Possession date of GAURAV LEGEND: 30 October 2026, moved from 30 December 2023 (30 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800010967, and currently active. Its completion date has moved from December 2023 to October 2026: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 35 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about GAURAV LEGEND?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GAURAV LEGEND has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EXT51800027513)

    Reason the builder gave MahaRERA:
    “1.The promoter has suffered from financial difficulties due to adverse economic condition in the Indian Real Estate Market. 2. Approvals/Permissions from the planning authority (i.e Slum Rehabilitation Authority) were delayed due to which w…” Read the full reason“1.The promoter has suffered from financial difficulties due to adverse economic condition in the Indian Real Estate Market. 2. Approvals/Permissions from the planning authority (i.e Slum Rehabilitation Authority) were delayed due to which we could not proceed with the construction work timely. Revised CC for construction above plinth was then received on 27th June 2022. 3. The promoter has suffered adverse climatic condition at the construction site due to heavy rains of Mumbai coastal causing water logging for weeks at the site.”
  3. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: GAURAV LEGEND’s extension records on MahaRERA (P51800010967), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GAURAV LEGEND

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 35 complaints, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800010967
Status
Registered and active
Builder
Monarch and Querish Builders
Location
Andheri West, Mumbai · 400053
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
December 2023
Latest completion date
October 2026
Delay so far
30 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
65
Sold or booked
98%
Towers
2
Complaints on MahaRERA
35
Court cases listed
0
Appeals at the tribunal
2
Title report on file
Not found

Construction progress of GAURAV LEGEND, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A100%50.5%0.6%0%
WING B100%50.5%0.38%0%

Commencement certificate (CC), as filed on MahaRERA

  • WING A: covers 19 floors
  • WING B: covers 19 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GAURAV LEGEND every month.

GAURAV LEGEND: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Unspecified—198
1 BHK294 – 38342
2 BHK383 – 50423

The builder’s record and reviews

Ravi Developments (a group of 9 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 4 finished, all within the promised date; 15 still being built, 8 past the promised date (typically 22 months late); 5 lapsed. 181 complaints on MahaRERA across 14 projects.

Read Google reviews of GAURAV LEGEND →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GAURAV LEGEND: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GAURAV LEGEND

What is the possession date of GAURAV LEGEND?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GAURAV LEGEND in Andheri West, Mumbai is 30 October 2026 — 30 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for GAURAV LEGEND?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GAURAV LEGEND's builder has filed on MahaRERA, the official one, is 30 October 2026, already 30 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GAURAV LEGEND extended?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV LEGEND's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "1.The promoter has suffered from financial difficulties due to adverse economic condition in the Indian Real Estate Market. 2. Approvals/Permissions from the planning authority (i.e Slum Rehabilitation Authority) were delayed due to which we could not proceed with the construction work timely. Revised CC for construction above plinth was then received on 27th June 2022. 3. The promoter has suffered adverse climatic condition at the construction site due to heavy rains of Mumbai coastal causing water logging for weeks at the site.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of GAURAV LEGEND?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GAURAV LEGEND in Andheri West, Mumbai is P51800010967.

Is GAURAV LEGEND registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV LEGEND is registered as P51800010967 and its status is "Registered and active".

What is the construction status of GAURAV LEGEND?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV LEGEND's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 50.5% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does GAURAV LEGEND have complaints on MahaRERA?

35 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is GAURAV LEGEND safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV LEGEND is registered on MahaRERA as P51800010967, its completion date has moved 30 months since registration and 35 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GAURAV LEGEND's possession date changes?

The latest dates are on GAURAV LEGEND's MahaRERA page (P51800010967). GharKundli's Kundli Watch sends a free WhatsApp update on GAURAV LEGEND every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GAURAV LEGEND have?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV LEGEND has 2 buildings filed: WING A with 21 floors; WING B with 21 floors and 65 units.

What are the flat sizes (carpet area) in GAURAV LEGEND?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for GAURAV LEGEND: 1 BHK: 294 to 383 sq ft carpet (42 homes); 2 BHK: 383 to 504 sq ft carpet (23 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of GAURAV LEGEND?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV LEGEND stands on 620 sq m of land (about 0.2 acres), with 5,954 sq m of sanctioned built-up area.

What is the track record of GAURAV LEGEND's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ravi Developments (a group of 9 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 4 finished, all within the promised date; 15 still being built, 8 past the promised date (typically 22 months late); 5 lapsed. 181 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of GAURAV LEGEND?

Google Maps has reviews of GAURAV LEGEND written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 35 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GAURAV LEGEND?

GAURAV LEGEND by Monarch and Querish Builders (Ravi) is in Andheri West, Mumbai (pincode 400053), near Andheri East, Marol, J.B. Nagar, Maharashtra, and is registered on MahaRERA as P51800010967, per GharKundli's check of MahaRERA records.

How many homes are in GAURAV LEGEND?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV LEGEND has 65 homes in 2 towers registered on MahaRERA, and 98% of them are sold or booked.

When was GAURAV LEGEND registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV LEGEND was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on GAURAV LEGEND?

No court cases are listed for GAURAV LEGEND on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of GAURAV LEGEND?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Monarch and Querish Builders, the company Ravi files this project under.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400053

All 161 projects in Andheri West (400053) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.