by PRIME HOUSING · Matunga (C.R.), Mumbai 400019Also near Matunga East, Matunga (CR), Wadala WestRegistered on MahaRERA as “SANGEET JYOTI”

What’s in the report? →

Possession date of Prime Sangeet Jyoti (MahaRERA P51900010030): 30 June 2025, moved from 31 December 2018 (78 months later), and it has already passed. It has 11 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900010030. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51900010030, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2025) has passed.

What do you want to know about Prime Sangeet Jyoti?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Prime Sangeet Jyoti has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2019

    Extended at the builder's request (MahaRERA application EXT51900000900)

    Reason the builder gave MahaRERA:
    “The construction of R.C.C. work and plaster is complete. The painting work of building is in progress. Work of fitting of lift will start from 20th December 2018 and we undertake to complete balance work and apply for Occupation Certificate…” Read the full reason“The construction of R.C.C. work and plaster is complete. The painting work of building is in progress. Work of fitting of lift will start from 20th December 2018 and we undertake to complete balance work and apply for Occupation Certificate 30th June 2019. The delay is due to non - availability of sand and other material and pending litigation between Landlord and Promoter. We seek extension of 12 months.”
  3. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT51900005263)

    Reason the builder gave MahaRERA:
    “1) The Promoter respectfully submits that the project of the Promoter is at Matunga, Mumbai. 2) The Promoter states that the delay in completion of the project is mainly because of market conditions and unavailability of sand and constructi…” Read the full reason“1) The Promoter respectfully submits that the project of the Promoter is at Matunga, Mumbai. 2) The Promoter states that the delay in completion of the project is mainly because of market conditions and unavailability of sand and construction materials and delay in permissions granted by M.C.G.M. 3) The promoter states that because of market condition payments were not received by the promoter as were expected. The promoter states that financial crunch resulted in further delay of project. 4) In spite of the same the Promoter had completed building and construction work of buildings is in f…”
  4. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51900017076)

    Reason the builder gave MahaRERA:
    “The delay in the completion of the real estate project has been primarily caused by a combination of procurement issues, site conditions, coordination challenges, and delay in OC. By implementing the outlined action plan, we aim to mitigate…” Read the full reason“The delay in the completion of the real estate project has been primarily caused by a combination of procurement issues, site conditions, coordination challenges, and delay in OC. By implementing the outlined action plan, we aim to mitigate these delays and move forward efficiently. However, we assure you that our utmost priority is to safeguard the interests of the allottees and ensure the successful completion of the project. In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. We have consent of 60% allottees for purpose of extension of RE…”

Source: Prime Sangeet Jyoti’s extension records on MahaRERA (P51900010030), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Prime Sangeet Jyoti

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900010030
Status
Lapsed (registration period ended)
Builder
PRIME HOUSING
Location
Matunga (C.R.), Mumbai · 400019
Project type
Others
Registered on
23 Aug 2017
Completion date at registration
December 2018
Latest completion date
June 2025
Delay so far
78 months
Homes
11
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Prime Sangeet Jyoti, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SANGEET JYOTI100%100%96%80%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Prime Sangeet Jyoti every 1–2 months.

Prime Sangeet Jyoti: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Prime Sangeet Jyoti →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Prime Sangeet Jyoti: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Prime Sangeet Jyoti

What is the possession date of Prime Sangeet Jyoti?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Prime Sangeet Jyoti in Matunga (C.R.), Mumbai is 30 June 2025 — 78 months later than 31 December 2018, the date given at registration. That date has already passed.

The date has already moved 78 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Prime Sangeet Jyoti?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Prime Sangeet Jyoti's builder has filed on MahaRERA, the official one, is 30 June 2025, already 78 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Prime Sangeet Jyoti extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Sangeet Jyoti's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2019, giving the reason "The construction of R.C.C. work and plaster is complete. The painting work of building is in progress. Work of fitting of lift will start from 20th December 2018 and we undertake to complete balance work and apply for Occupation Certificate 30th June 2019. The delay is due to non - availability of sand and other material and pending litigation between Landlord and Promoter. We seek extension of 12 months."; to 31 December 2020, giving the reason "1) The Promoter respectfully submits that the project of the Promoter is at Matunga, Mumbai. 2) The Promoter states that the delay in completion of the project is mainly because of market conditions and unavailability of sand and construction materials and delay in permissions granted by M.C.G.M. 3) The promoter states that because of market condition payments were not received by the promoter as were expected. The promoter states that financial crunch resulted in further delay of project. 4) In spite of the same the Promoter had completed building and construction work of buildings is in f…"; to 30 June 2025, giving the reason "The delay in the completion of the real estate project has been primarily caused by a combination of procurement issues, site conditions, coordination challenges, and delay in OC. By implementing the outlined action plan, we aim to mitigate these delays and move forward efficiently. However, we assure you that our utmost priority is to safeguard the interests of the allottees and ensure the successful completion of the project. In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. We have consent of 60% allottees for purpose of extension of RE…".

What is the RERA number of Prime Sangeet Jyoti?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Prime Sangeet Jyoti in Matunga (C.R.), Mumbai is P51900010030.

Is Prime Sangeet Jyoti registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Sangeet Jyoti is registered as P51900010030 and its status is "Lapsed (registration period ended)".

What is the current construction status of Prime Sangeet Jyoti? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Sangeet Jyoti's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SANGEET JYOTI is 100% done and internal work 96%. GharKundli's full report compares construction progress with the deadline.

Does Prime Sangeet Jyoti have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Prime Sangeet Jyoti safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Sangeet Jyoti is registered on MahaRERA as P51900010030, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 78 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Prime Sangeet Jyoti?

Prime Sangeet Jyoti isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Prime Sangeet Jyoti?

For a flat in Prime Sangeet Jyoti (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Prime Sangeet Jyoti received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Prime Sangeet Jyoti isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Prime Sangeet Jyoti?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Sangeet Jyoti's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Prime Sangeet Jyoti uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Prime Sangeet Jyoti was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Prime Sangeet Jyoti's possession date changes?

The latest dates are on Prime Sangeet Jyoti's MahaRERA page (P51900010030). GharKundli's Kundli Watch sends a free WhatsApp update on Prime Sangeet Jyoti every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Prime Sangeet Jyoti have?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Sangeet Jyoti has one building filed: SANGEET JYOTI with 18 floors.

How big is the land of Prime Sangeet Jyoti?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Sangeet Jyoti stands on 334 sq m of land (about 0.1 acres), with 1,070 sq m of sanctioned built-up area.

What are the reviews of Prime Sangeet Jyoti?

Google Maps has reviews of Prime Sangeet Jyoti written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Prime Sangeet Jyoti?

Prime Sangeet Jyoti by PRIME HOUSING is in Matunga (C.R.), Mumbai, pincode 400019 (near Matunga East, Matunga (CR), Wadala West), Maharashtra, and is registered on MahaRERA as P51900010030, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO 310/10. GharKundli lists all 104 MahaRERA projects in Matunga (400019).

How many flats are in Prime Sangeet Jyoti?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Sangeet Jyoti has 11 homes in 1 tower registered on MahaRERA.

When was Prime Sangeet Jyoti registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Sangeet Jyoti was registered on MahaRERA on 23 August 2017. GharKundli did not find a title report on the land on file there.

Does Prime Sangeet Jyoti have any legal issues or court cases?

No court cases are listed for Prime Sangeet Jyoti on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Prime Sangeet Jyoti?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRIME HOUSING, which has 1 other project registered on MahaRERA.

Other projects in Matunga (400019)

All 104 projects in Matunga (400019) →

Other projects by PRIME HOUSING

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.