ZIA Complex Wing E

by I. R. Construction · Kurla East, Mumbai 400070Also near Nehru Nagar, Kurla West, Chembur

What’s in the report? →

Possession date of ZIA Complex Wing E (MahaRERA P51800013616): 31 December 2025, moved from 30 March 2021 (57 months later), and it has already passed. It has 41 homes (1 BHK, 291–321 sq ft carpet), 98% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800013616. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800013616, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about ZIA Complex Wing E?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of ZIA Complex Wing E has moved

  1. 30 March 2021

    Completion date given when the project was registered

  2. 30 March 2022

    Extended at the builder's request (MahaRERA application EXT51800010311)

    Reason the builder gave MahaRERA:
    “The approvals for additional FSI and upper floors of the sale building Zia Complex wing E could not be obtained due to change in policies for conversion of scheme and subsequent publication of DCPR 2034. The revised LOI under new provisions…” Read the full reason“The approvals for additional FSI and upper floors of the sale building Zia Complex wing E could not be obtained due to change in policies for conversion of scheme and subsequent publication of DCPR 2034. The revised LOI under new provisions is process and will be issued soon enabling us to start work on the remaining floors of the sale building. Request the Hon'ble Authority to grant extension to the registered project.”
  3. 30 September 2023

    Extended at the builder's request (MahaRERA application EXT51800013799)

    Reason the builder gave MahaRERA: “Certain approvals were to be sought from Ministry of Housing, Maharashtra Government which was unexpected and thus it took time for getting the FSI loaded and IOA/CC to be issued by Slum Rehabilitation Authority.”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800024370)

    Reason the builder gave MahaRERA:
    “Sir, The construction work of the project is completed and only minor finishes are remaining. We have also completed the RCC framework of the new religious structure, which will soon be handed over to users. The temporary religious structur…” Read the full reason“Sir, The construction work of the project is completed and only minor finishes are remaining. We have also completed the RCC framework of the new religious structure, which will soon be handed over to users. The temporary religious structure which was an impediment in completing the firefighting work shall be demolished soon and the firefighting work along with the balance site infrastructure shall be completed thereafter. We will need some time to get the Occupation certificate thereafter. We therefore request this Authority to grant an extension to the project as per consent granted by Al…”

Source: ZIA Complex Wing E’s extension records on MahaRERA (P51800013616), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ZIA Complex Wing E

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800013616
Status
Lapsed (registration period ended)
Builder
I. R. Construction
Location
Kurla East, Mumbai · 400070
Project type
Others
Registered on
16 Oct 2017
Completion date at registration
March 2021
Latest completion date
December 2025
Delay so far
57 months
Homes
41
Sold or booked
98%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of ZIA Complex Wing E, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing E100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ZIA Complex Wing E every 1–2 months.

ZIA Complex Wing E: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK291 – 31440
Other3211

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of ZIA Complex Wing E →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ZIA Complex Wing E: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about ZIA Complex Wing E

What is the possession date of ZIA Complex Wing E?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ZIA Complex Wing E in Kurla East, Mumbai is 31 December 2025 — 57 months later than 30 March 2021, the date given at registration. That date has already passed.

The date has already moved 57 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for ZIA Complex Wing E?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ZIA Complex Wing E's builder has filed on MahaRERA, the official one, is 31 December 2025, already 57 months later than the 30 March 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ZIA Complex Wing E extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ZIA Complex Wing E's builder applied to MahaRERA to extend the completion date 3 times: to 30 March 2022, giving the reason "The approvals for additional FSI and upper floors of the sale building Zia Complex wing E could not be obtained due to change in policies for conversion of scheme and subsequent publication of DCPR 2034. The revised LOI under new provisions is process and will be issued soon enabling us to start work on the remaining floors of the sale building. Request the Hon'ble Authority to grant extension to the registered project."; to 30 September 2023, giving the reason "Certain approvals were to be sought from Ministry of Housing, Maharashtra Government which was unexpected and thus it took time for getting the FSI loaded and IOA/CC to be issued by Slum Rehabilitation Authority."; to 31 December 2025, giving the reason "Sir, The construction work of the project is completed and only minor finishes are remaining. We have also completed the RCC framework of the new religious structure, which will soon be handed over to users. The temporary religious structure which was an impediment in completing the firefighting work shall be demolished soon and the firefighting work along with the balance site infrastructure shall be completed thereafter. We will need some time to get the Occupation certificate thereafter. We therefore request this Authority to grant an extension to the project as per consent granted by Al…".

What is the RERA number of ZIA Complex Wing E?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ZIA Complex Wing E in Kurla East, Mumbai is P51800013616.

Is ZIA Complex Wing E registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ZIA Complex Wing E is registered as P51800013616 and its status is "Lapsed (registration period ended)".

What is the current construction status of ZIA Complex Wing E? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), ZIA Complex Wing E's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Wing E is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does ZIA Complex Wing E have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is ZIA Complex Wing E safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ZIA Complex Wing E is registered on MahaRERA as P51800013616, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 57 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in ZIA Complex Wing E?

ZIA Complex Wing E isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in ZIA Complex Wing E are 291 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in ZIA Complex Wing E?

For a flat in ZIA Complex Wing E (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has ZIA Complex Wing E received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), ZIA Complex Wing E isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for ZIA Complex Wing E?

According to GharKundli's check of MahaRERA records (updated October 2026), ZIA Complex Wing E's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has ZIA Complex Wing E uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for ZIA Complex Wing E was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if ZIA Complex Wing E's possession date changes?

The latest dates are on ZIA Complex Wing E's MahaRERA page (P51800013616). GharKundli's Kundli Watch sends a free WhatsApp update on ZIA Complex Wing E every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ZIA Complex Wing E have?

According to GharKundli's check of MahaRERA records (updated October 2026), ZIA Complex Wing E has one building filed: Wing E with 17 floors.

What are the flat sizes (carpet area) in ZIA Complex Wing E?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ZIA Complex Wing E: 1 BHK: 291 to 314 sq ft carpet (40 homes); Other: 321 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of ZIA Complex Wing E?

According to GharKundli's check of MahaRERA records (updated October 2026), ZIA Complex Wing E stands on 3,206 sq m of land (about 0.8 acres), with 1,245 sq m of sanctioned built-up area.

What are the reviews of ZIA Complex Wing E?

Google Maps has reviews of ZIA Complex Wing E written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of ZIA Complex Wing E?

ZIA Complex Wing E by I. R. Construction is in Kurla East, Mumbai, pincode 400070 (near Nehru Nagar, Kurla West, Chembur), Maharashtra, and is registered on MahaRERA as P51800013616, per GharKundli's check of MahaRERA records. Its land is filed as 631 Part. GharKundli lists all 92 MahaRERA projects in Kurla West (400070).

How many flats are in ZIA Complex Wing E, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), ZIA Complex Wing E has 41 homes in 1 tower registered on MahaRERA, and 98% of them are sold or booked.

When was ZIA Complex Wing E registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ZIA Complex Wing E was registered on MahaRERA on 16 October 2017. GharKundli did not find a title report on the land on file there.

Does ZIA Complex Wing E have any legal issues or court cases?

No court cases are listed for ZIA Complex Wing E on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of ZIA Complex Wing E?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is I. R. Construction.