Transcon Triumph Tower 2
by Transcon Triumph Phase 2 Private Limited · Andheri West, MumbaiAlso near Vesava, Andheri Railway Station, Jogeshwari West
Possession date of Transcon Triumph Tower 2: 30 June 2027, moved from 30 June 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800027978, and currently active. 22 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Transcon Triumph Tower 2?
How the possession date of Transcon Triumph Tower 2 has moved
30 June 2026
Completion date given when the project was registered
30 June 2027
Extended at the builder's request (MahaRERA application EA26062621554)
Reason the builder gave MahaRERA:
“Submission of Technical Reasons for Delay In Completion of the Project "Transcon Triumph Tower 2", Maha RERA Reg. No P51800027978. Respected Sir, We, M/S Transcon Developers Private Limited (Formerly known as Transcon Triumph Phase 2 Pvt Lt…” Read the full reason
“Submission of Technical Reasons for Delay In Completion of the Project "Transcon Triumph Tower 2", Maha RERA Reg. No P51800027978. Respected Sir, We, M/S Transcon Developers Private Limited (Formerly known as Transcon Triumph Phase 2 Pvt Ltd), are the promoters of the real estate project known as "Transcon Triumph Tower 2" bearing Maha RERA Registration No. P51800027978. Reason The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. We have been grappled with shortage of labour and…”
Source: Transcon Triumph Tower 2’s extension records on MahaRERA (P51800027978), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Transcon Triumph Tower 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 22 complaints and 21 court cases, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Transcon Triumph Tower 1P51800005361 · possession 30 Dec 2022
- Transcon Triumph Tower 3P51800030321 · possession 30 Jan 2027
- Transcon Triumph Tower 4P51800034924 · possession 31 Jul 2027
- MahaRERA registration
- P51800027978
- Status
- Registered and active
- Builder
- Transcon Triumph Phase 2 Private Limited
- Location
- Andheri West, Mumbai · 400053
- Project type
- Residential / Group Housing
- Registered on
- 21 Jan 2021
- Completion date at registration
- June 2026
- Latest completion date
- June 2027
- Delay so far
- 12 months
- Homes
- 324
- Sold or booked
- 96%
- Towers
- 1
- Complaints on MahaRERA
- 22
- Court cases listed
- 21
- Appeals at the tribunal
- 5
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Transcon Triumph Tower 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Transcon Triumph Tower 2 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Transcon Triumph Tower 2: covers This C.C. is further extended from 31st to 35th upper floor for Tower-2
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Transcon Triumph Tower 2 every month.
Transcon Triumph Tower 2: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 501 – 856 | 172 |
| 1 BHK | 376 – 397 | 96 |
| 3 BHK | 858 – 1,143 | 56 |
| Shops | 687 – 2,335 | 9 |
- Buildings: Transcon Triumph Tower 2 (42 floors, 333 units)
- Land: 1,263 sq m (about 0.3 acres) · sanctioned built-up 21,747 sq m · recreational space 1,889 sq m
The builder’s record and reviews
Transcon-sheth Creators (a group of 6 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 3 finished, all within the promised date; 10 still being built, 1 past the promised date (typically 18 months late); 3 lapsed. 144 complaints on MahaRERA across 14 projects.
Read Google reviews of Transcon Triumph Tower 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Transcon Triumph Tower 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Transcon Triumph Tower 2
What is the possession date of Transcon Triumph Tower 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Transcon Triumph Tower 2 in Andheri West, Mumbai is 30 June 2027 — 12 months later than 30 June 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Transcon Triumph Tower 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Transcon Triumph Tower 2's builder has filed on MahaRERA, the official one, is 30 June 2027, already 12 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Transcon Triumph Tower 2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Transcon Triumph Tower 2's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "Submission of Technical Reasons for Delay In Completion of the Project "Transcon Triumph Tower 2", Maha RERA Reg. No P51800027978. Respected Sir, We, M/S Transcon Developers Private Limited (Formerly known as Transcon Triumph Phase 2 Pvt Ltd), are the promoters of the real estate project known as "Transcon Triumph Tower 2" bearing Maha RERA Registration No. P51800027978. Reason The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. We have been grappled with shortage of labour and…".
What is the RERA number of Transcon Triumph Tower 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Transcon Triumph Tower 2 in Andheri West, Mumbai is P51800027978.
Is Transcon Triumph Tower 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Transcon Triumph Tower 2 is registered as P51800027978 and its status is "Registered and active".
What is the construction status of Transcon Triumph Tower 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Transcon Triumph Tower 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Transcon Triumph Tower 2 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Transcon Triumph Tower 2 have complaints on MahaRERA?
22 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Transcon Triumph Tower 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Transcon Triumph Tower 2 is registered on MahaRERA as P51800027978, its completion date has moved 12 months since registration and 22 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Transcon Triumph Tower 2 have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Transcon Triumph Tower 1 (P51800005361, possession 30 Dec 2022); Transcon Triumph Tower 3 (P51800030321, possession 30 Jan 2027); Transcon Triumph Tower 4 (P51800034924, possession 31 Jul 2027). Check that your agreement names the registration of your own wing.
How can I get updates if Transcon Triumph Tower 2's possession date changes?
The latest dates are on Transcon Triumph Tower 2's MahaRERA page (P51800027978). GharKundli's Kundli Watch sends a free WhatsApp update on Transcon Triumph Tower 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Transcon Triumph Tower 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Transcon Triumph Tower 2 has one building filed: Transcon Triumph Tower 2 with 42 floors and 333 units.
What are the flat sizes (carpet area) in Transcon Triumph Tower 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Transcon Triumph Tower 2: 2 BHK: 501 to 856 sq ft carpet (172 homes); 1 BHK: 376 to 397 sq ft carpet (96 homes); 3 BHK: 858 to 1143 sq ft carpet (56 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Transcon Triumph Tower 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Transcon Triumph Tower 2 stands on 1,263 sq m of land (about 0.3 acres), with 21,747 sq m of sanctioned built-up area and 1,889 sq m of recreational open space.
What is the track record of Transcon Triumph Tower 2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Transcon-sheth Creators (a group of 6 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 3 finished, all within the promised date; 10 still being built, 1 past the promised date (typically 18 months late); 3 lapsed. 144 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Transcon Triumph Tower 2?
Google Maps has reviews of Transcon Triumph Tower 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 22 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Transcon Triumph Tower 2?
Transcon Triumph Tower 2 by Transcon Triumph Phase 2 Private Limited is in Andheri West, Mumbai (pincode 400053), near Vesava, Andheri Railway Station, Jogeshwari West, Maharashtra, and is registered on MahaRERA as P51800027978, per GharKundli's check of MahaRERA records.
How many homes are in Transcon Triumph Tower 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Transcon Triumph Tower 2 has 324 homes in 1 tower registered on MahaRERA, and 96% of them are sold or booked.
When was Transcon Triumph Tower 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Transcon Triumph Tower 2 was registered on MahaRERA on 21 January 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Transcon Triumph Tower 2?
21 court cases are listed for Transcon Triumph Tower 2 on MahaRERA, and 5 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Transcon Triumph Tower 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Transcon Triumph Phase 2 Private Limited, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Transcon Triumph Tower 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400053
- Parinee i
- Sunbeam Heights
- Tru Gardenia
- Gayatri Enclave
- ESTO ARKIS
- Naman Fifty Eight
- AMAHA SUNFLOWER
- FAME GARDEN
Other projects by Transcon Triumph Phase 2 Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.