Geecee Laxmi Kunj
by GeeCee Ventures Limited · Juhu, Mumbai 400049Also near Vile Parle West, JVPD Scheme, Vile Parle EastRegistered on MahaRERA as “Laxmi Kunj”
What’s in the report? →Possession: Geecee Laxmi Kunj (MahaRERA P51800046721) is marked completed on MahaRERA. It has 6 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800046721. Status: Completed.
Source: MahaRERA website — records for P51800046721, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Geecee Laxmi Kunj?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on Geecee Laxmi Kunj
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800046721
- Status
- Completed
- Builder
- GeeCee Ventures Limited
- Location
- Juhu, Mumbai · 400049
- Project type
- Residential / Group Housing
- Registered on
- 1 Sep 2022
- Completion date at registration
- December 2024
- Homes
- 6
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 10
Construction progress of Geecee Laxmi Kunj, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| LAXMI KUNJ | 100% | 100% | 95% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Geecee Laxmi Kunj every 1–2 months.
Geecee Laxmi Kunj: buildings, flats and land, as filed on MahaRERA
- Buildings: LAXMI KUNJ (10 floors)
- Land: 502 sq m (about 0.1 acres) · sanctioned built-up 1,626 sq m
- Boundaries filed include: EAST WEST ROAD NUMBER 2, NORTH SOUTH ROAD NUMBER 8
- Land, as filed: 737
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Geecee Ventures has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 7 finished, all within the promised date; 4 still being built, none past the promised date yet. 2 complaints on MahaRERA across 1 project.
Read Google reviews of Geecee Laxmi Kunj →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Geecee Laxmi Kunj: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Geecee Laxmi Kunj
What is the possession date of Geecee Laxmi Kunj?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Geecee Laxmi Kunj in Juhu, Mumbai is 31 December 2024.
Is the builder's possession date different from the MahaRERA date for Geecee Laxmi Kunj?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Geecee Laxmi Kunj's builder has filed on MahaRERA, the official one, is 31 December 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Geecee Laxmi Kunj?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Geecee Laxmi Kunj in Juhu, Mumbai is P51800046721.
Is Geecee Laxmi Kunj registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Geecee Laxmi Kunj is registered as P51800046721 and its status is "Completed".
What is the current construction status of Geecee Laxmi Kunj? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Geecee Laxmi Kunj's status on MahaRERA is "Completed". As filed by the builder, slab work on LAXMI KUNJ is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Geecee Laxmi Kunj have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Geecee Laxmi Kunj safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Geecee Laxmi Kunj is registered on MahaRERA as P51800046721, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Geecee Laxmi Kunj?
According to GharKundli's check of MahaRERA records (updated October 2026), Geecee Laxmi Kunj is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in Geecee Laxmi Kunj?
For a flat in Geecee Laxmi Kunj (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Geecee Laxmi Kunj received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated October 2026), Geecee Laxmi Kunj is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was Geecee Laxmi Kunj completed?
According to GharKundli's check of MahaRERA records (updated October 2026), Geecee Laxmi Kunj is marked completed on MahaRERA, and the completion date filed there is 31 December 2024. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Is Geecee Laxmi Kunj a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Geecee Laxmi Kunj's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Geecee Laxmi Kunj uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Geecee Laxmi Kunj was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Geecee Laxmi Kunj's possession date changes?
The latest dates are on Geecee Laxmi Kunj's MahaRERA page (P51800046721). GharKundli's Kundli Watch sends a free WhatsApp update on Geecee Laxmi Kunj every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Geecee Laxmi Kunj have?
According to GharKundli's check of MahaRERA records (updated October 2026), Geecee Laxmi Kunj has one building filed: LAXMI KUNJ with 10 floors.
How big is the land of Geecee Laxmi Kunj?
According to GharKundli's check of MahaRERA records (updated October 2026), Geecee Laxmi Kunj stands on 502 sq m of land (about 0.1 acres), with 1,626 sq m of sanctioned built-up area.
What is the track record of Geecee Laxmi Kunj's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Geecee Ventures has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 7 finished, all within the promised date; 4 still being built, none past the promised date yet. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Geecee Laxmi Kunj?
Google Maps has reviews of Geecee Laxmi Kunj written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Geecee Laxmi Kunj?
Geecee Laxmi Kunj by GeeCee Ventures Limited is in Juhu, Mumbai, pincode 400049 (near Vile Parle West, JVPD Scheme, Vile Parle East), Maharashtra, and is registered on MahaRERA as P51800046721, per GharKundli's check of MahaRERA records. Its boundaries filed there include EAST WEST ROAD NUMBER 2, NORTH SOUTH ROAD NUMBER 8. Its land is filed as 737. GharKundli lists all 78 MahaRERA projects in Juhu (400049).
How many flats are in Geecee Laxmi Kunj?
According to GharKundli's check of MahaRERA records (updated October 2026), Geecee Laxmi Kunj has 6 homes in 1 tower registered on MahaRERA.
When was Geecee Laxmi Kunj registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Geecee Laxmi Kunj was registered on MahaRERA on 1 September 2022. GharKundli did not find a title report on the land on file there.
Does Geecee Laxmi Kunj have any legal issues or court cases?
No court cases are listed for Geecee Laxmi Kunj on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Geecee Laxmi Kunj?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GeeCee Ventures Limited, which has 10 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Geecee Laxmi Kunj
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Juhu (400049)
All 78 projects in Juhu (400049) →Other projects by GeeCee Ventures Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.