PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.
by ARJUNSINGH BHOORSINGH RATHORE · Vile Parle West, Mumbai
Possession date of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.: 30 June 2027, moved from 30 June 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800021193, and currently active. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?
How the possession date of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. has moved
30 June 2023
Completion date given when the project was registered
29 June 2024
Extended at the builder's request (MahaRERA application EXT51800016863)
Reason the builder gave MahaRERA: “Due to the Covid-19 Pandemic Situation in the Country We could not completed our Work on time, Therefore request you to kindly consider our attached extension letter”
30 June 2026
Extended at the builder's request (MahaRERA application EXT51800024171)
Reason the builder gave MahaRERA:
“The primary reasons for the delay, as we understand, include arch 1. Road Winding Issues in D P 2034 There have been challenges with road construction due to changes in planning regulations and technical issues, which have directly impacted…” Read the full reason
“The primary reasons for the delay, as we understand, include arch 1. Road Winding Issues in D P 2034 There have been challenges with road construction due to changes in planning regulations and technical issues, which have directly impacted the project's timeline 2 Ongoing Court Cases Legal disputes between the society and certain members of the project have contributed to the overall delay These issues are currently resolved. 3 Other Legal Litigations and Regulatory Delays. In addition to the above, there have been other legal and regulatory challenges, including delays in obtaining the ne…”30 June 2027
Extended at the builder's request (MahaRERA application EA19082622231)
Reason the builder gave MahaRERA:
“I, Arjun Singh Rathore, Proprietor of M/s. Rasal Builders & Developers, is the promoters of the real estate project known as "PRIYA CO-OPERATIVE HOUSING SOCIETY LIMITED" bearing Maha RERA Registration No. P51800021193. The primary reasons f…” Read the full reason
“I, Arjun Singh Rathore, Proprietor of M/s. Rasal Builders & Developers, is the promoters of the real estate project known as "PRIYA CO-OPERATIVE HOUSING SOCIETY LIMITED" bearing Maha RERA Registration No. P51800021193. The primary reasons for the delay, as we understand, include: 1. Road Winding Issues in D P 2034: There have been challenges with road construction due to changes in planning regulations and technical issues, which have directly impacted the project's timeline. 2. Ongoing Court Cases: Legal disputes between the society and certain members of the project have contributed to th…”
Source: PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.’s extension records on MahaRERA (P51800021193), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800021193
- Status
- Registered and active
- Builder
- ARJUNSINGH BHOORSINGH RATHORE
- Location
- Vile Parle West, Mumbai · 400058
- Project type
- Residential / Group Housing
- Registered on
- 14 Jun 2019
- Completion date at registration
- June 2023
- Latest completion date
- June 2027
- Delay so far
- 48 months
- Homes
- 28
- Sold or booked
- 21%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD., as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PRIYA CO-OPERATIVE HOUSING SOCIETY LIMITED | 100% | 60% | 15% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- PRIYA CO-OPERATIVE HOUSING SOCIETY LIMITED: covers C.C. Up to top of 5th floor
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. every month.
PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Other | 501 – 786 | 13 |
| 2 BHK | 737 – 786 | 9 |
| 1 Room Kitchen | 201 – 219 | 4 |
| Shops | 129 – 272 | 2 |
| Office Space | 1,404 | 1 |
| 3 BHK | 818 | 1 |
| 1 BHK | 367 | 1 |
- Buildings: PRIYA CO-OPERATIVE HOUSING SOCIETY LIMITED (5 floors, 31 units)
- Land: 678 sq m (about 0.2 acres) · sanctioned built-up 678 sq m · recreational space 20 sq m
- Boundaries filed include: GULMOHAR ROAD, CP GOENKA INTERNATIONAL SCHOOL
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.
What is the possession date of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. in Vile Parle West, Mumbai is 30 June 2027 — 48 months later than 30 June 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.'s builder has filed on MahaRERA, the official one, is 30 June 2027, already 48 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. extended?
