by Rohan Developers Pvt Ltd · Prarthna Samaj, MumbaiAlso near Girgaon, Khetwadi, Grant Road

Possession date of Lifescapes Arihant: 31 January 2025, moved from 30 June 2021 (43 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51900005185. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (January 2025) has passed.

What do you want to know about Lifescapes Arihant?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Lifescapes Arihant has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51900009653)

    Reason the builder gave MahaRERA:
    “Dear Sir, we have completed about 70 % of our super structure. However, due to the break in construction due to covid-19, we are facing several obstacles in adhering to our original timelines due to practical and financial issues due to the…” Read the full reason“Dear Sir, we have completed about 70 % of our super structure. However, due to the break in construction due to covid-19, we are facing several obstacles in adhering to our original timelines due to practical and financial issues due to the covid induced lockdowns. hence we request your goodself to kindly grant us an extension for 1 year for completion of the project.”
  3. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51900013840)

    Reason the builder gave MahaRERA: “The Project is near completion and finishing is going on at full swing. We request for the period of 6 months till 30/06/2023 and the allottees have given their consents for the same which is attached herewith for your perusal please!”
  4. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT51900016901)

    Reason the builder gave MahaRERA:
    “Due to some earlier delays in obtaining approvals from various regulatory authority at the desired timeline, the project execution has been delayed as the civil contractor demobilised number of labourers from the site. Later on, he was not…” Read the full reason“Due to some earlier delays in obtaining approvals from various regulatory authority at the desired timeline, the project execution has been delayed as the civil contractor demobilised number of labourers from the site. Later on, he was not able to remobilise the labour force as per site needs due to which the timelines for other activities of finishing, lift fitting, etc have been delayed accordingly. Now all aspects till obtaining occupation certificate have been lined up and 8 to 9 months are needed to complete the project and obtain OC. Hence Rohan Developers Pvt. Ltd. is seeking 9 month…”
  5. 31 August 2024

    Extended at the builder's request (MahaRERA application EXT51900019596)

    Reason the builder gave MahaRERA:
    “Due to some earlier delays in obtaining approvals from various regulatory authorities in the expected timelines, the project execution was already delayed. Construction activities had slowed down and had significantly impacted the project p…” Read the full reason“Due to some earlier delays in obtaining approvals from various regulatory authorities in the expected timelines, the project execution was already delayed. Construction activities had slowed down and had significantly impacted the project progress due to shortage of labour and material supply during Covid-19 Pandemic. During pandemic, the civil contractor demobilised majority of the labourers from the site. Later on, he was not able to remobilise the labour force as per site needs due to which the timelines for other activities of finishing, lift fitting, etc have been delayed accordingly.…”
  6. 31 January 2025

    Extended at the builder's request (MahaRERA application EXT51900025286)

    Reason the builder gave MahaRERA:
    “Over the past nine months, a significant number of Government Staffs were assigned to election duties for the Lok Sabha and Maharashtra Assembly Elections. As a result, there has been a shortage of staff in various government departments, c…” Read the full reason“Over the past nine months, a significant number of Government Staffs were assigned to election duties for the Lok Sabha and Maharashtra Assembly Elections. As a result, there has been a shortage of staff in various government departments, causing delays in obtaining the required approval including Occupation Certificate within the expected timeline. The construction of Project Lifescapes Arihant is nearly completed. Currently, we are actively working to obtain the Occupation Certificate and anticipate completing the project within the next three months. In light of this, Rohan Developers Pv…”

Source: Lifescapes Arihant’s extension records on MahaRERA (P51900005185), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Lifescapes Arihant

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the January 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900005185
Status
Lapsed (registration period ended)
Builder
Rohan Developers Pvt Ltd
Location
Prarthna Samaj, Mumbai · 400004
Project type
Residential / Group Housing
Registered on
10 Aug 2017
Completion date at registration
June 2021
Latest completion date
January 2025
Delay so far
43 months
Homes
61
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Lifescapes Arihant, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Lifescapes Arihant94%100%100%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lifescapes Arihant every month.

