Possession date of Soham Majesty (MahaRERA P51800030226): 30 December 2024, moved from 31 December 2023 (12 months later), and it has already passed. It has 16 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800030226. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800030226, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2024) has passed.

What do you want to know about Soham Majesty?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Soham Majesty has moved

  1. 31 December 2023

    Completion date given when the project was registered

  2. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT51800018895)

    Reason the builder gave MahaRERA:
    “THE PROJECT IS COMPLETED IN ALL ASPECT AS ON DATE. ALSO APPLICATION FOR PROJECT COMPLETION CERTIFICATE HAS BEEN MADE. THE PROJECT WILL RECEIVE COMPLETION CERTIFICATE FROM THE COMPETENT AUTHORITY AT THE EARLIEST. HENCE WE REQUEST YOU TO EXTE…” Read the full reason“THE PROJECT IS COMPLETED IN ALL ASPECT AS ON DATE. ALSO APPLICATION FOR PROJECT COMPLETION CERTIFICATE HAS BEEN MADE. THE PROJECT WILL RECEIVE COMPLETION CERTIFICATE FROM THE COMPETENT AUTHORITY AT THE EARLIEST. HENCE WE REQUEST YOU TO EXTEND OUR PROPOSED PROJECT COMPLETION DATE.”

Source: Soham Majesty’s extension records on MahaRERA (P51800030226), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Soham Majesty

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800030226
Status
Lapsed (registration period ended)
Builder
LAXMIKANT RAMCHANDRA SAWANT
Location
Chikuwadi, Shimpoli Village, Mumbai · 400092
Project type
Residential / Group Housing
Registered on
5 Aug 2021
Completion date at registration
December 2023
Latest completion date
December 2024
Delay so far
12 months
Homes
16
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Soham Majesty, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SOHAM MAJESTY100%100%90%80%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Soham Majesty every 1–2 months.

Soham Majesty: buildings, flats and land, as filed on MahaRERA

  • Buildings: SOHAM MAJESTY (15 floors)
  • Land: 404 sq m (about 0.1 acres) · sanctioned built-up 342 sq m
  • Land, as filed: FP NO. 535
  • Map: Get directions

The builder’s record and reviews

Laxmikant Ramchandra Sawant has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Soham Majesty →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Soham Majesty: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Soham Majesty

What is the possession date of Soham Majesty?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Soham Majesty in Chikuwadi, Shimpoli Village, Mumbai is 30 December 2024 — 12 months later than 31 December 2023, the date given at registration. That date has already passed.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Soham Majesty?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Soham Majesty's builder has filed on MahaRERA, the official one, is 30 December 2024, already 12 months later than the 31 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Soham Majesty extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Soham Majesty's builder applied to MahaRERA to extend the completion date once: to 30 December 2024, giving the reason "THE PROJECT IS COMPLETED IN ALL ASPECT AS ON DATE. ALSO APPLICATION FOR PROJECT COMPLETION CERTIFICATE HAS BEEN MADE. THE PROJECT WILL RECEIVE COMPLETION CERTIFICATE FROM THE COMPETENT AUTHORITY AT THE EARLIEST. HENCE WE REQUEST YOU TO EXTEND OUR PROPOSED PROJECT COMPLETION DATE.".

What is the RERA number of Soham Majesty?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Soham Majesty in Chikuwadi, Shimpoli Village, Mumbai is P51800030226.

Is Soham Majesty registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Soham Majesty is registered as P51800030226 and its status is "Lapsed (registration period ended)".

What is the current construction status of Soham Majesty? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Soham Majesty's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SOHAM MAJESTY is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does Soham Majesty have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Soham Majesty safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Soham Majesty is registered on MahaRERA as P51800030226, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Soham Majesty?

Soham Majesty isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Soham Majesty?

For a flat in Soham Majesty (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Soham Majesty received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Soham Majesty isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Soham Majesty?

According to GharKundli's check of MahaRERA records (updated October 2026), Soham Majesty's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Soham Majesty uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Soham Majesty was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Soham Majesty's possession date changes?

The latest dates are on Soham Majesty's MahaRERA page (P51800030226). GharKundli's Kundli Watch sends a free WhatsApp update on Soham Majesty every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Soham Majesty have?

According to GharKundli's check of MahaRERA records (updated October 2026), Soham Majesty has one building filed: SOHAM MAJESTY with 15 floors.

How big is the land of Soham Majesty?

According to GharKundli's check of MahaRERA records (updated October 2026), Soham Majesty stands on 404 sq m of land (about 0.1 acres), with 342 sq m of sanctioned built-up area.

What is the track record of Soham Majesty's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Laxmikant Ramchandra Sawant has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Soham Majesty?

Google Maps has reviews of Soham Majesty written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Soham Majesty?

Soham Majesty by LAXMIKANT RAMCHANDRA SAWANT is in Chikuwadi, Shimpoli Village, Mumbai, pincode 400092, Maharashtra, and is registered on MahaRERA as P51800030226, per GharKundli's check of MahaRERA records. Its land is filed as FP NO. 535. GharKundli lists all 362 MahaRERA projects in Borivali West (400092).

How many flats are in Soham Majesty?

According to GharKundli's check of MahaRERA records (updated October 2026), Soham Majesty has 16 homes in 1 tower registered on MahaRERA.

When was Soham Majesty registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Soham Majesty was registered on MahaRERA on 5 August 2021. GharKundli did not find a title report on the land on file there.

Does Soham Majesty have any legal issues or court cases?

No court cases are listed for Soham Majesty on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Soham Majesty?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LAXMIKANT RAMCHANDRA SAWANT, which has 2 other projects registered on MahaRERA.

Other projects in Borivali

All 362 projects in Borivali West (400092) →

Other projects by LAXMIKANT RAMCHANDRA SAWANT

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.