Shagun Krishvi Apartments

by M/s Shagun Construction · Girgaon, Mumbai 400004Also near Khetwadi, Grant Road, BhuleshwarRegistered on MahaRERA as “Krishvi Apartments”

What’s in the report? →

Possession: Shagun Krishvi Apartments (MahaRERA P51900004145) is marked completed on MahaRERA. It has 82 homes (1 BHK, 2 BHK and 3 BHK, 355–991 sq ft carpet), 100% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900004145. Status: Completed.

Source: MahaRERA website — records for P51900004145, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Shagun Krishvi Apartments?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shagun Krishvi Apartments has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT51900006367)

    Reason the builder gave MahaRERA:
    “The reason for delay is Property Card is not updated by the concerned authority. Due to this, MHADA is not issuing NOC to Occupation Certificate. We have received Part Occupation Certificate on 31st December, 2018 but MCGM needs NOC to Occu…” Read the full reason“The reason for delay is Property Card is not updated by the concerned authority. Due to this, MHADA is not issuing NOC to Occupation Certificate. We have received Part Occupation Certificate on 31st December, 2018 but MCGM needs NOC to Occupation Certificate from MHADA to issue Full Occupation Certificate. We had applied for updating the Property Card in our name on 4th September, 2013 which did not process ahead. Later we applied for updating the property card on 9th October, 2018 and a regular follow up is been done by our office for the same. We are expecting the Property card to be upda…”
  3. 21 August 2025

    Extended at the builder's request (MahaRERA application EA27042620750)

    Reason the builder gave MahaRERA: “as per application enlcosed”

Source: Shagun Krishvi Apartments’s extension records on MahaRERA (P51900004145), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shagun Krishvi Apartments

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the August 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900004145
Status
Completed
Builder
M/s Shagun Construction
Location
Girgaon, Mumbai · 400004
Project type
Others
Registered on
8 Aug 2017
Completion date at registration
December 2018
Latest completion date
August 2025
Delay so far
80 months
Homes
82
Sold or booked
100%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Shagun Krishvi Apartments, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Krishvi Apartments A Wing100%100%100%100%
Krishvi Apartments B Wing100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Krishvi Apartments A Wing: covers 24 floors
  • Krishvi Apartments B Wing: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shagun Krishvi Apartments every 1–2 months.

Shagun Krishvi Apartments: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK355 – 59061
2 BHK548 – 81215
Shops129 – 60112
3 BHK692 – 9916

The builder’s record and reviews

Shagun Associates (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 79 months); 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Shagun Krishvi Apartments →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shagun Krishvi Apartments: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shagun Krishvi Apartments

What is the possession date of Shagun Krishvi Apartments?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shagun Krishvi Apartments in Girgaon, Mumbai is 21 August 2025 — 80 months later than 31 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Shagun Krishvi Apartments?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shagun Krishvi Apartments's builder has filed on MahaRERA, the official one, is 21 August 2025, already 80 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shagun Krishvi Apartments extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Apartments's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2020, giving the reason "The reason for delay is Property Card is not updated by the concerned authority. Due to this, MHADA is not issuing NOC to Occupation Certificate. We have received Part Occupation Certificate on 31st December, 2018 but MCGM needs NOC to Occupation Certificate from MHADA to issue Full Occupation Certificate. We had applied for updating the Property Card in our name on 4th September, 2013 which did not process ahead. Later we applied for updating the property card on 9th October, 2018 and a regular follow up is been done by our office for the same. We are expecting the Property card to be upda…"; to 21 August 2025, giving the reason "as per application enlcosed".

What is the RERA number of Shagun Krishvi Apartments?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shagun Krishvi Apartments in Girgaon, Mumbai is P51900004145.

Is Shagun Krishvi Apartments registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Apartments is registered as P51900004145 and its status is "Completed".

What is the current construction status of Shagun Krishvi Apartments? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Apartments's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Shagun Krishvi Apartments have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shagun Krishvi Apartments safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Apartments is registered on MahaRERA as P51900004145, its MahaRERA status is "Completed", its completion date has moved 80 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shagun Krishvi Apartments?

According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Apartments is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Shagun Krishvi Apartments?

For a flat in Shagun Krishvi Apartments (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Shagun Krishvi Apartments received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Apartments is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Shagun Krishvi Apartments completed?

According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Apartments is marked completed on MahaRERA, and the completion date filed there is 21 August 2025. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Is Shagun Krishvi Apartments a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Apartments is a redevelopment: 50 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Shagun Krishvi Apartments uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shagun Krishvi Apartments was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shagun Krishvi Apartments's possession date changes?

The latest dates are on Shagun Krishvi Apartments's MahaRERA page (P51900004145). GharKundli's Kundli Watch sends a free WhatsApp update on Shagun Krishvi Apartments every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shagun Krishvi Apartments have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Apartments has 2 buildings filed: Krishvi Apartments A Wing with 24 floors and 77 units; Krishvi Apartments B Wing with 9 floors and 17 units.

What are the flat sizes (carpet area) in Shagun Krishvi Apartments?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shagun Krishvi Apartments: 1 BHK: 355 to 590 sq ft carpet (61 homes); 2 BHK: 548 to 812 sq ft carpet (15 homes); 3 BHK: 692 to 991 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Shagun Krishvi Apartments?

According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Apartments stands on 888 sq m of land (about 0.2 acres), with 4,789 sq m of sanctioned built-up area.

What is the track record of Shagun Krishvi Apartments's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Associates (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 79 months); 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shagun Krishvi Apartments?

Google Maps has reviews of Shagun Krishvi Apartments written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shagun Krishvi Apartments?

Shagun Krishvi Apartments by M/s Shagun Construction is in Girgaon, Mumbai, pincode 400004 (near Khetwadi, Grant Road, Bhuleshwar), Maharashtra, and is registered on MahaRERA as P51900004145, per GharKundli's check of MahaRERA records. Its land is filed as 829, 830. GharKundli lists all 79 MahaRERA projects in Girgaon (400004).

How many flats are in Shagun Krishvi Apartments, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Apartments has 82 homes in 2 towers registered on MahaRERA, and 100% of them are sold or booked.

When was Shagun Krishvi Apartments registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Apartments was registered on MahaRERA on 8 August 2017. GharKundli did not find a title report on the land on file there.

Does Shagun Krishvi Apartments have any legal issues or court cases?

No court cases are listed for Shagun Krishvi Apartments on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shagun Krishvi Apartments?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s Shagun Construction.

Other projects in Girgaon (400004)

All 79 projects in Girgaon (400004) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.