Bhagwati Ashish
by Pritesh Damji Savla · Jogeshwari East, MumbaiAlso near Andheri East, Jvlr, Andheri West
Possession: Bhagwati Ashish is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800010515. Status: Completed. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Bhagwati Ashish?
How the possession date of Bhagwati Ashish has moved
15 November 2020
Completion date given when the project was registered
15 May 2021
Extended at the builder's request (MahaRERA application EXT51800008592)
Reason the builder gave MahaRERA: “DUE TO COVID LABOURS ARE NOT AVAILABLE AT SITE FOR LAST 6 MONTHS AND STILL NOT RESUME THE WORK.”
31 May 2022
Extended at the builder's request (MahaRERA application EXT51800009571)
Reason the builder gave MahaRERA: “Due to corona labour again left the city and BMC staff is on Corona work and are not issuing new approvals for further work.”
1 June 2023
Extended at the builder's request (MahaRERA application EXT51800013084)
Reason the builder gave MahaRERA:
“SIR/MAM, The approvals for further construction were received in FEB 2022 and work has been started in full fledge. All RCC work of the project has been completed so far and finishing work completion of the project is in the process. Howeve…” Read the full reason
“SIR/MAM, The approvals for further construction were received in FEB 2022 and work has been started in full fledge. All RCC work of the project has been completed so far and finishing work completion of the project is in the process. However, we shall endeavor completion of project within extended duration of 6 months. We, request your honor to consider our prayer of extending date of completion of project by 6 months i.e. from 01/12/2022 to 01/06/2023.”31 May 2024
Extended at the builder's request (MahaRERA application EXT51800016865)
Reason the builder gave MahaRERA:
“Subject: Extension of 12_months for Project “BHAGWATI ASHISH CHSL” videMahaRERA Project Registration Number P51800010515 under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. Respected Sir/Madam, This is to inform yo…” Read the full reason
“Subject: Extension of 12_months for Project “BHAGWATI ASHISH CHSL” videMahaRERA Project Registration Number P51800010515 under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. Respected Sir/Madam, This is to inform you that the project “BHAGWATI ASHISH CHSL” developed by M/s. Vini Developers has been granted registration under MahaRERA vide registration no.P51800010515 dated 31.08.2017. The said registration is valid till 01.06.2023. We submit that we have received approvals for further construction in February 2022. Accordingly, we have completed all RCC work includi…”
Source: Bhagwati Ashish’s extension records on MahaRERA (P51800010515), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Bhagwati Ashish
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints and 1 court case, and how it ended
- Construction pace against the May 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800010515
- Status
- Completed
- Builder
- Pritesh Damji Savla
- Location
- Jogeshwari East, Mumbai · 400060
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- November 2020
- Latest completion date
- May 2024
- Delay so far
- 42 months
- Homes
- 28
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 1
- Appeals at the tribunal
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Bhagwati Ashish, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Bhagwati Ashish CHSL | 100% | 100% | 95% | 95% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bhagwati Ashish every month.
Bhagwati Ashish: buildings, flats and land, as filed on MahaRERA
- Buildings: Bhagwati Ashish CHSL (13 floors)
- Land: 1,101 sq m (about 0.3 acres) · sanctioned built-up 1,370 sq m · recreational space 1,101 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Pritesh Damji Savla has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 61 months). 3 complaints on MahaRERA across 2 projects.
Read Google reviews of Bhagwati Ashish →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Bhagwati Ashish: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Bhagwati Ashish
What is the possession date of Bhagwati Ashish?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Bhagwati Ashish in Jogeshwari East, Mumbai is 31 May 2024 — 42 months later than 15 November 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Bhagwati Ashish?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Bhagwati Ashish's builder has filed on MahaRERA, the official one, is 31 May 2024, already 42 months later than the 15 November 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Bhagwati Ashish extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhagwati Ashish's builder applied to MahaRERA to extend the completion date 4 times: to 15 May 2021, giving the reason "DUE TO COVID LABOURS ARE NOT AVAILABLE AT SITE FOR LAST 6 MONTHS AND STILL NOT RESUME THE WORK."; to 31 May 2022, giving the reason "Due to corona labour again left the city and BMC staff is on Corona work and are not issuing new approvals for further work."; to 1 June 2023, giving the reason "SIR/MAM, The approvals for further construction were received in FEB 2022 and work has been started in full fledge. All RCC work of the project has been completed so far and finishing work completion of the project is in the process. However, we shall endeavor completion of project within extended duration of 6 months. We, request your honor to consider our prayer of extending date of completion of project by 6 months i.e. from 01/12/2022 to 01/06/2023."; to 31 May 2024, giving the reason "Subject: Extension of 12_months for Project “BHAGWATI ASHISH CHSL” videMahaRERA Project Registration Number P51800010515 under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. Respected Sir/Madam, This is to inform you that the project “BHAGWATI ASHISH CHSL” developed by M/s. Vini Developers has been granted registration under MahaRERA vide registration no.P51800010515 dated 31.08.2017. The said registration is valid till 01.06.2023. We submit that we have received approvals for further construction in February 2022. Accordingly, we have completed all RCC work includi…".
What is the RERA number of Bhagwati Ashish?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Bhagwati Ashish in Jogeshwari East, Mumbai is P51800010515.
Is Bhagwati Ashish registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhagwati Ashish is registered as P51800010515 and its status is "Completed".
What is the construction status of Bhagwati Ashish?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhagwati Ashish's status on MahaRERA is "Completed". As filed by the builder, slab work on Bhagwati Ashish CHSL is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Bhagwati Ashish have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Bhagwati Ashish safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhagwati Ashish is registered on MahaRERA as P51800010515, its MahaRERA status is "Completed", its completion date has moved 42 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Bhagwati Ashish's possession date changes?
The latest dates are on Bhagwati Ashish's MahaRERA page (P51800010515). GharKundli's Kundli Watch sends a free WhatsApp update on Bhagwati Ashish every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Bhagwati Ashish have?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhagwati Ashish has one building filed: Bhagwati Ashish CHSL with 13 floors.
How big is the land of Bhagwati Ashish?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhagwati Ashish stands on 1,101 sq m of land (about 0.3 acres), with 1,370 sq m of sanctioned built-up area and 1,101 sq m of recreational open space.
What is the track record of Bhagwati Ashish's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Pritesh Damji Savla has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 61 months). 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Bhagwati Ashish?
Google Maps has reviews of Bhagwati Ashish written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Bhagwati Ashish?
Bhagwati Ashish by Pritesh Damji Savla is in Jogeshwari East, Mumbai (pincode 400060), near Andheri East, Jvlr, Andheri West, Maharashtra, and is registered on MahaRERA as P51800010515, per GharKundli's check of MahaRERA records.
How many homes are in Bhagwati Ashish?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhagwati Ashish has 28 homes in 1 tower registered on MahaRERA.
When was Bhagwati Ashish registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhagwati Ashish was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Bhagwati Ashish?
1 court case is listed for Bhagwati Ashish on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Bhagwati Ashish?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Pritesh Damji Savla, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Bhagwati Ashish
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400060
- SHIVSOLITAIRE
- BHAWANI HEIGHTS
- Vraj Bhumi Heights
- SHIVKUNJ
- AVANT HERITAGE - III
- SHRADDHA WEST RESIDENCY
- ROSE BLOSSOM CHSL
- DATTARAM TOWER
Other projects by Pritesh Damji Savla
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.