Rajendra Dolphin Tower
by Rajendra Builders Private Limited · Kharodi, Mumbai 400095Also near Malad West, Borivali, Kandivali westRegistered on MahaRERA as “Dolphin Tower”
What’s in the report? →Possession date of Rajendra Dolphin Tower (MahaRERA P51800020320): 6 May 2024, moved from 30 June 2019 (59 months later), and it has already passed. It has 78 homes (1 BHK and 2 BHK, 473–646 sq ft carpet), 87% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800020320. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800020320, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (May 2024) has passed.
What do you want to know about Rajendra Dolphin Tower?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Rajendra Dolphin Tower has moved
30 June 2019
Completion date given when the project was registered
31 October 2023
Extended at the builder's request (MahaRERA application EXT51800016550)
Reason the builder gave MahaRERA:
“We have completed the proposed building comprising of Stilt + 1st to 16th upper floor on said plot. Now, we are Applying for Occupation Certificate/Building Completion Certificate for Completed building under reference, As per Proforma 'A'…” Read the full reason
“We have completed the proposed building comprising of Stilt + 1st to 16th upper floor on said plot. Now, we are Applying for Occupation Certificate/Building Completion Certificate for Completed building under reference, As per Proforma 'A' of Approved Amended plan dt. 09.01.2014, there is deduction for Road Set back area and Reservation of Municipal School (RE 1.1) and Playground which admeasures 2.58 Sq.mt. for Road Setback area, 4.90 Sq.mt. Municipal School Re(1. 1) and Playground 19.50 Sq.mt. which we have already Handed over to MCGM as per the Possession Receipt u.no. CHE/ DP/ 19047/TDR…”6 May 2024
Extended at the builder's request (MahaRERA application EXT51800017967)
Reason the builder gave MahaRERA: “Project is completed only OC is pending due to plot handover to BMC”
Source: Rajendra Dolphin Tower’s extension records on MahaRERA (P51800020320), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Rajendra Dolphin Tower
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 court cases, and how it ended
- Construction pace against the May 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800020320
- Status
- Lapsed (registration period ended)
- Builder
- Rajendra Builders Private Limited
- Location
- Kharodi, Mumbai · 400095
- Project type
- Residential / Group Housing
- Registered on
- 5 Apr 2019
- Completion date at registration
- June 2019
- Latest completion date
- May 2024
- Delay so far
- 59 months
- Homes
- 78
- Sold or booked
- 87%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 4
- Title report on file
- Not found
Construction progress of Rajendra Dolphin Tower, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Dolphin Tower | 50% | 50% | 50% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- Dolphin Tower: covers 17 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rajendra Dolphin Tower every 1–2 months.
Rajendra Dolphin Tower: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 646 | 62 |
| 1 BHK | 473 | 16 |
- Buildings: Dolphin Tower (18 floors, 78 units)
- Car parking: 39 covered
- Land: 2,148 sq m (about 0.5 acres) · sanctioned built-up 5,715 sq m · recreational space 320 sq m
- Land, as filed: CTS no 336
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Rajendra Dolphin Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Rajendra Dolphin Tower: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Rajendra Dolphin Tower
What is the possession date of Rajendra Dolphin Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Rajendra Dolphin Tower in Kharodi, Mumbai is 6 May 2024 — 59 months later than 30 June 2019, the date given at registration. That date has already passed.
The date has already moved 59 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Rajendra Dolphin Tower?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Rajendra Dolphin Tower's builder has filed on MahaRERA, the official one, is 6 May 2024, already 59 months later than the 30 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Rajendra Dolphin Tower extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajendra Dolphin Tower's builder applied to MahaRERA to extend the completion date 2 times: to 31 October 2023, giving the reason "We have completed the proposed building comprising of Stilt + 1st to 16th upper floor on said plot. Now, we are Applying for Occupation Certificate/Building Completion Certificate for Completed building under reference, As per Proforma 'A' of Approved Amended plan dt. 09.01.2014, there is deduction for Road Set back area and Reservation of Municipal School (RE 1.1) and Playground which admeasures 2.58 Sq.mt. for Road Setback area, 4.90 Sq.mt. Municipal School Re(1. 1) and Playground 19.50 Sq.mt. which we have already Handed over to MCGM as per the Possession Receipt u.no. CHE/ DP/ 19047/TDR…"; to 6 May 2024, giving the reason "Project is completed only OC is pending due to plot handover to BMC".
What is the RERA number of Rajendra Dolphin Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Rajendra Dolphin Tower in Kharodi, Mumbai is P51800020320.
Is Rajendra Dolphin Tower registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajendra Dolphin Tower is registered as P51800020320 and its status is "Lapsed (registration period ended)".
What is the current construction status of Rajendra Dolphin Tower? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajendra Dolphin Tower's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Dolphin Tower is 50% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does Rajendra Dolphin Tower have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Rajendra Dolphin Tower safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajendra Dolphin Tower is registered on MahaRERA as P51800020320, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 59 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Rajendra Dolphin Tower?
Rajendra Dolphin Tower isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Rajendra Dolphin Tower are 473 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Rajendra Dolphin Tower?
For a flat in Rajendra Dolphin Tower (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Rajendra Dolphin Tower received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Rajendra Dolphin Tower isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 6 May 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Rajendra Dolphin Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajendra Dolphin Tower's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (6 May 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Rajendra Dolphin Tower uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Rajendra Dolphin Tower was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Rajendra Dolphin Tower's possession date changes?
The latest dates are on Rajendra Dolphin Tower's MahaRERA page (P51800020320). GharKundli's Kundli Watch sends a free WhatsApp update on Rajendra Dolphin Tower every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Rajendra Dolphin Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajendra Dolphin Tower has one building filed: Dolphin Tower with 18 floors and 78 units.
What are the flat sizes (carpet area) in Rajendra Dolphin Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Rajendra Dolphin Tower: 2 BHK: 646 sq ft carpet (62 homes); 1 BHK: 473 sq ft carpet (16 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Rajendra Dolphin Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 39 covered car parking spaces for Rajendra Dolphin Tower.
How big is the land of Rajendra Dolphin Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajendra Dolphin Tower stands on 2,148 sq m of land (about 0.5 acres), with 5,715 sq m of sanctioned built-up area and 320 sq m of recreational open space.
What are the reviews of Rajendra Dolphin Tower?
Google Maps has reviews of Rajendra Dolphin Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Rajendra Dolphin Tower?
Rajendra Dolphin Tower by Rajendra Builders Private Limited is in Kharodi, Mumbai, pincode 400095 (near Malad West, Borivali, Kandivali west), Maharashtra, and is registered on MahaRERA as P51800020320, per GharKundli's check of MahaRERA records. Its land is filed as CTS no 336. GharKundli lists all 52 MahaRERA projects in Malad West (400095).
How many flats are in Rajendra Dolphin Tower, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajendra Dolphin Tower has 78 homes in 1 tower registered on MahaRERA, and 87% of them are sold or booked.
When was Rajendra Dolphin Tower registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajendra Dolphin Tower was registered on MahaRERA on 5 April 2019. GharKundli did not find a title report on the land on file there.
Does Rajendra Dolphin Tower have any legal issues or court cases?
4 court cases are listed for Rajendra Dolphin Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Rajendra Dolphin Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Rajendra Builders Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of Rajendra Dolphin Tower
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Malad West (400095)
- Aquarose
- Galaxy Heights, Tower-II, Wing A to B
- Galaxy Heights, Tower-IV
- Ardhya Aura
- Scorpio
- Florence Heights A and B Wing
- Lotus
- Bay Vue
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.