CHINMAY PLAZA

by ATMARAM NARAYAN SHINDE · Village Bhadav, Raigarh

Possession date of CHINMAY PLAZA: 31 December 2028, moved from 31 December 2026 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000056422, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about CHINMAY PLAZA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of CHINMAY PLAZA has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    Extended at the builder's request

  3. 31 December 2028

    Extended at the builder's request (MahaRERA application EA10092622508)

    Reason the builder gave MahaRERA: “1) Poor booking response from customer. 2) Because of poor response our work was very slow.”

Source: CHINMAY PLAZA’s extension records on MahaRERA (P52000056422), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on CHINMAY PLAZA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000056422
Status
Registered and active
Builder
ATMARAM NARAYAN SHINDE
Location
Village Bhadav, Raigarh · 402104
Project type
Residential / Group Housing
Registered on
31 May 2024
Completion date at registration
December 2026
Latest completion date
December 2028
Delay so far
24 months
Homes
70
Sold or booked
19%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of CHINMAY PLAZA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
CHINMAY PLAZA100%80%35%0%

Commencement certificate (CC), as filed on MahaRERA

  • CHINMAY PLAZA: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on CHINMAY PLAZA every month.

CHINMAY PLAZA: buildings, flats and land, as filed on MahaRERA

  • Buildings: CHINMAY PLAZA (8 floors, 85 units)
  • Car parking: 14 covered
  • Land: 1,720 sq m (about 0.4 acres) · sanctioned built-up 3,884 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of CHINMAY PLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

CHINMAY PLAZA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about CHINMAY PLAZA

What is the possession date of CHINMAY PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for CHINMAY PLAZA in Village Bhadav, Raigarh is 31 December 2028 — 24 months later than 31 December 2026, the date given at registration.

Is the builder's possession date different from the MahaRERA date for CHINMAY PLAZA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date CHINMAY PLAZA's builder has filed on MahaRERA, the official one, is 31 December 2028, already 24 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of CHINMAY PLAZA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), CHINMAY PLAZA's builder applied to MahaRERA to extend the completion date 2 times: to 30 April 2027; to 31 December 2028, giving the reason "1) Poor booking response from customer. 2) Because of poor response our work was very slow.".

What is the RERA number of CHINMAY PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of CHINMAY PLAZA in Village Bhadav, Raigarh is P52000056422.

Is CHINMAY PLAZA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), CHINMAY PLAZA is registered as P52000056422 and its status is "Registered and active".

What is the construction status of CHINMAY PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), CHINMAY PLAZA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on CHINMAY PLAZA is 80% done and internal work 35%. GharKundli's full report compares construction progress with the deadline.

Does CHINMAY PLAZA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is CHINMAY PLAZA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), CHINMAY PLAZA is registered on MahaRERA as P52000056422, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if CHINMAY PLAZA's possession date changes?

The latest dates are on CHINMAY PLAZA's MahaRERA page (P52000056422). GharKundli's Kundli Watch sends a free WhatsApp update on CHINMAY PLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does CHINMAY PLAZA have?

According to GharKundli's check of MahaRERA records (updated October 2026), CHINMAY PLAZA has one building filed: CHINMAY PLAZA with 8 floors and 85 units.

How much parking does CHINMAY PLAZA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 14 covered car parking spaces for CHINMAY PLAZA.

How big is the land of CHINMAY PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), CHINMAY PLAZA stands on 1,720 sq m of land (about 0.4 acres), with 3,884 sq m of sanctioned built-up area.

Where can I read reviews of CHINMAY PLAZA?

Google Maps has reviews of CHINMAY PLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is CHINMAY PLAZA?

CHINMAY PLAZA by ATMARAM NARAYAN SHINDE is in Village Bhadav, Raigarh (pincode 402104), Maharashtra, and is registered on MahaRERA as P52000056422, per GharKundli's check of MahaRERA records.

How many homes are in CHINMAY PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), CHINMAY PLAZA has 70 homes in 1 tower registered on MahaRERA, and 19% of them are sold or booked.

When was CHINMAY PLAZA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), CHINMAY PLAZA was registered on MahaRERA on 31 May 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on CHINMAY PLAZA?

No court cases are listed for CHINMAY PLAZA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of CHINMAY PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ATMARAM NARAYAN SHINDE.

All projects with possession due in 2028 in Raigad →

Other projects in Mangaon

All 34 projects in Mangaon (402104) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.