Bhavani Plaza
by Padmakar Purushottam Gokarna · Kanjur East, MumbaiAlso near Kanjurmarg, Bhandup West, Vikhroli
Possession date of Bhavani Plaza: 30 October 2027, moved from 31 December 2019 (90 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800011262, and currently active. Its completion date has moved from December 2019 to October 2027: 90 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 10 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Bhavani Plaza?
How the possession date of Bhavani Plaza has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51800003801)
Reason the builder gave MahaRERA:
“We would like to inform you that because of the litigation against the said project Name: Bhavani Plaza, Project registration number: P51800011262 the project has been delayed the details of litigation we have already mentioned while regist…” Read the full reason
“We would like to inform you that because of the litigation against the said project Name: Bhavani Plaza, Project registration number: P51800011262 the project has been delayed the details of litigation we have already mentioned while registering with MahaRERA authority. The project work is 70% completed as on today, we request you to give extension as applicable for this project so we can complete the pending work in due course.”30 June 2022
Extended at the builder's request (MahaRERA application EXT51800010017)
Reason the builder gave MahaRERA:
“Dear Sir, We hereby apply for extension u/s 7(3) of the registered project bearing vide no. P5180011262 do hereby declare that the extended date of completion of above mentioned project was 30th June 2021. We would like to inform you that t…” Read the full reason
“Dear Sir, We hereby apply for extension u/s 7(3) of the registered project bearing vide no. P5180011262 do hereby declare that the extended date of completion of above mentioned project was 30th June 2021. We would like to inform you that the project is 70% completed. We have total 16 apartments in project name Bhavani Plaza and out of that 7 apartments are sold and 9 apartments are unsold which needs to be sell but without the Extension Number we are unable to sell those apartments. Hence we are making this application for Project Extension u/s 7(3). We request you give extension for our p…”30 December 2023
Extended at the builder's request (MahaRERA application EXT51800013603)
Reason the builder gave MahaRERA: “WE ARE TRYING TO APPLY FOR OC REQUESTING YOU TO GRANT EXTENTION TILL 30-12-2023”
30 June 2024
Extended at the builder's request (MahaRERA application EXT51800018327)
Reason the builder gave MahaRERA: “Due to an issue with the landowner, the project was not able to be completed in time. we are therefore requesting to please grant us the extension till 30.06.2024”
31 March 2025
Extended at the builder's request (MahaRERA application EXT51800024107)
Reason the builder gave MahaRERA: “The project work is completed, we are applying for the extension because we are applying for the occupancy certificate. Kindly grant us the extension so we can complete the project closure formalities.”
30 June 2026
Extended at the builder's request (MahaRERA application EA30072502257)
Reason the builder gave MahaRERA:
“The project has been completed, and we are now applying for the occupancy certificate. Due to issues between the landowner and the allottees, the project was not completed on time. Therefore, we kindly request an extension until June 30, 20…” Read the full reason
“The project has been completed, and we are now applying for the occupancy certificate. Due to issues between the landowner and the allottees, the project was not completed on time. Therefore, we kindly request an extension until June 30, 2026.”30 June 2027
Extended at the builder's request (MahaRERA application EA29062621605)
Reason the builder gave MahaRERA:
“We would like to inform you that we have already applied for the Occupancy Certificate (OC) on for our project. However, the Occupancy Certificate has not yet been received from the competent authority. As the issuance of the OC is currentl…” Read the full reason
“We would like to inform you that we have already applied for the Occupancy Certificate (OC) on for our project. However, the Occupancy Certificate has not yet been received from the competent authority. As the issuance of the OC is currently pending and beyond our control, we are unable to complete the final compliance process within the stipulated project completion date. In view of this, we kindly request to granting an extension of the RERA project validity for the necessary period, until the Occupancy Certificate is received.”30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Bhavani Plaza’s extension records on MahaRERA (P51800011262), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Bhavani Plaza
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 10 complaints and 3 court cases, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800011262
- Status
- Registered and active
- Builder
- Padmakar Purushottam Gokarna
- Location
- Kanjur East, Mumbai · 400078
- Project type
- Mixed
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- October 2027
- Delay so far
- 90 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 40
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 10
- Court cases listed
- 3
- Appeals at the tribunal
- 4
- Title report on file
- Not found
Construction progress of Bhavani Plaza, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BHAVANI PLAZA A WING AND B WING | 100% | 97% | 97% | 97% |
Commencement certificate (CC), as filed on MahaRERA
- BHAVANI PLAZA A WING AND B WING: covers Ground plus 7th Floor Full CC
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bhavani Plaza every month.
