Anand Nagar Phase 1
by Anubhavshri Realty Pvt. Ltd. · Kalina, Raigarh
Possession: Anand Nagar Phase 1 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000005747. Status: Completed. 8 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Anand Nagar Phase 1?
How the possession date of Anand Nagar Phase 1 has moved
30 June 2018
Completion date given when the project was registered
30 June 2019
Extended at the builder's request (MahaRERA application EXT52000000439)
Reason the builder gave MahaRERA:
“An extension of 12 months is requested for this phase. This phase comprises of 5 buildings, two buildings A5 and D1 are already handed over and two other buildings A6 and D2 are 85% complete. The main reason for extension of this phase is f…” Read the full reason
“An extension of 12 months is requested for this phase. This phase comprises of 5 buildings, two buildings A5 and D1 are already handed over and two other buildings A6 and D2 are 85% complete. The main reason for extension of this phase is for the completion of this fifth building knows as C1 due two reasons: 1. In this project we are the land owners and had earlier appointed a developer M/s. Adhikari & Associates. The earlier developers failed in the performance of their contract and hence we had to terminate their contract and take over the project in October 2016. We took over the work wi…”31 December 2021
Extended at the builder's request (MahaRERA application EXT52000010520)
Reason the builder gave MahaRERA:
“The project is almost 90-95% complete and the same has got delayed due to pandemic and certain reasons beyond the control of the promoters . The promoters of the project require an extension of time till December 2021 for completion of this…” Read the full reason
“The project is almost 90-95% complete and the same has got delayed due to pandemic and certain reasons beyond the control of the promoters . The promoters of the project require an extension of time till December 2021 for completion of this project . The consent of 51% allotters is herewith submitted under section 7(3)”30 June 2022
Revised completion date on MahaRERA
Source: Anand Nagar Phase 1’s extension records on MahaRERA (P52000005747), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Anand Nagar Phase 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 8 complaints, and how it ended
- Construction pace against the June 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Anand Nagar Phase 2P52000003466 · possession 31 Dec 2018
- Anand Nagar Phase 3P52000007147 · possession 31 Dec 2028
- MahaRERA registration
- P52000005747
- Status
- Completed
- Builder
- Anubhavshri Realty Pvt. Ltd.
- Location
- Kalina, Raigarh · 402104
- Project type
- Residential / Group Housing
- Registered on
- 11 Aug 2017
- Completion date at registration
- June 2018
- Latest completion date
- June 2022
- Delay so far
- 48 months
- Homes
- 110
- Towers
- 5
- Complaints on MahaRERA
- 8
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Anand Nagar Phase 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A-5 | 100% | 100% | 100% | 90% |
| A-6 | 100% | 100% | 100% | 90% |
| D-1 | 100% | 100% | 100% | 90% |
| D-2 | 100% | 100% | 100% | 90% |
| C-1 | 100% | 100% | 100% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Anand Nagar Phase 1 every month.
Anand Nagar Phase 1: buildings, flats and land, as filed on MahaRERA
- Buildings: A-5 (6 floors) · A-6 (6 floors) · D-1 (6 floors) · D-2 (6 floors) · C-1 (6 floors)
- Land: 6,482 sq m (about 1.6 acres) · sanctioned built-up 5,834 sq m · recreational space 648 sq m
- Boundaries filed include: National Highway No 17
The builder’s record and reviews
Anubhavshri Realty (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 48 months); 2 still being built, 2 past the promised date (typically 55 months late); 1 lapsed. 10 complaints on MahaRERA across 2 projects.
Read Google reviews of Anand Nagar Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Anand Nagar Phase 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Anand Nagar Phase 1
What is the possession date of Anand Nagar Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Anand Nagar Phase 1 in Kalina, Raigarh is 30 June 2022 — 48 months later than 30 June 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Anand Nagar Phase 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Anand Nagar Phase 1's builder has filed on MahaRERA, the official one, is 30 June 2022, already 48 months later than the 30 June 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Anand Nagar Phase 1 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Anand Nagar Phase 1's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2019, giving the reason "An extension of 12 months is requested for this phase. This phase comprises of 5 buildings, two buildings A5 and D1 are already handed over and two other buildings A6 and D2 are 85% complete. The main reason for extension of this phase is for the completion of this fifth building knows as C1 due two reasons: 1. In this project we are the land owners and had earlier appointed a developer M/s. Adhikari & Associates. The earlier developers failed in the performance of their contract and hence we had to terminate their contract and take over the project in October 2016. We took over the work wi…"; to 31 December 2021, giving the reason "The project is almost 90-95% complete and the same has got delayed due to pandemic and certain reasons beyond the control of the promoters . The promoters of the project require an extension of time till December 2021 for completion of this project . The consent of 51% allotters is herewith submitted under section 7(3)".
What is the RERA number of Anand Nagar Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Anand Nagar Phase 1 in Kalina, Raigarh is P52000005747.
Is Anand Nagar Phase 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Anand Nagar Phase 1 is registered as P52000005747 and its status is "Completed".
What is the construction status of Anand Nagar Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), Anand Nagar Phase 1's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does Anand Nagar Phase 1 have complaints on MahaRERA?
8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Anand Nagar Phase 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Anand Nagar Phase 1 is registered on MahaRERA as P52000005747, its MahaRERA status is "Completed", its completion date has moved 48 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Anand Nagar Phase 1 have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Anand Nagar Phase 2 (P52000003466, possession 31 Dec 2018); Anand Nagar Phase 3 (P52000007147, possession 31 Dec 2028). Check that your agreement names the registration of your own wing.
How can I get updates if Anand Nagar Phase 1's possession date changes?
The latest dates are on Anand Nagar Phase 1's MahaRERA page (P52000005747). GharKundli's Kundli Watch sends a free WhatsApp update on Anand Nagar Phase 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Anand Nagar Phase 1 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Anand Nagar Phase 1 has 5 buildings filed: A-5 with 6 floors; A-6 with 6 floors; D-1 with 6 floors; D-2 with 6 floors; C-1 with 6 floors.
How big is the land of Anand Nagar Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), Anand Nagar Phase 1 stands on 6,482 sq m of land (about 1.6 acres), with 5,834 sq m of sanctioned built-up area and 648 sq m of recreational open space.
What is the track record of Anand Nagar Phase 1's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Anubhavshri Realty (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 48 months); 2 still being built, 2 past the promised date (typically 55 months late); 1 lapsed. 10 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Anand Nagar Phase 1?
Google Maps has reviews of Anand Nagar Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Anand Nagar Phase 1?
Anand Nagar Phase 1 by Anubhavshri Realty Pvt. Ltd. is in Kalina, Raigarh (pincode 402104), Maharashtra, and is registered on MahaRERA as P52000005747, per GharKundli's check of MahaRERA records. Its boundaries filed there include National Highway No 17.
How many homes are in Anand Nagar Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), Anand Nagar Phase 1 has 110 homes in 5 towers registered on MahaRERA.
When was Anand Nagar Phase 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Anand Nagar Phase 1 was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Anand Nagar Phase 1?
No court cases are listed for Anand Nagar Phase 1 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Anand Nagar Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Anubhavshri Realty Pvt. Ltd., which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Anand Nagar Phase 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kalina
- Green Bay
- Bougainvillea
- Bluemoon Annexe
- UNO
- Anand Nagar Commericial building
- Sunteck Icon, Kolekalyan, CST Road, Kalina, Santacruz East, Mumbai
- INSIGNIA
- Kalpataru Bliss Apartments
Other projects by Anubhavshri Realty Pvt. Ltd.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.