution slowed down, and the unsold flats could not be sold in time, making it difficult to raise the necessary funds for uninterrupted progress.”

Source: Bougainvillea’s extension records on MahaRERA (P51800010842), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Bougainvillea

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 12 complaints, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800010842
Status
Registered and active
Builder
Richa Realtors Private Ltd.
Location
Kalina, Mumbai · 400098
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
April 2019
Latest completion date
December 2026
Delay so far
92 months
Homes
35
Sold or booked
83%
Towers
1
Complaints on MahaRERA
12
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of Bougainvillea, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Bougainviella100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Bougainviella: covers 12 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bougainvillea every month.

Bougainvillea: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Other934 – 1,21022
3 BHK1,19811
2 BHK620 – 9292
  • Buildings: Bougainviella (15 floors, 35 units)
  • Car parking: 45 open
  • Land: 1,676 sq m (about 0.4 acres) · sanctioned built-up 6,776 sq m · recreational space 240 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Bougainvillea →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Bougainvillea: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Bougainvillea

What is the possession date of Bougainvillea?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Bougainvillea in Kalina, Mumbai is 31 December 2026 — 92 months later than 30 April 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Bougainvillea?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Bougainvillea's builder has filed on MahaRERA, the official one, is 31 December 2026, already 92 months later than the 30 April 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Bougainvillea extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Bougainvillea's builder applied to MahaRERA to extend the completion date 7 times: to 30 April 2020, giving the reason "Wherein we have submitted revised completion date of the project as 1st April, 2020. We hereby regretfully, inform you that we will not be able to complete the said project Till April,2019. The said delay is not deliberate butsome unavoidable circumstances are forced us to delay the project. Following are the chronological events which will explain the said delay details uploaded We have received Commencement Certificate on dated 27th May 2019 We have also initiated process of construction"; to 31 May 2021, giving the reason "We have taken extension from 30.04.2019 to 30.04.2020 due to different circumstances and details of the same was also uploaded while taking extension considering previous circumstances along with pandemic situation we request you to give us extension 31st May, 2021. Even in this situation we have completed 75% of work and putting our efforts to complete prior to extension date."; to 31 March 2023, giving the reason "Due to COVID-19"; to 31 December 2023, giving the reason "Due to Financial issue Project was delayed now we are completed 90% please find the consent"; to 30 August 2024, giving the reason "Due to non-corporation of some existing customers"; to 31 August 2025, giving the reason "financial issues"; to 31 December 2026, giving the reason "Initially, the progress of the project was severely affected by the COVID-19 pandemic, which caused restrictions on labour availability, material supply, and overall construction activity. Subsequently, the project faced financial constraints. Further, certain clients stopped making their scheduled payments, which directly impacted the project cash flow. Due to these combined challenges, the project execution slowed down, and the unsold flats could not be sold in time, making it difficult to raise the necessary funds for uninterrupted progress.".

What is the RERA number of Bougainvillea?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Bougainvillea in Kalina, Mumbai is P51800010842.

Is Bougainvillea registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Bougainvillea is registered as P51800010842 and its status is "Registered and active". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.

What is the construction status of Bougainvillea?

According to GharKundli's check of MahaRERA records (updated October 2026), Bougainvillea's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Bougainviella is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Bougainvillea have complaints on MahaRERA?

12 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Bougainvillea safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Bougainvillea is registered on MahaRERA as P51800010842, its completion date has moved 92 months since registration, 12 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Bougainvillea's possession date changes?

The latest dates are on Bougainvillea's MahaRERA page (P51800010842). GharKundli's Kundli Watch sends a free WhatsApp update on Bougainvillea every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Bougainvillea have?

According to GharKundli's check of MahaRERA records (updated October 2026), Bougainvillea has one building filed: Bougainviella with 15 floors and 35 units.

What are the flat sizes (carpet area) in Bougainvillea?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Bougainvillea: Other: 934 to 1210 sq ft carpet (22 homes); 3 BHK: 1198 sq ft carpet (11 homes); 2 BHK: 620 to 929 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Bougainvillea have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 45 open car parking spaces for Bougainvillea.

How big is the land of Bougainvillea?

According to GharKundli's check of MahaRERA records (updated October 2026), Bougainvillea stands on 1,676 sq m of land (about 0.4 acres), with 6,776 sq m of sanctioned built-up area and 240 sq m of recreational open space.

Where can I read reviews of Bougainvillea?

Google Maps has reviews of Bougainvillea written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 12 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Bougainvillea?

Bougainvillea by Richa Realtors Private Ltd. is in Kalina, Mumbai (pincode 400098), near Santacruz East, Chembur, Bandra East, Maharashtra, and is registered on MahaRERA as P51800010842, per GharKundli's check of MahaRERA records.

How many homes are in Bougainvillea?

According to GharKundli's check of MahaRERA records (updated October 2026), Bougainvillea has 35 homes in 1 tower registered on MahaRERA, and 83% of them are sold or booked.

When was Bougainvillea registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Bougainvillea was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Bougainvillea?

No court cases are listed for Bougainvillea on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Bougainvillea?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Richa Realtors Private Ltd..

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Kalina

All 30 projects in Santacruz East (400098) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.