Manisha Corporate Park
by GOVINDRAJULU PAPA NAIDU · Mulund West, Mumbai 400080Also near Mulund East, Bhandup West, Wagle I.E
What’s in the report? →Possession date of Manisha Corporate Park (MahaRERA P51800021382): 30 April 2028, moved from 9 June 2025 (30 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800021382, and currently active. Its completion date has moved from June 2025 to April 2028: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800021382, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Manisha Corporate Park?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Manisha Corporate Park has moved
9 June 2025
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EXT51800028387)
Reason the builder gave MahaRERA:
“I/ We, Govindrajulu Papa Naidu, the promoter of the project Manisha Corporate Park (Registration No. P51800021382) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We apologize for the de…” Read the full reason
“I/ We, Govindrajulu Papa Naidu, the promoter of the project Manisha Corporate Park (Registration No. P51800021382) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We hereby declare that we have received the Occ…”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Manisha Corporate Park’s extension records on MahaRERA (P51800021382), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Manisha Corporate Park
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800021382
- Status
- Registered and active
- Builder
- GOVINDRAJULU PAPA NAIDU
- Location
- Mulund West, Mumbai · 400080
- Project type
- Commercial
- Registered on
- 24 Jun 2019
- Completion date at registration
- June 2025
- Latest completion date
- April 2028
- Delay so far
- 30 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 62%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Manisha Corporate Park, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MANISHA CORPORATE PARK | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- MANISHA CORPORATE PARK: covers 20 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Manisha Corporate Park every 1–2 months.
Manisha Corporate Park: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 217 – 621 | 177 |
| Shops | 85 – 705 | 10 |
- Buildings: MANISHA CORPORATE PARK (25 floors, 187 units)
- Land: 1,590 sq m (about 0.4 acres) · sanctioned built-up 7,979 sq m · recreational space 264 sq m
- Boundaries filed include: MAHATMA GANDHI ROAD
- Land, as filed: CTS 1147, 1147/1 TO 19
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Govind Papa Naidu has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 1 months late). No complaints on MahaRERA.
Read Google reviews of Manisha Corporate Park →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Manisha Corporate Park: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Manisha Corporate Park
What is the possession date of Manisha Corporate Park?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Manisha Corporate Park in Mulund West, Mumbai is 30 April 2028 — 30 months later than 9 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 30 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Manisha Corporate Park?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Manisha Corporate Park's builder has filed on MahaRERA, the official one, is 30 April 2028, already 30 months later than the 9 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Manisha Corporate Park extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Manisha Corporate Park's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "I/ We, Govindrajulu Papa Naidu, the promoter of the project Manisha Corporate Park (Registration No. P51800021382) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We hereby declare that we have received the Occ…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Manisha Corporate Park?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Manisha Corporate Park in Mulund West, Mumbai is P51800021382.
Is Manisha Corporate Park registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Manisha Corporate Park is registered as P51800021382 and its status is "Registered and active".
What is the current construction status of Manisha Corporate Park? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Manisha Corporate Park's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MANISHA CORPORATE PARK is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Manisha Corporate Park have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Manisha Corporate Park safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Manisha Corporate Park is registered on MahaRERA as P51800021382, its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Manisha Corporate Park?
Manisha Corporate Park is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Manisha Corporate Park?
For a flat in Manisha Corporate Park (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Manisha Corporate Park received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Manisha Corporate Park is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Manisha Corporate Park a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Manisha Corporate Park is a redevelopment: 15 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Manisha Corporate Park uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Manisha Corporate Park was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Manisha Corporate Park's possession date changes?
The latest dates are on Manisha Corporate Park's MahaRERA page (P51800021382). GharKundli's Kundli Watch sends a free WhatsApp update on Manisha Corporate Park every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Manisha Corporate Park have?
According to GharKundli's check of MahaRERA records (updated October 2026), Manisha Corporate Park has one building filed: MANISHA CORPORATE PARK with 25 floors and 187 units.
How big is the land of Manisha Corporate Park?
According to GharKundli's check of MahaRERA records (updated October 2026), Manisha Corporate Park stands on 1,590 sq m of land (about 0.4 acres), with 7,979 sq m of sanctioned built-up area and 264 sq m of recreational open space.
What is the track record of Manisha Corporate Park's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Govind Papa Naidu has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 1 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Manisha Corporate Park?
Google Maps has reviews of Manisha Corporate Park written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Manisha Corporate Park?
Manisha Corporate Park by GOVINDRAJULU PAPA NAIDU is in Mulund West, Mumbai, pincode 400080 (near Mulund East, Bhandup West, Wagle I.E), Maharashtra, and is registered on MahaRERA as P51800021382, per GharKundli's check of MahaRERA records. Its boundaries filed there include MAHATMA GANDHI ROAD. Its land is filed as CTS 1147, 1147/1 TO 19. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).
How many flats are in Manisha Corporate Park, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Manisha Corporate Park has 0 homes in 1 tower registered on MahaRERA, and 62% of them are sold or booked.
When was Manisha Corporate Park registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Manisha Corporate Park was registered on MahaRERA on 24 June 2019. GharKundli did not find a title report on the land on file there.
Does Manisha Corporate Park have any legal issues or court cases?
No court cases are listed for Manisha Corporate Park on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Manisha Corporate Park?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GOVINDRAJULU PAPA NAIDU, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Manisha Corporate Park
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Mulund West (400080)
- Malhar Guide
- Arihant Royale
- The Sanctuary - Tower 5
- Keshavpada
- Dhanraj Tower
- Mulund Mahavirdham Co. Op. Housing Soc. LTD.
- Madhuvan Nivanta
- Shraddha Paradise Enclave
Other projects by GOVINDRAJULU PAPA NAIDU
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.