According to GharKundli's check of MahaRERA records (updated October 2026), PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.'s builder applied to MahaRERA to extend the completion date 3 times: to 29 June 2024, giving the reason "Due to the Covid-19 Pandemic Situation in the Country We could not completed our Work on time, Therefore request you to kindly consider our attached extension letter"; to 30 June 2026, giving the reason "The primary reasons for the delay, as we understand, include arch 1. Road Winding Issues in D P 2034 There have been challenges with road construction due to changes in planning regulations and technical issues, which have directly impacted the project's timeline 2 Ongoing Court Cases Legal disputes between the society and certain members of the project have contributed to the overall delay These issues are currently resolved. 3 Other Legal Litigations and Regulatory Delays. In addition to the above, there have been other legal and regulatory challenges, including delays in obtaining the ne…"; to 30 June 2027, giving the reason "I, Arjun Singh Rathore, Proprietor of M/s. Rasal Builders & Developers, is the promoters of the real estate project known as "PRIYA CO-OPERATIVE HOUSING SOCIETY LIMITED" bearing Maha RERA Registration No. P51800021193. The primary reasons for the delay, as we understand, include: 1. Road Winding Issues in D P 2034: There have been challenges with road construction due to changes in planning regulations and technical issues, which have directly impacted the project's timeline. 2. Ongoing Court Cases: Legal disputes between the society and certain members of the project have contributed to th…".
What is the RERA number of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. in Vile Parle West, Mumbai is P51800021193.
Is PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. is registered as P51800021193 and its status is "Registered and active".
What is the construction status of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.'s status on MahaRERA is "Registered and active". As filed by the builder, slab work on PRIYA CO-OPERATIVE HOUSING SOCIETY LIMITED is 60% done and internal work 15%. GharKundli's full report compares construction progress with the deadline.
Does PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. is registered on MahaRERA as P51800021193, its completion date has moved 48 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.'s possession date changes?
The latest dates are on PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.'s MahaRERA page (P51800021193). GharKundli's Kundli Watch sends a free WhatsApp update on PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. have?
According to GharKundli's check of MahaRERA records (updated October 2026), PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. has one building filed: PRIYA CO-OPERATIVE HOUSING SOCIETY LIMITED with 5 floors and 31 units.
What are the flat sizes (carpet area) in PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.: Other: 501 to 786 sq ft carpet (13 homes); 2 BHK: 737 to 786 sq ft carpet (9 homes); 1 Room Kitchen: 201 to 219 sq ft carpet (4 homes); 3 BHK: 818 sq ft carpet (1 homes); 1 BHK: 367 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. stands on 678 sq m of land (about 0.2 acres), with 678 sq m of sanctioned built-up area and 20 sq m of recreational open space.
Where can I read reviews of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?
Google Maps has reviews of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?
PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. by ARJUNSINGH BHOORSINGH RATHORE is in Vile Parle West, Mumbai (pincode 400058), Maharashtra, and is registered on MahaRERA as P51800021193, per GharKundli's check of MahaRERA records. Its boundaries filed there include GULMOHAR ROAD, CP GOENKA INTERNATIONAL SCHOOL.
How many homes are in PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. has 28 homes in 1 tower registered on MahaRERA, and 21% of them are sold or booked.
When was PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. was registered on MahaRERA on 14 June 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?
No court cases are listed for PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARJUNSINGH BHOORSINGH RATHORE.
Check it yourself on MahaRERA
- How to check the possession date of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Vile Parle West
- VEER ELEGANCE
- New Brindavan CHSL
- PARSHWA DARSHAN CO OPERATIVE HOUSING SOCIETY LIMITED
- TULSIDHAM CHS
- PRAMUKH SHRINIKET APARTMENTS
- SHAGUN RESIDENCY
- DURGA GAYATRI
- ZEE TULSI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.