Tridhaatu Kshitij
by Tridhaatu Construction Private Limited · Mahim, MumbaiAlso near Dadar West, Shivaji Park, Matunga West
Possession date of Tridhaatu Kshitij: 30 December 2023. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900009306. Status: Lapsed (registration period ended). 7 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2023) has passed.
What do you want to know about Tridhaatu Kshitij?
GharKundli’s full report on Tridhaatu Kshitij
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 7 complaints, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900009306
- Status
- Lapsed (registration period ended)
- Builder
- Tridhaatu Construction Private Limited
- Location
- Mahim, Mumbai · 400016
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- December 2023
- Homes
- 66
- Towers
- 1
- Complaints on MahaRERA
- 7
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of Tridhaatu Kshitij, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Tridhaatu Kshitij | 70% | 100% | 70% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tridhaatu Kshitij every month.
Tridhaatu Kshitij: buildings, flats and land, as filed on MahaRERA
- Buildings: Tridhaatu Kshitij (37 floors)
- Land: 3,437 sq m (about 0.8 acres) · sanctioned built-up 8,981 sq m · recreational space 516 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Tridhaatu Kshitij →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Tridhaatu Kshitij: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Tridhaatu Kshitij
What is the possession date of Tridhaatu Kshitij?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Tridhaatu Kshitij in Mahim, Mumbai is 30 December 2023. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Tridhaatu Kshitij?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Tridhaatu Kshitij's builder has filed on MahaRERA, the official one, is 30 December 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Tridhaatu Kshitij?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Tridhaatu Kshitij in Mahim, Mumbai is P51900009306.
Is Tridhaatu Kshitij registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Tridhaatu Kshitij is registered as P51900009306 and its status is "Lapsed (registration period ended)".
What is the construction status of Tridhaatu Kshitij?
According to GharKundli's check of MahaRERA records (updated November 2026), Tridhaatu Kshitij's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Tridhaatu Kshitij is 100% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does Tridhaatu Kshitij have complaints on MahaRERA?
7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Tridhaatu Kshitij safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Tridhaatu Kshitij is registered on MahaRERA as P51900009306, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Tridhaatu Kshitij's possession date changes?
The latest dates are on Tridhaatu Kshitij's MahaRERA page (P51900009306). GharKundli's Kundli Watch sends a free WhatsApp update on Tridhaatu Kshitij every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Tridhaatu Kshitij have?
According to GharKundli's check of MahaRERA records (updated November 2026), Tridhaatu Kshitij has one building filed: Tridhaatu Kshitij with 37 floors.
How big is the land of Tridhaatu Kshitij?
According to GharKundli's check of MahaRERA records (updated November 2026), Tridhaatu Kshitij stands on 3,437 sq m of land (about 0.8 acres), with 8,981 sq m of sanctioned built-up area and 516 sq m of recreational open space.
Where can I read reviews of Tridhaatu Kshitij?
Google Maps has reviews of Tridhaatu Kshitij written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Tridhaatu Kshitij?
Tridhaatu Kshitij by Tridhaatu Construction Private Limited is in Mahim, Mumbai (pincode 400016), near Dadar West, Shivaji Park, Matunga West, Maharashtra, and is registered on MahaRERA as P51900009306, per GharKundli's check of MahaRERA records.
How many homes are in Tridhaatu Kshitij?
According to GharKundli's check of MahaRERA records (updated November 2026), Tridhaatu Kshitij has 66 homes in 1 tower registered on MahaRERA.
When was Tridhaatu Kshitij registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Tridhaatu Kshitij was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Tridhaatu Kshitij?
No court cases are listed for Tridhaatu Kshitij on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Tridhaatu Kshitij?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Tridhaatu Construction Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of Tridhaatu Kshitij
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400016
All 83 projects in Mahim (400016) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.