by HEKS INFRASTRUCTURE & DEVELOPERS (Rubberwala) · Parel, MumbaiAlso near Ramnagar, Lalbaug, Sion

Possession date of VALENCIA: 30 November 2026, moved from 31 July 2018 (96 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900006034, and currently active. Its completion date has moved from July 2018 to November 2026: 96 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about VALENCIA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VALENCIA has moved

  1. 31 July 2018

    Completion date given when the project was registered

  2. 31 January 2024

    Extended at the builder's request (MahaRERA application EXT51900011319)

    Reason the builder gave MahaRERA:
    “n accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-…” Read the full reason“n accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 78.95% allottees for purpose of extension of RERA registration period of the said project.”
  3. 30 July 2025

    Extended at the builder's request (MahaRERA application EXT51900025246)

    Reason the builder gave MahaRERA: “We are unable to complete the Project on time due to some financial crises but we are trying to close asap with all the formalities & compliance. Its a humble requested to grant for Extension upto 30.7.2025.”
  4. 31 July 2026

    Extended at the builder's request (MahaRERA application EA13082502370)

    Reason the builder gave MahaRERA:
    “The Project is nearing completion. We anticipate wrapping up the primary tasks very soon.To ensure the full and proper utilization of the remaining FSI. we kindly request a one-year extension. This additional time will allow us to make furt…” Read the full reason“The Project is nearing completion. We anticipate wrapping up the primary tasks very soon.To ensure the full and proper utilization of the remaining FSI. we kindly request a one-year extension. This additional time will allow us to make further necessary amendments and consume the balance FSI effectively.”
  5. 30 November 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: VALENCIA’s extension records on MahaRERA (P51900006034), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VALENCIA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the November 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900006034
Status
Registered and active
Builder
HEKS INFRASTRUCTURE & DEVELOPERS
Location
Parel, Mumbai · 400012
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
July 2018
Latest completion date
November 2026
Delay so far
96 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
23
Sold or booked
88%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of VALENCIA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VALENCIA100%92%95%100%

Commencement certificate (CC), as filed on MahaRERA

  • VALENCIA: covers 20 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VALENCIA every month.

VALENCIA: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK300 – 39119
2 BHK5074
Office Space2,3231
  • Buildings: VALENCIA (22 floors, 24 units)
  • Land: 463 sq m (about 0.1 acres) · sanctioned built-up 2,910 sq m
  • Boundaries filed include: DR BATLIWALA ROAD, DR BATLIWALA CROSS ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Rubberwala Housing & Infrastructure (a group of 10 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 61 months); 7 still being built, 3 past the promised date (typically 30 months late); 1 lapsed. 13 complaints on MahaRERA across 2 projects.

Read Google reviews of VALENCIA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VALENCIA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VALENCIA

What is the possession date of VALENCIA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VALENCIA in Parel, Mumbai is 30 November 2026 — 96 months later than 31 July 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for VALENCIA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VALENCIA's builder has filed on MahaRERA, the official one, is 30 November 2026, already 96 months later than the 31 July 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VALENCIA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), VALENCIA's builder applied to MahaRERA to extend the completion date 3 times: to 31 January 2024, giving the reason "n accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 78.95% allottees for purpose of extension of RERA registration period of the said project."; to 30 July 2025, giving the reason "We are unable to complete the Project on time due to some financial crises but we are trying to close asap with all the formalities & compliance. Its a humble requested to grant for Extension upto 30.7.2025."; to 31 July 2026, giving the reason "The Project is nearing completion. We anticipate wrapping up the primary tasks very soon.To ensure the full and proper utilization of the remaining FSI. we kindly request a one-year extension. This additional time will allow us to make further necessary amendments and consume the balance FSI effectively.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of VALENCIA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VALENCIA in Parel, Mumbai is P51900006034.

Is VALENCIA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VALENCIA is registered as P51900006034 and its status is "Registered and active".

What is the construction status of VALENCIA?

According to GharKundli's check of MahaRERA records (updated October 2026), VALENCIA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VALENCIA is 92% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does VALENCIA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is VALENCIA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), VALENCIA is registered on MahaRERA as P51900006034, its completion date has moved 96 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VALENCIA's possession date changes?

The latest dates are on VALENCIA's MahaRERA page (P51900006034). GharKundli's Kundli Watch sends a free WhatsApp update on VALENCIA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VALENCIA have?

According to GharKundli's check of MahaRERA records (updated October 2026), VALENCIA has one building filed: VALENCIA with 22 floors and 24 units.

What are the flat sizes (carpet area) in VALENCIA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for VALENCIA: 1 BHK: 300 to 391 sq ft carpet (19 homes); 2 BHK: 507 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of VALENCIA?

According to GharKundli's check of MahaRERA records (updated October 2026), VALENCIA stands on 463 sq m of land (about 0.1 acres), with 2,910 sq m of sanctioned built-up area.

What is the track record of VALENCIA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Rubberwala Housing & Infrastructure (a group of 10 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 61 months); 7 still being built, 3 past the promised date (typically 30 months late); 1 lapsed. 13 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of VALENCIA?

Google Maps has reviews of VALENCIA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VALENCIA?

VALENCIA by HEKS INFRASTRUCTURE & DEVELOPERS (Rubberwala) is in Parel, Mumbai (pincode 400012), near Ramnagar, Lalbaug, Sion, Maharashtra, and is registered on MahaRERA as P51900006034, per GharKundli's check of MahaRERA records. Its boundaries filed there include DR BATLIWALA ROAD, DR BATLIWALA CROSS ROAD.

How many homes are in VALENCIA?

According to GharKundli's check of MahaRERA records (updated October 2026), VALENCIA has 23 homes in 1 tower registered on MahaRERA, and 88% of them are sold or booked.

When was VALENCIA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VALENCIA was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on VALENCIA?

No court cases are listed for VALENCIA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of VALENCIA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HEKS INFRASTRUCTURE & DEVELOPERS, the company Rubberwala files this project under.

All projects with possession due in 2026 in Mumbai City →

Other projects in pincode 400012

All 65 projects in Parel (400012) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.