by Ekta Developers · Kurla, Mumbai 400070Also near Parel, Byculla, Kandivali WestRegistered on MahaRERA as “MANRAJ VIEW”
What’s in the report? →Possession date of Ekta Manraj View (MahaRERA P51800011821): 30 September 2026, moved from 30 June 2021 (59 months later), and it has already passed. It has 45 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800011821. Status: Lapsed (registration period ended). Its completion date has moved from June 2021 to September 2026: 59 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800011821, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (September 2026) has passed.
What do you want to know about Ekta Manraj View?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Ekta Manraj View has moved
30 June 2021
Completion date given when the project was registered
30 June 2022
Extended at the builder's request (MahaRERA application EXT51800009378)
Reason the builder gave MahaRERA: “Due to the pandemic”
30 December 2023
Extended at the builder's request (MahaRERA application EXT51800014000)
Reason the builder gave MahaRERA: “Due to the pandemic”
31 May 2026
Extended at the builder's request (MahaRERA application EXT51800018448)
Reason the builder gave MahaRERA:
“We want to apply for the extension till 31.05.2026 as the project is nearly 70% completed. There was delay due to closure of Main Access Road for nearly 2 Years by MCGM for construction of Road Over Bridge which affected the Supply of Mater…” Read the full reason
“We want to apply for the extension till 31.05.2026 as the project is nearly 70% completed. There was delay due to closure of Main Access Road for nearly 2 Years by MCGM for construction of Road Over Bridge which affected the Supply of Material at Site. Presently our work is progressing steadily and is expected to be completed by 31.05.2026. We have not made any allotment of flat till date; hence we are not attaching resolution of the association of allottees.”30 September 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Ekta Manraj View’s extension records on MahaRERA (P51800011821), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Ekta Manraj View
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800011821
- Status
- Lapsed (registration period ended)
- Builder
- Ekta Developers
- Location
- Kurla, Mumbai · 400070
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- September 2026
- Delay so far
- 59 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 45
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of Ekta Manraj View, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MANRAJ VIEW | 100% | 50% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ekta Manraj View every 1–2 months.
Ekta Manraj View: buildings, flats and land, as filed on MahaRERA
- Buildings: MANRAJ VIEW (8 floors)
- Land: 703 sq m (about 0.2 acres) · sanctioned built-up 2,881 sq m
- Land, as filed: 843, 843/1 TO 32
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Rajan Lilaram Nathani HUF (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 still being built, none past the promised date yet; 2 lapsed. No complaints on MahaRERA.
Read Google reviews of Ekta Manraj View →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Ekta Manraj View: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Ekta Manraj View
What is the possession date of Ekta Manraj View?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ekta Manraj View in Kurla, Mumbai is 30 September 2026 — 59 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
The date has already moved 59 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Ekta Manraj View?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Ekta Manraj View's builder has filed on MahaRERA, the official one, is 30 September 2026, already 59 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Ekta Manraj View extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Manraj View's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2022, giving the reason "Due to the pandemic"; to 30 December 2023, giving the reason "Due to the pandemic"; to 31 May 2026, giving the reason "We want to apply for the extension till 31.05.2026 as the project is nearly 70% completed. There was delay due to closure of Main Access Road for nearly 2 Years by MCGM for construction of Road Over Bridge which affected the Supply of Material at Site. Presently our work is progressing steadily and is expected to be completed by 31.05.2026. We have not made any allotment of flat till date; hence we are not attaching resolution of the association of allottees.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Ekta Manraj View?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ekta Manraj View in Kurla, Mumbai is P51800011821.
Is Ekta Manraj View registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Manraj View is registered as P51800011821 and its status is "Lapsed (registration period ended)".
What is the current construction status of Ekta Manraj View? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Manraj View's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MANRAJ VIEW is 50% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Ekta Manraj View have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Ekta Manraj View safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Manraj View is registered on MahaRERA as P51800011821, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 59 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Ekta Manraj View?
Ekta Manraj View isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Ekta Manraj View?
For a flat in Ekta Manraj View (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Ekta Manraj View received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Manraj View isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Ekta Manraj View?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Manraj View's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Ekta Manraj View uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ekta Manraj View was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Ekta Manraj View's possession date changes?
The latest dates are on Ekta Manraj View's MahaRERA page (P51800011821). GharKundli's Kundli Watch sends a free WhatsApp update on Ekta Manraj View every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Ekta Manraj View have?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Manraj View has one building filed: MANRAJ VIEW with 8 floors.
How big is the land of Ekta Manraj View?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Manraj View stands on 703 sq m of land (about 0.2 acres), with 2,881 sq m of sanctioned built-up area.
What is the track record of Ekta Manraj View's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajan Lilaram Nathani HUF (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 still being built, none past the promised date yet; 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Ekta Manraj View?
Google Maps has reviews of Ekta Manraj View written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Ekta Manraj View?
Ekta Manraj View by Ekta Developers is in Kurla, Mumbai, pincode 400070 (near Parel, Byculla, Kandivali West), Maharashtra, and is registered on MahaRERA as P51800011821, per GharKundli's check of MahaRERA records. Its land is filed as 843, 843/1 TO 32. GharKundli lists all 92 MahaRERA projects in Kurla West (400070).
How many flats are in Ekta Manraj View?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Manraj View has 45 homes in 1 tower registered on MahaRERA.
When was Ekta Manraj View registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Manraj View was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Does Ekta Manraj View have any legal issues or court cases?
No court cases are listed for Ekta Manraj View on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Ekta Manraj View?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ekta Developers, which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Ekta Manraj View
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Kurla West (400070)
- Sai Chamunda
- Twin Galaxy
- Deraiya Luxurio
- Jai Shreeram Prasanna CHSL
- Dadamiya’s Man'souza Height
- Kalyan Kutir Co-operative Housing Society Limited
- Taiba Residency
- Anupam Villa CHSL
Other projects by Ekta Developers