Skip to content
GharKundli

SHAMBHAV DARSHAN

by AAVISHKAR ENTERPRISES · Borivali East, MumbaiAlso near Borivali West, Mandapeshwar, Dahisar

Possession date of SHAMBHAV DARSHAN: 31 December 2026, moved from 30 December 2020 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800009321, and currently active. MahaRERA has issued a regulatory order on this project. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHAMBHAV DARSHAN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHAMBHAV DARSHAN has moved

  1. 30 December 2020

    Completion date given when the project was registered

  2. 30 December 2021

    Extended at the builder's request (MahaRERA application EXT51800008831)

    Reason the builder gave MahaRERA: “Due to pandemic Covid-19, work of the project has stopped and discontinued.Further work will start as lock down gets over and worker and contractor are able to commute and visit the site.”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800017131)

    Reason the builder gave MahaRERA:
    “Due to the pandemic Covid-19, the work of the project has stopped and been discontinued. Further work will start as the lockdown gets over and workers and contractors are able to commute and visit the site & Other reasons for the Aviation p…” Read the full reason“Due to the pandemic Covid-19, the work of the project has stopped and been discontinued. Further work will start as the lockdown gets over and workers and contractors are able to commute and visit the site & Other reasons for the Aviation permission and delay of Forest permission.”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EA21062501701)

    Reason the builder gave MahaRERA:
    “1) Even after the Suo-moto extension granted by the Authority after the COVID-19 pandemic, a shortage of skilled labourers and Building Materials for a longer time affected the construction of the project. 2) The application for obtaining N…” Read the full reason“1) Even after the Suo-moto extension granted by the Authority after the COVID-19 pandemic, a shortage of skilled labourers and Building Materials for a longer time affected the construction of the project. 2) The application for obtaining NOC from the Aviation department started from 17/01/2021, NOC received on 23/05/2022, it took one and a half years longer time to receive. 3) As per the concession report, DP remarks dated. 11/10/2022 and the Supreme Court Order dated. 23/09/2022 Project plot is affected forest limit of 100 mtrs. of the Sanjay Gandhi National Park, hence the NOC form ESZ (…”

Source: SHAMBHAV DARSHAN’s extension records on MahaRERA (P51800009321), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHAMBHAV DARSHAN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009321
Status
Registered and active
Builder
AAVISHKAR ENTERPRISES
Location
Borivali East, Mumbai · 400066
Project type
Others
Registered on
22 Aug 2017
Completion date at registration
December 2020
Latest completion date
December 2026
Delay so far
72 months
Homes
20
Sold or booked
88%
Towers
1
Complaints on MahaRERA
4
Court cases listed
0
Appeals at the tribunal
2
MahaRERA regulatory orders
1
Title report on file
Not found

Construction progress of SHAMBHAV DARSHAN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHAMBHAV DARSHAN100%90%85%85%

Commencement certificate (CC), as filed on MahaRERA

  • SHAMBHAV DARSHAN: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHAMBHAV DARSHAN every month.

SHAMBHAV DARSHAN: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK408 – 53213
Shops1,136 – 1,8606
2 BHK532 – 5506
1 Room Kitchen2421
  • Buildings: SHAMBHAV DARSHAN (13 floors, 26 units)
  • Land: 817 sq m (about 0.2 acres) · sanctioned built-up 1,841 sq m
  • Boundaries filed include: MAIN KASTURBA ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHAMBHAV DARSHAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHAMBHAV DARSHAN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHAMBHAV DARSHAN

What is the possession date of SHAMBHAV DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHAMBHAV DARSHAN in Borivali East, Mumbai is 31 December 2026 — 72 months later than 30 December 2020, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SHAMBHAV DARSHAN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHAMBHAV DARSHAN's builder has filed on MahaRERA, the official one, is 31 December 2026, already 72 months later than the 30 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHAMBHAV DARSHAN extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHAMBHAV DARSHAN's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2021, giving the reason "Due to pandemic Covid-19, work of the project has stopped and discontinued.Further work will start as lock down gets over and worker and contractor are able to commute and visit the site."; to 31 December 2024, giving the reason "Due to the pandemic Covid-19, the work of the project has stopped and been discontinued. Further work will start as the lockdown gets over and workers and contractors are able to commute and visit the site & Other reasons for the Aviation permission and delay of Forest permission."; to 31 December 2026, giving the reason "1) Even after the Suo-moto extension granted by the Authority after the COVID-19 pandemic, a shortage of skilled labourers and Building Materials for a longer time affected the construction of the project. 2) The application for obtaining NOC from the Aviation department started from 17/01/2021, NOC received on 23/05/2022, it took one and a half years longer time to receive. 3) As per the concession report, DP remarks dated. 11/10/2022 and the Supreme Court Order dated. 23/09/2022 Project plot is affected forest limit of 100 mtrs. of the Sanjay Gandhi National Park, hence the NOC form ESZ (…".

What is the RERA number of SHAMBHAV DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHAMBHAV DARSHAN in Borivali East, Mumbai is P51800009321.

Is SHAMBHAV DARSHAN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHAMBHAV DARSHAN is registered as P51800009321 and its status is "Registered and active".

What is the construction status of SHAMBHAV DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SHAMBHAV DARSHAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHAMBHAV DARSHAN is 90% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.

Does SHAMBHAV DARSHAN have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SHAMBHAV DARSHAN safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHAMBHAV DARSHAN is registered on MahaRERA as P51800009321, its completion date has moved 72 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHAMBHAV DARSHAN's possession date changes?

The latest dates are on SHAMBHAV DARSHAN's MahaRERA page (P51800009321). GharKundli's Kundli Watch sends a free WhatsApp update on SHAMBHAV DARSHAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHAMBHAV DARSHAN have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHAMBHAV DARSHAN has one building filed: SHAMBHAV DARSHAN with 13 floors and 26 units.

What are the flat sizes (carpet area) in SHAMBHAV DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SHAMBHAV DARSHAN: 1 BHK: 408 to 532 sq ft carpet (13 homes); 2 BHK: 532 to 550 sq ft carpet (6 homes); 1 Room Kitchen: 242 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of SHAMBHAV DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SHAMBHAV DARSHAN stands on 817 sq m of land (about 0.2 acres), with 1,841 sq m of sanctioned built-up area.

Where can I read reviews of SHAMBHAV DARSHAN?

Google Maps has reviews of SHAMBHAV DARSHAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHAMBHAV DARSHAN?

SHAMBHAV DARSHAN by AAVISHKAR ENTERPRISES is in Borivali East, Mumbai (pincode 400066), near Borivali West, Mandapeshwar, Dahisar, Maharashtra, and is registered on MahaRERA as P51800009321, per GharKundli's check of MahaRERA records. Its boundaries filed there include MAIN KASTURBA ROAD.

How many homes are in SHAMBHAV DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SHAMBHAV DARSHAN has 20 homes in 1 tower registered on MahaRERA, and 88% of them are sold or booked.

When was SHAMBHAV DARSHAN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHAMBHAV DARSHAN was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SHAMBHAV DARSHAN?

No court cases are listed for SHAMBHAV DARSHAN on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SHAMBHAV DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AAVISHKAR ENTERPRISES.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400066

All 228 projects in Borivali East (400066) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.