Bhavani Plaza: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 324 – 450 | 18 |
| 2 BHK | 453 – 574 | 11 |
| Other | 459 – 461 | 5 |
| 1 Room Kitchen | 262 – 280 | 4 |
| Office Space | 901 | 3 |
| 3 BHK | 574 – 809 | 2 |
- Buildings: BHAVANI PLAZA A WING AND B WING (13 floors, 43 units)
- Land: 851 sq m (about 0.2 acres) · sanctioned built-up 183 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Bhavani Plaza →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Bhavani Plaza: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Bhavani Plaza
What is the possession date of Bhavani Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Bhavani Plaza in Kanjur East, Mumbai is 30 October 2027 — 90 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Bhavani Plaza?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Bhavani Plaza's builder has filed on MahaRERA, the official one, is 30 October 2027, already 90 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Bhavani Plaza extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhavani Plaza's builder applied to MahaRERA to extend the completion date 7 times: to 30 December 2020, giving the reason "We would like to inform you that because of the litigation against the said project Name: Bhavani Plaza, Project registration number: P51800011262 the project has been delayed the details of litigation we have already mentioned while registering with MahaRERA authority. The project work is 70% completed as on today, we request you to give extension as applicable for this project so we can complete the pending work in due course."; to 30 June 2022, giving the reason "Dear Sir, We hereby apply for extension u/s 7(3) of the registered project bearing vide no. P5180011262 do hereby declare that the extended date of completion of above mentioned project was 30th June 2021. We would like to inform you that the project is 70% completed. We have total 16 apartments in project name Bhavani Plaza and out of that 7 apartments are sold and 9 apartments are unsold which needs to be sell but without the Extension Number we are unable to sell those apartments. Hence we are making this application for Project Extension u/s 7(3). We request you give extension for our p…"; to 30 December 2023, giving the reason "WE ARE TRYING TO APPLY FOR OC REQUESTING YOU TO GRANT EXTENTION TILL 30-12-2023"; to 30 June 2024, giving the reason "Due to an issue with the landowner, the project was not able to be completed in time. we are therefore requesting to please grant us the extension till 30.06.2024"; to 31 March 2025, giving the reason "The project work is completed, we are applying for the extension because we are applying for the occupancy certificate. Kindly grant us the extension so we can complete the project closure formalities."; to 30 June 2026, giving the reason "The project has been completed, and we are now applying for the occupancy certificate. Due to issues between the landowner and the allottees, the project was not completed on time. Therefore, we kindly request an extension until June 30, 2026."; to 30 June 2027, giving the reason "We would like to inform you that we have already applied for the Occupancy Certificate (OC) on for our project. However, the Occupancy Certificate has not yet been received from the competent authority. As the issuance of the OC is currently pending and beyond our control, we are unable to complete the final compliance process within the stipulated project completion date. In view of this, we kindly request to granting an extension of the RERA project validity for the necessary period, until the Occupancy Certificate is received.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Bhavani Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Bhavani Plaza in Kanjur East, Mumbai is P51800011262.
Is Bhavani Plaza registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhavani Plaza is registered as P51800011262 and its status is "Registered and active".
What is the construction status of Bhavani Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhavani Plaza's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BHAVANI PLAZA A WING AND B WING is 97% done and internal work 97%. GharKundli's full report compares construction progress with the deadline.
Does Bhavani Plaza have complaints on MahaRERA?
10 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Bhavani Plaza safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhavani Plaza is registered on MahaRERA as P51800011262, its completion date has moved 90 months since registration and 10 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Bhavani Plaza's possession date changes?
The latest dates are on Bhavani Plaza's MahaRERA page (P51800011262). GharKundli's Kundli Watch sends a free WhatsApp update on Bhavani Plaza every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Bhavani Plaza have?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhavani Plaza has one building filed: BHAVANI PLAZA A WING AND B WING with 13 floors and 43 units.
What are the flat sizes (carpet area) in Bhavani Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Bhavani Plaza: 1 BHK: 324 to 450 sq ft carpet (18 homes); 2 BHK: 453 to 574 sq ft carpet (11 homes); Other: 459 to 461 sq ft carpet (5 homes); 1 Room Kitchen: 262 to 280 sq ft carpet (4 homes); 3 BHK: 574 to 809 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Bhavani Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhavani Plaza stands on 851 sq m of land (about 0.2 acres), with 183 sq m of sanctioned built-up area.
Where can I read reviews of Bhavani Plaza?
Google Maps has reviews of Bhavani Plaza written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 10 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Bhavani Plaza?
Bhavani Plaza by Padmakar Purushottam Gokarna is in Kanjur East, Mumbai (pincode 400078), near Kanjurmarg, Bhandup West, Vikhroli, Maharashtra, and is registered on MahaRERA as P51800011262, per GharKundli's check of MahaRERA records.
How many homes are in Bhavani Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhavani Plaza has 40 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Bhavani Plaza registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhavani Plaza was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Bhavani Plaza?
3 court cases are listed for Bhavani Plaza on MahaRERA, and 4 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Bhavani Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Padmakar Purushottam Gokarna.
Check it yourself on MahaRERA
- How to check the possession date of Bhavani Plaza
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Mumbai
- SATYAM CO-OPERATIVE HOUSING SOCIETY LIMITED
- BHAGYAWAN PRIMROSE
- Rite Amor
- Paras Residency
- SHREE
- VISHWA BHUVAN
- BKC 28
- AQUINA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.