Skip to content
GharKundli

ALAG CAPITAL

by ALAG PROPERTY CONSTRUCTIONS PVT. LTD. · Mulund West, MumbaiAlso near Bhandup West, Nahur, Mulund East

Possession date of ALAG CAPITAL: 30 April 2027, moved from 30 June 2024 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800020773, and currently active. Its completion date has moved from June 2024 to April 2027: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about ALAG CAPITAL?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ALAG CAPITAL has moved

  1. 30 June 2024

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51800025331)

    Reason the builder gave MahaRERA:
    “We sincerely apologize for the delay in both the completion of the project and the submission of this application. The delay has been caused due to procurement issues, site conditions, coordination challenges, and delay in obtaining the Occ…” Read the full reason“We sincerely apologize for the delay in both the completion of the project and the submission of this application. The delay has been caused due to procurement issues, site conditions, coordination challenges, and delay in obtaining the Occupancy Certificate (OC). We hereby apply for the Extension U/s 7(3), Kindly approve our request for extension till date 31-12-2026.”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: ALAG CAPITAL’s extension records on MahaRERA (P51800020773), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ALAG CAPITAL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800020773
Status
Registered and active
Builder
ALAG PROPERTY CONSTRUCTIONS PVT. LTD.
Location
Mulund West, Mumbai · 400080
Project type
Others
Registered on
9 May 2019
Completion date at registration
June 2024
Latest completion date
April 2027
Delay so far
30 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
60
Towers
3
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of ALAG CAPITAL, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ALAG CAPITAL 1A100%0%0%0%
ALAG CAPITAL 1B100%0%0%0%
ALAG CAPITAL 1C100%100%30%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ALAG CAPITAL every month.

ALAG CAPITAL: buildings, flats and land, as filed on MahaRERA

  • Buildings: ALAG CAPITAL 1A (20 floors) · ALAG CAPITAL 1B (20 floors) · ALAG CAPITAL 1C (4 floors)
  • Land: 3,658 sq m (about 0.9 acres) · recreational space 732 sq m
  • Boundaries filed include: MULUND GOREGAON LINK ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Alag Property Constructions has 5 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 6 months); 2 still being built, 2 past the promised date (typically 32 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of ALAG CAPITAL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ALAG CAPITAL: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ALAG CAPITAL

What is the possession date of ALAG CAPITAL?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ALAG CAPITAL in Mulund West, Mumbai is 30 April 2027 — 30 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for ALAG CAPITAL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ALAG CAPITAL's builder has filed on MahaRERA, the official one, is 30 April 2027, already 30 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ALAG CAPITAL extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ALAG CAPITAL's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We sincerely apologize for the delay in both the completion of the project and the submission of this application. The delay has been caused due to procurement issues, site conditions, coordination challenges, and delay in obtaining the Occupancy Certificate (OC). We hereby apply for the Extension U/s 7(3), Kindly approve our request for extension till date 31-12-2026.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of ALAG CAPITAL?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ALAG CAPITAL in Mulund West, Mumbai is P51800020773.

Is ALAG CAPITAL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ALAG CAPITAL is registered as P51800020773 and its status is "Registered and active".

What is the construction status of ALAG CAPITAL?

According to GharKundli's check of MahaRERA records (updated October 2026), ALAG CAPITAL's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does ALAG CAPITAL have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ALAG CAPITAL safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ALAG CAPITAL is registered on MahaRERA as P51800020773, its completion date has moved 30 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ALAG CAPITAL's possession date changes?

The latest dates are on ALAG CAPITAL's MahaRERA page (P51800020773). GharKundli's Kundli Watch sends a free WhatsApp update on ALAG CAPITAL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ALAG CAPITAL have?

According to GharKundli's check of MahaRERA records (updated October 2026), ALAG CAPITAL has 3 buildings filed: ALAG CAPITAL 1A with 20 floors; ALAG CAPITAL 1B with 20 floors; ALAG CAPITAL 1C with 4 floors.

How big is the land of ALAG CAPITAL?

According to GharKundli's check of MahaRERA records (updated October 2026), ALAG CAPITAL stands on 3,658 sq m of land (about 0.9 acres) and 732 sq m of recreational open space.

What is the track record of ALAG CAPITAL's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Alag Property Constructions has 5 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 6 months); 2 still being built, 2 past the promised date (typically 32 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ALAG CAPITAL?

Google Maps has reviews of ALAG CAPITAL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ALAG CAPITAL?

ALAG CAPITAL by ALAG PROPERTY CONSTRUCTIONS PVT. LTD. is in Mulund West, Mumbai (pincode 400080), near Bhandup West, Nahur, Mulund East, Maharashtra, and is registered on MahaRERA as P51800020773, per GharKundli's check of MahaRERA records. Its boundaries filed there include MULUND GOREGAON LINK ROAD.

How many homes are in ALAG CAPITAL?

According to GharKundli's check of MahaRERA records (updated October 2026), ALAG CAPITAL has 60 homes in 3 towers registered on MahaRERA.

When was ALAG CAPITAL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ALAG CAPITAL was registered on MahaRERA on 9 May 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on ALAG CAPITAL?

No court cases are listed for ALAG CAPITAL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of ALAG CAPITAL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ALAG PROPERTY CONSTRUCTIONS PVT. LTD., which has 4 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400080

All 303 projects in Mulund West (400080) →

Other projects by ALAG PROPERTY CONSTRUCTIONS PVT. LTD.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.