ROYAL PRISTO

by ROYAL REALTORS · Vaishetpada Kurar Village Malad East, MumbaiAlso near Dindoshi, Pathanwadi, Dhanjiwadi

Possession date of ROYAL PRISTO: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800019529, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 5 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about ROYAL PRISTO?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ROYAL PRISTO has moved

  1. 30 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: ROYAL PRISTO’s extension records on MahaRERA (P51800019529), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ROYAL PRISTO

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 complaints and 3 court cases, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800019529
Status
Registered and active
Builder
ROYAL REALTORS
Location
Vaishetpada Kurar Village Malad East, Mumbai · 400097
Project type
Residential / Group Housing
Registered on
8 Feb 2019
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
681
Towers
2
Complaints on MahaRERA
5
Court cases listed
3
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of ROYAL PRISTO, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ROYAL PRISTO100%100%25%0%
ROYAL PARV100%100%100%50%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ROYAL PRISTO every month.

ROYAL PRISTO: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Royal Realtors (a group of 4 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 12 months); 5 still being built, none past the promised date yet; 1 lapsed. 9 complaints on MahaRERA across 3 projects.

Read Google reviews of ROYAL PRISTO →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ROYAL PRISTO: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ROYAL PRISTO

What is the possession date of ROYAL PRISTO?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ROYAL PRISTO in Vaishetpada Kurar Village Malad East, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for ROYAL PRISTO?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ROYAL PRISTO's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of ROYAL PRISTO?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ROYAL PRISTO in Vaishetpada Kurar Village Malad East, Mumbai is P51800019529.

Is ROYAL PRISTO registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ROYAL PRISTO is registered as P51800019529 and its status is "Registered and active".

What is the construction status of ROYAL PRISTO?

According to GharKundli's check of MahaRERA records (updated November 2026), ROYAL PRISTO's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does ROYAL PRISTO have complaints on MahaRERA?

5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ROYAL PRISTO safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), ROYAL PRISTO is registered on MahaRERA as P51800019529, its completion date has not been moved by the builder and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ROYAL PRISTO's possession date changes?

The latest dates are on ROYAL PRISTO's MahaRERA page (P51800019529). GharKundli's Kundli Watch sends a free WhatsApp update on ROYAL PRISTO every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ROYAL PRISTO have?

According to GharKundli's check of MahaRERA records (updated November 2026), ROYAL PRISTO has 2 buildings filed: ROYAL PRISTO with 36 floors; ROYAL PARV with 28 floors.

How big is the land of ROYAL PRISTO?

According to GharKundli's check of MahaRERA records (updated November 2026), ROYAL PRISTO stands on 12,861 sq m of land (about 3.2 acres), with 23,083 sq m of sanctioned built-up area and 894 sq m of recreational open space.

What is the track record of ROYAL PRISTO's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Royal Realtors (a group of 4 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 12 months); 5 still being built, none past the promised date yet; 1 lapsed. 9 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ROYAL PRISTO?

Google Maps has reviews of ROYAL PRISTO written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ROYAL PRISTO?

ROYAL PRISTO by ROYAL REALTORS is in Vaishetpada Kurar Village Malad East, Mumbai (pincode 400097), near Dindoshi, Pathanwadi, Dhanjiwadi, Maharashtra, and is registered on MahaRERA as P51800019529, per GharKundli's check of MahaRERA records.

How many homes are in ROYAL PRISTO?

According to GharKundli's check of MahaRERA records (updated November 2026), ROYAL PRISTO has 681 homes in 2 towers registered on MahaRERA.

When was ROYAL PRISTO registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ROYAL PRISTO was registered on MahaRERA on 8 February 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on ROYAL PRISTO?

3 court cases are listed for ROYAL PRISTO on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of ROYAL PRISTO?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ROYAL REALTORS, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400097

All 195 projects in Malad East (400097) →

Other projects by ROYAL REALTORS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.