According to GharKundli's check of MahaRERA records, 31 housing projects are registered in pincode 402104 (Mangaon, Raigad). 18 are still being built, 3 with possession due by the end of 2027. For 24, the completion date on MahaRERA is later than the one first promised. 3 have at least one complaint filed on MahaRERA.
Pincode 402104 also covers: Khandad, Utekhol, Kalina, Mangaon SO RaigarhMH, Hodgaon, Kavil Vahal.
“Possession due” is the latest completion date the builder has filed on MahaRERA; “first promised” is the date given at registration. Open a project for its full MahaRERA record.
| Project | MahaRERA status | Possession due (MahaRERA) | First promised | Complaints |
|---|---|---|---|---|
| Farhan Developers Bashir Hasan Kirkire | Active | 30 Apr 2027 | 30 Dec 2026 | 0 |
| VISHWA APARTMENTS RATNMALA RAMESH KHANVILKAR | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| Anand Nagar Commericial building Anubhavshri Realty Pvt. Ltd. | Active | 31 Dec 2027 | 30 Dec 2021 | 0 |
| Riviera JAIRAM NANDKISHOR BHASIN | Active | 30 Jan 2028 | 31 Dec 2025 | 0 |
| GURUDEV APARTMENT RAJESH SAMARTH PRABHU | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| INFINITY ENCLAVE INFINITY BUILDCON | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| Patel Heritage Patel Builders And Developers | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| DONGRE PLAZA SHOEB FARID DONGRE | Active | 31 Jul 2028 | 31 Mar 2028 | 0 |
| VRINDAVAN S P Construction | Active | 18 Oct 2028 | 18 Jun 2028 | 0 |
| Anand Nagar Phase 3 Anubhavshri Realty Pvt. Ltd. | Active | 31 Dec 2028 | 30 Dec 2020 | 2 |
| CHINMAY PLAZA ATMARAM NARAYAN SHINDE | Active | 31 Dec 2028 | 31 Dec 2026 | 0 |
| More Estates MORE ESTATES | Active | 17 Feb 2029 | same | 0 |
| Manohar Apartments B wing Ashvattha Developers | Active | 31 Mar 2029 | same | 0 |
| Galande Complex Santosh Sahadev Galande | Active | 30 Apr 2029 | 30 Mar 2026 | 0 |
| ROYAL SHOPPING CENTRE AFLAH BUILDERS AND DEVELOPERS | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| AAKASH RIVER VIEW AAKASH DEVELOPERS | Active | 31 Dec 2029 | 30 May 2023 | 0 |
| YOGESHWARI GARDEN Shree Yogeshwari Developers Private Limited | Active | 30 Jul 2030 | 30 Mar 2030 | 0 |
| Rising Residency RISING BUILDERS AND DEVELOPERS | Active | 30 Apr 2031 | 31 Dec 2030 | 0 |
| Anand Nagar Phase 1 Anubhavshri Realty Pvt. Ltd. | Completed | 30 Jun 2022 | 30 Jun 2018 | 8 |
| KONDVILKAR HEIGHTS Shree Yogeshwari Developers Private Limited | Completed | 30 Jun 2022 | 30 Dec 2020 | 0 |
| RISING COMPLEX RISING BUILDERS AND DEVELOPERS | Completed | 30 Sep 2022 | 23 Nov 2021 | 0 |
| Mahalaxmi Nivara MAHALAXMI BUILDTECH LLP | Completed | 30 Jun 2023 | 30 Jun 2021 | 0 |
| Trimurti Apartment Pradip Gauru More | Completed | 30 Dec 2023 | same | 0 |
| VAKRATUNDA RESIDENCY GREENFIELD DEVELOPERS | Completed | 23 Jun 2024 | 24 Jun 2023 | 0 |
| MANOHAR APARTMENT AMEYA SHRIKANT BHAVE | Completed | 31 Mar 2025 | 31 Mar 2024 | 0 |
| The Landmark Patel Builders And Developers | Completed | 31 Oct 2025 | same | 0 |
| ROYAL PALACE SUNIL MAHADEV PUSALKAR | Lapsed | 14 Oct 2019passed | same | 0 |
| Malhar Residency Radheshyam Estate and Developers Private Limited | Lapsed | 30 Dec 2022passed | 31 Dec 2019 | 1 |
| SHRUTI SHUBHAM TECHNO ASSOCIATE BUILDER AND DEVELOPERS | Lapsed | 30 Dec 2022passed | same | 0 |
| MANSAROVAR UMA DEVELOPERS | Lapsed | 30 Dec 2025passed | 30 Dec 2024 | 0 |
| SAHJEEVAN SAHAKARI GRUHNIRMAN SANSTHA LTD WANGRE BUILDERS AND DEVELOPERS PRIVATE LIMITED | Lapsed | 31 Dec 2025passed | same | 0 |
Other areas in Raigad
- Panvel · 2,293
- Neral · 291
- Taloja · 273
- Karjat · 260
- Shilphata · 168
- Dronagiri · 167
- Kharghar · 157
- Pen · 110
- Panvel · 101
- Alibag · 94
- Mahad · 74
- Kalamboli · 67
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records. Projects are grouped by the pincode filed on MahaRERA.