by SIDDHIVINAYAK HABITATS · Dadar West, Mumbai 400028Also near Shivaji Park, Matunga, Dadar East

What’s in the report? →

Possession date of Siddhivinayak Habitats (MahaRERA P51900007465): 30 June 2024, moved from 30 March 2022 (27 months later), and it has already passed. It has 33 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900007465. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51900007465, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2024) has passed.

What do you want to know about Siddhivinayak Habitats?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Siddhivinayak Habitats has moved

  1. 30 March 2022

    Completion date given when the project was registered

  2. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51900013112)

    Reason the builder gave MahaRERA:
    “Respected Sir, With reference to above we have to state and submit as under : 1. Due to the lockdown, the construction of property had come to a full halt, owing to the lockdown to combat COVID-19, the supply chain for obtaining constructio…” Read the full reason“Respected Sir, With reference to above we have to state and submit as under : 1. Due to the lockdown, the construction of property had come to a full halt, owing to the lockdown to combat COVID-19, the supply chain for obtaining construction material has been disrupted and the workforce have migrated back to their home states. Due to these circumstances, project took some time to restart the work. 2. Further we faced a lot of financial difficulty due to the Covid-19 pandemic and were unable to have the CC issued before the lapse of IOD No CHE/CTY/1194/G/N/337(NEW)/IOD/1/Amend. Moreover, aft…”

Source: Siddhivinayak Habitats’s extension records on MahaRERA (P51900007465), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Siddhivinayak Habitats

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900007465
Status
Lapsed (registration period ended)
Builder
SIDDHIVINAYAK HABITATS
Location
Dadar West, Mumbai · 400028
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
March 2022
Latest completion date
June 2024
Delay so far
27 months
Homes
33
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Siddhivinayak Habitats, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Siddhivinayak Habitats100%90%20%10%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Siddhivinayak Habitats every 1–2 months.

Siddhivinayak Habitats: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Siddhivinayak Habitats →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Siddhivinayak Habitats: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Siddhivinayak Habitats

What is the possession date of Siddhivinayak Habitats?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Siddhivinayak Habitats in Dadar West, Mumbai is 30 June 2024 — 27 months later than 30 March 2022, the date given at registration. That date has already passed.

The date has already moved 27 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Siddhivinayak Habitats?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Siddhivinayak Habitats's builder has filed on MahaRERA, the official one, is 30 June 2024, already 27 months later than the 30 March 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Siddhivinayak Habitats extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhivinayak Habitats's builder applied to MahaRERA to extend the completion date once: to 30 June 2024, giving the reason "Respected Sir, With reference to above we have to state and submit as under : 1. Due to the lockdown, the construction of property had come to a full halt, owing to the lockdown to combat COVID-19, the supply chain for obtaining construction material has been disrupted and the workforce have migrated back to their home states. Due to these circumstances, project took some time to restart the work. 2. Further we faced a lot of financial difficulty due to the Covid-19 pandemic and were unable to have the CC issued before the lapse of IOD No CHE/CTY/1194/G/N/337(NEW)/IOD/1/Amend. Moreover, aft…".

What is the RERA number of Siddhivinayak Habitats?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Siddhivinayak Habitats in Dadar West, Mumbai is P51900007465.

Is Siddhivinayak Habitats registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhivinayak Habitats is registered as P51900007465 and its status is "Lapsed (registration period ended)".

What is the current construction status of Siddhivinayak Habitats? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhivinayak Habitats's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Siddhivinayak Habitats is 90% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.

Does Siddhivinayak Habitats have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Siddhivinayak Habitats safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhivinayak Habitats is registered on MahaRERA as P51900007465, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Siddhivinayak Habitats?

Siddhivinayak Habitats isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Siddhivinayak Habitats?

For a flat in Siddhivinayak Habitats (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Siddhivinayak Habitats received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Siddhivinayak Habitats isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Siddhivinayak Habitats?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhivinayak Habitats's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Siddhivinayak Habitats uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Siddhivinayak Habitats was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Siddhivinayak Habitats's possession date changes?

The latest dates are on Siddhivinayak Habitats's MahaRERA page (P51900007465). GharKundli's Kundli Watch sends a free WhatsApp update on Siddhivinayak Habitats every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Siddhivinayak Habitats have?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhivinayak Habitats has one building filed: Siddhivinayak Habitats with 24 floors.

How big is the land of Siddhivinayak Habitats?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhivinayak Habitats stands on 471 sq m of land (about 0.1 acres), with 1,558 sq m of sanctioned built-up area and 471 sq m of recreational open space.

What are the reviews of Siddhivinayak Habitats?

Google Maps has reviews of Siddhivinayak Habitats written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Siddhivinayak Habitats?

Siddhivinayak Habitats by SIDDHIVINAYAK HABITATS is in Dadar West, Mumbai, pincode 400028 (near Shivaji Park, Matunga, Dadar East), Maharashtra, and is registered on MahaRERA as P51900007465, per GharKundli's check of MahaRERA records. Its land is filed as 1821 old plot no 111. GharKundli lists all 148 MahaRERA projects in Dadar West (400028).

How many flats are in Siddhivinayak Habitats?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhivinayak Habitats has 33 homes in 1 tower registered on MahaRERA.

When was Siddhivinayak Habitats registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhivinayak Habitats was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Does Siddhivinayak Habitats have any legal issues or court cases?

No court cases are listed for Siddhivinayak Habitats on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Siddhivinayak Habitats?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SIDDHIVINAYAK HABITATS.

Other projects in Dadar West (400028)

All 148 projects in Dadar West (400028) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.