Possession date of Galande Complex: 30 April 2029, moved from 30 March 2026 (33 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000025291, and currently active. Its completion date has moved from March 2026 to April 2029: 33 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Galande Complex?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Galande Complex has moved

  1. 30 March 2026

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EA16022619844)

    Reason the builder gave MahaRERA:
    “1. Project stands at 70% completion. 2. The consent of 66.67% of allottees has been uploaded in support of this extension application. 2. Form B uploaded. 3. PERT for the remaining completion work is uploaded in the Application. 4. The Proj…” Read the full reason“1. Project stands at 70% completion. 2. The consent of 66.67% of allottees has been uploaded in support of this extension application. 2. Form B uploaded. 3. PERT for the remaining completion work is uploaded in the Application. 4. The Project got delayed due to following reasons: a. COVID-19 Impact (2020–2022): The pandemic significantly disrupted construction due to lockdowns, labor shortages, and supply chain issues, causing unavoidable delays. b. Plan Modification (2022): The sanctioned plan was modified and approved in 2022, allowing construction to begin in 2023. 5. The revised date o…”
  3. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Galande Complex’s extension records on MahaRERA (P52000025291), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Galande Complex

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000025291
Status
Registered and active
Builder
Santosh Sahadev Galande
Location
New Panchayat Samiti, Raigarh · 402104
Project type
Residential / Group Housing
Registered on
5 Apr 2020
Completion date at registration
March 2026
Latest completion date
April 2029
Delay so far
33 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
31
Sold or booked
11%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Galande Complex, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Galande Complex100%100%50%0%

Commencement certificate (CC), as filed on MahaRERA

  • Galande Complex: covers 4 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Galande Complex every month.

Galande Complex: buildings, flats and land, as filed on MahaRERA

  • Buildings: Galande Complex (5 floors, 36 units)
  • Land: 1,000 sq m (about 0.2 acres) · sanctioned built-up 953 sq m
  • Boundaries filed include: Nagarpanchayat Road

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Galande Complex →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Galande Complex: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Galande Complex

What is the possession date of Galande Complex?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Galande Complex in New Panchayat Samiti, Raigarh is 30 April 2029 — 33 months later than 30 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Galande Complex?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Galande Complex's builder has filed on MahaRERA, the official one, is 30 April 2029, already 33 months later than the 30 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Galande Complex extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Galande Complex's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "1. Project stands at 70% completion. 2. The consent of 66.67% of allottees has been uploaded in support of this extension application. 2. Form B uploaded. 3. PERT for the remaining completion work is uploaded in the Application. 4. The Project got delayed due to following reasons: a. COVID-19 Impact (2020–2022): The pandemic significantly disrupted construction due to lockdowns, labor shortages, and supply chain issues, causing unavoidable delays. b. Plan Modification (2022): The sanctioned plan was modified and approved in 2022, allowing construction to begin in 2023. 5. The revised date o…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Galande Complex?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Galande Complex in New Panchayat Samiti, Raigarh is P52000025291.

Is Galande Complex registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Galande Complex is registered as P52000025291 and its status is "Registered and active".

What is the construction status of Galande Complex?

According to GharKundli's check of MahaRERA records (updated October 2026), Galande Complex's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Galande Complex is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does Galande Complex have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Galande Complex safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Galande Complex is registered on MahaRERA as P52000025291, its completion date has moved 33 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Galande Complex's possession date changes?

The latest dates are on Galande Complex's MahaRERA page (P52000025291). GharKundli's Kundli Watch sends a free WhatsApp update on Galande Complex every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Galande Complex have?

According to GharKundli's check of MahaRERA records (updated October 2026), Galande Complex has one building filed: Galande Complex with 5 floors and 36 units.

How big is the land of Galande Complex?

According to GharKundli's check of MahaRERA records (updated October 2026), Galande Complex stands on 1,000 sq m of land (about 0.2 acres), with 953 sq m of sanctioned built-up area.

Where can I read reviews of Galande Complex?

Google Maps has reviews of Galande Complex written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Galande Complex?

Galande Complex by Santosh Sahadev Galande is in New Panchayat Samiti, Raigarh (pincode 402104), Maharashtra, and is registered on MahaRERA as P52000025291, per GharKundli's check of MahaRERA records. Its boundaries filed there include Nagarpanchayat Road.

How many homes are in Galande Complex?

According to GharKundli's check of MahaRERA records (updated October 2026), Galande Complex has 31 homes in 1 tower registered on MahaRERA, and 11% of them are sold or booked.

When was Galande Complex registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Galande Complex was registered on MahaRERA on 5 April 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on Galande Complex?

No court cases are listed for Galande Complex on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Galande Complex?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Santosh Sahadev Galande.

All projects with possession due in 2029 in Raigad →

Other projects in Mangaon

All 34 projects in Mangaon (402104) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.