Skip to content
GharKundli

CD PLOT NO 7

by SD SVP Nagar Redevelopment Private Limited · Andheri West, MumbaiAlso near Ambivali, Versova, Model Town

Possession date of CD PLOT NO 7: 30 October 2021, moved from 31 October 2019 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800020059. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (October 2021) has passed.

What do you want to know about CD PLOT NO 7?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of CD PLOT NO 7 has moved

  1. 31 October 2019

    Completion date given when the project was registered

  2. 30 October 2020

    Extended at the builder's request (MahaRERA application EXT51800002586)

    Reason the builder gave MahaRERA:
    “The applicability of the DCPR 2034 to the ongoing schemes and the various transition policies of the MCGM for implementation of DCPR 2034, which was under suggestion and objection since March 2018. Based on the Transitional policy which fin…” Read the full reason“The applicability of the DCPR 2034 to the ongoing schemes and the various transition policies of the MCGM for implementation of DCPR 2034, which was under suggestion and objection since March 2018. Based on the Transitional policy which finalized and issued for our project in November 2018, we have revised the calculations and planning of the construction work at site, which is time consuming factor. Litigation filed by one non-co-operative member of the Society of Plot 69; the project was stalled for a year from February 2015. We have succeeded on 26.02.2016, however till that period, the…”
  3. 30 October 2021

    Revised completion date on MahaRERA

Source: CD PLOT NO 7’s extension records on MahaRERA (P51800020059), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on CD PLOT NO 7

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the October 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800020059
Status
Lapsed (registration period ended)
Builder
SD SVP Nagar Redevelopment Private Limited
Location
Andheri West, Mumbai · 400053
Project type
Residential / Group Housing
Registered on
25 Mar 2019
Completion date at registration
October 2019
Latest completion date
October 2021
Delay so far
24 months
Homes
12
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of CD PLOT NO 7, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE VIGHNESHWAR HEIGHTS100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on CD PLOT NO 7 every month.

CD PLOT NO 7: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

SD SVP Nagar Redevelopment has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 1 lapsed. 34 complaints on MahaRERA across 2 projects.

Read Google reviews of CD PLOT NO 7 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

CD PLOT NO 7: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about CD PLOT NO 7

What is the possession date of CD PLOT NO 7?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for CD PLOT NO 7 in Andheri West, Mumbai is 30 October 2021 — 24 months later than 31 October 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for CD PLOT NO 7?

Builders and listing sites often quote an earlier "target" date for handover. The completion date CD PLOT NO 7's builder has filed on MahaRERA, the official one, is 30 October 2021, already 24 months later than the 31 October 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of CD PLOT NO 7 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), CD PLOT NO 7's builder applied to MahaRERA to extend the completion date once: to 30 October 2020, giving the reason "The applicability of the DCPR 2034 to the ongoing schemes and the various transition policies of the MCGM for implementation of DCPR 2034, which was under suggestion and objection since March 2018. Based on the Transitional policy which finalized and issued for our project in November 2018, we have revised the calculations and planning of the construction work at site, which is time consuming factor. Litigation filed by one non-co-operative member of the Society of Plot 69; the project was stalled for a year from February 2015. We have succeeded on 26.02.2016, however till that period, the…".

What is the RERA number of CD PLOT NO 7?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of CD PLOT NO 7 in Andheri West, Mumbai is P51800020059.

Is CD PLOT NO 7 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), CD PLOT NO 7 is registered as P51800020059 and its status is "Lapsed (registration period ended)".

What is the construction status of CD PLOT NO 7?

According to GharKundli's check of MahaRERA records (updated November 2026), CD PLOT NO 7's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHREE VIGHNESHWAR HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does CD PLOT NO 7 have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is CD PLOT NO 7 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), CD PLOT NO 7 is registered on MahaRERA as P51800020059, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if CD PLOT NO 7's possession date changes?

The latest dates are on CD PLOT NO 7's MahaRERA page (P51800020059). GharKundli's Kundli Watch sends a free WhatsApp update on CD PLOT NO 7 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does CD PLOT NO 7 have?

According to GharKundli's check of MahaRERA records (updated November 2026), CD PLOT NO 7 has one building filed: SHREE VIGHNESHWAR HEIGHTS with 23 floors.

How big is the land of CD PLOT NO 7?

According to GharKundli's check of MahaRERA records (updated November 2026), CD PLOT NO 7 stands on 1,313 sq m of land (about 0.3 acres), with 6,165 sq m of sanctioned built-up area and 120 sq m of recreational open space.

What is the track record of CD PLOT NO 7's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), SD SVP Nagar Redevelopment has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 1 lapsed. 34 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of CD PLOT NO 7?

Google Maps has reviews of CD PLOT NO 7 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is CD PLOT NO 7?

CD PLOT NO 7 by SD SVP Nagar Redevelopment Private Limited is in Andheri West, Mumbai (pincode 400053), near Ambivali, Versova, Model Town, Maharashtra, and is registered on MahaRERA as P51800020059, per GharKundli's check of MahaRERA records.

How many homes are in CD PLOT NO 7?

According to GharKundli's check of MahaRERA records (updated November 2026), CD PLOT NO 7 has 12 homes in 1 tower registered on MahaRERA.

When was CD PLOT NO 7 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), CD PLOT NO 7 was registered on MahaRERA on 25 March 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on CD PLOT NO 7?

No court cases are listed for CD PLOT NO 7 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of CD PLOT NO 7?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SD SVP Nagar Redevelopment Private Limited, which has 1 other project registered on MahaRERA.

Other projects in pincode 400053

All 161 projects in Andheri West (400053) →

Other projects by SD SVP Nagar Redevelopment Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.