by ZOEB ENTERPRISES · Parel, MumbaiAlso near Dadar, Kalanagar, Bandra East, Ramnagar

Possession date of AAYESHA PALACE: 31 December 2027, moved from 30 December 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900023852, and currently active. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AAYESHA PALACE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AAYESHA PALACE has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51900018767)

    Reason the builder gave MahaRERA: “Project CC for Approved number of Floors from 17th to 22nd on 13-11-2022. Therefore, the time for Constructing the additional 5 Floors is taking time. There is delay on part of MCGM to issue CC on time.”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51900027276)

    Reason the builder gave MahaRERA:
    “Dear Sir/Ma’am, I, Mr. Mohammed Alam Abdul Majid Ansari, hereby declare the following with respect to the project “AAYESHA PALACE” bearing registration number P51900023852 registered under MahaRERA 1. Status of Work Completed: We are please…” Read the full reason“Dear Sir/Ma’am, I, Mr. Mohammed Alam Abdul Majid Ansari, hereby declare the following with respect to the project “AAYESHA PALACE” bearing registration number P51900023852 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the full RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applyi…”
  4. 31 December 2027

    Extended at the builder's request (MahaRERA application EA24022619992)

    Reason the builder gave MahaRERA:
    “Dear Sir/Ma’am, I, Mr. Mohammed Alam Abdul Majid Ansari, hereby declare the following with respect to the project “AAYESHA PALACE” bearing registration number P51900023852 registered under MahaRERA 1. Status of Work Completed: We are please…” Read the full reason“Dear Sir/Ma’am, I, Mr. Mohammed Alam Abdul Majid Ansari, hereby declare the following with respect to the project “AAYESHA PALACE” bearing registration number P51900023852 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applyi…”

Source: AAYESHA PALACE’s extension records on MahaRERA (P51900023852), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AAYESHA PALACE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900023852
Status
Registered and active
Builder
ZOEB ENTERPRISES
Location
Parel, Mumbai · 400012
Project type
Residential / Group Housing
Registered on
7 Jan 2020
Completion date at registration
December 2023
Latest completion date
December 2027
Delay so far
48 months
Homes
162
Sold or booked
16%
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of AAYESHA PALACE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AAYESHA PALACE100%100%100%95%

Commencement certificate (CC), as filed on MahaRERA

  • AAYESHA PALACE: covers 23 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AAYESHA PALACE every month.

AAYESHA PALACE: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK361 – 384162

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of AAYESHA PALACE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AAYESHA PALACE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AAYESHA PALACE

What is the possession date of AAYESHA PALACE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AAYESHA PALACE in Parel, Mumbai is 31 December 2027 — 48 months later than 30 December 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for AAYESHA PALACE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AAYESHA PALACE's builder has filed on MahaRERA, the official one, is 31 December 2027, already 48 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AAYESHA PALACE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AAYESHA PALACE's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "Project CC for Approved number of Floors from 17th to 22nd on 13-11-2022. Therefore, the time for Constructing the additional 5 Floors is taking time. There is delay on part of MCGM to issue CC on time."; to 31 December 2025, giving the reason "Dear Sir/Ma’am, I, Mr. Mohammed Alam Abdul Majid Ansari, hereby declare the following with respect to the project “AAYESHA PALACE” bearing registration number P51900023852 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the full RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applyi…"; to 31 December 2027, giving the reason "Dear Sir/Ma’am, I, Mr. Mohammed Alam Abdul Majid Ansari, hereby declare the following with respect to the project “AAYESHA PALACE” bearing registration number P51900023852 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applyi…".

What is the RERA number of AAYESHA PALACE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AAYESHA PALACE in Parel, Mumbai is P51900023852.

Is AAYESHA PALACE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AAYESHA PALACE is registered as P51900023852 and its status is "Registered and active".

What is the construction status of AAYESHA PALACE?

According to GharKundli's check of MahaRERA records (updated October 2026), AAYESHA PALACE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AAYESHA PALACE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does AAYESHA PALACE have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is AAYESHA PALACE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AAYESHA PALACE is registered on MahaRERA as P51900023852, its completion date has moved 48 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AAYESHA PALACE's possession date changes?

The latest dates are on AAYESHA PALACE's MahaRERA page (P51900023852). GharKundli's Kundli Watch sends a free WhatsApp update on AAYESHA PALACE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AAYESHA PALACE have?

According to GharKundli's check of MahaRERA records (updated October 2026), AAYESHA PALACE has one building filed: AAYESHA PALACE with 23 floors and 162 units.

What are the flat sizes (carpet area) in AAYESHA PALACE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for AAYESHA PALACE: 1 BHK: 361 to 384 sq ft carpet (162 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of AAYESHA PALACE?

According to GharKundli's check of MahaRERA records (updated October 2026), AAYESHA PALACE stands on 769 sq m of land (about 0.2 acres), with 5,866 sq m of sanctioned built-up area.

Where can I read reviews of AAYESHA PALACE?

Google Maps has reviews of AAYESHA PALACE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AAYESHA PALACE?

AAYESHA PALACE by ZOEB ENTERPRISES is in Parel, Mumbai (pincode 400012), near Dadar, Kalanagar, Bandra East, Ramnagar, Maharashtra, and is registered on MahaRERA as P51900023852, per GharKundli's check of MahaRERA records. Its boundaries filed there include PARSI COLONY.

How many homes are in AAYESHA PALACE?

According to GharKundli's check of MahaRERA records (updated October 2026), AAYESHA PALACE has 162 homes in 1 tower registered on MahaRERA, and 16% of them are sold or booked.

When was AAYESHA PALACE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AAYESHA PALACE was registered on MahaRERA on 7 January 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on AAYESHA PALACE?

No court cases are listed for AAYESHA PALACE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of AAYESHA PALACE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ZOEB ENTERPRISES.

All projects with possession due in 2027 in Mumbai City →

Other projects in pincode 400012

All 65 projects in Parel (400012) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.