Lifescapes Arihant: buildings, flats and land, as filed on MahaRERA

  • Buildings: Lifescapes Arihant (26 floors)
  • Land: 1,406 sq m (about 0.3 acres) · sanctioned built-up 9,183 sq m · recreational space 92 sq m
  • Boundaries filed include: Vithalbhai Patel Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Rohan Developers (a group of 3 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 18 months); 3 lapsed. 26 complaints on MahaRERA across 4 projects.

Read Google reviews of Lifescapes Arihant →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Lifescapes Arihant: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Lifescapes Arihant

What is the possession date of Lifescapes Arihant?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lifescapes Arihant in Prarthna Samaj, Mumbai is 31 January 2025 — 43 months later than 30 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Lifescapes Arihant?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Lifescapes Arihant's builder has filed on MahaRERA, the official one, is 31 January 2025, already 43 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Lifescapes Arihant extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Arihant's builder applied to MahaRERA to extend the completion date 5 times: to 30 June 2022, giving the reason "Dear Sir, we have completed about 70 % of our super structure. However, due to the break in construction due to covid-19, we are facing several obstacles in adhering to our original timelines due to practical and financial issues due to the covid induced lockdowns. hence we request your goodself to kindly grant us an extension for 1 year for completion of the project."; to 30 June 2023, giving the reason "The Project is near completion and finishing is going on at full swing. We request for the period of 6 months till 30/06/2023 and the allottees have given their consents for the same which is attached herewith for your perusal please!"; to 31 March 2024, giving the reason "Due to some earlier delays in obtaining approvals from various regulatory authority at the desired timeline, the project execution has been delayed as the civil contractor demobilised number of labourers from the site. Later on, he was not able to remobilise the labour force as per site needs due to which the timelines for other activities of finishing, lift fitting, etc have been delayed accordingly. Now all aspects till obtaining occupation certificate have been lined up and 8 to 9 months are needed to complete the project and obtain OC. Hence Rohan Developers Pvt. Ltd. is seeking 9 month…"; to 31 August 2024, giving the reason "Due to some earlier delays in obtaining approvals from various regulatory authorities in the expected timelines, the project execution was already delayed. Construction activities had slowed down and had significantly impacted the project progress due to shortage of labour and material supply during Covid-19 Pandemic. During pandemic, the civil contractor demobilised majority of the labourers from the site. Later on, he was not able to remobilise the labour force as per site needs due to which the timelines for other activities of finishing, lift fitting, etc have been delayed accordingly.…"; to 31 January 2025, giving the reason "Over the past nine months, a significant number of Government Staffs were assigned to election duties for the Lok Sabha and Maharashtra Assembly Elections. As a result, there has been a shortage of staff in various government departments, causing delays in obtaining the required approval including Occupation Certificate within the expected timeline. The construction of Project Lifescapes Arihant is nearly completed. Currently, we are actively working to obtain the Occupation Certificate and anticipate completing the project within the next three months. In light of this, Rohan Developers Pv…".

What is the RERA number of Lifescapes Arihant?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lifescapes Arihant in Prarthna Samaj, Mumbai is P51900005185.

Is Lifescapes Arihant registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Arihant is registered as P51900005185 and its status is "Lapsed (registration period ended)".

What is the construction status of Lifescapes Arihant?

According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Arihant's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Lifescapes Arihant is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Lifescapes Arihant have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Lifescapes Arihant safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Arihant is registered on MahaRERA as P51900005185, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 43 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Lifescapes Arihant's possession date changes?

The latest dates are on Lifescapes Arihant's MahaRERA page (P51900005185). GharKundli's Kundli Watch sends a free WhatsApp update on Lifescapes Arihant every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Lifescapes Arihant have?

According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Arihant has one building filed: Lifescapes Arihant with 26 floors.

How big is the land of Lifescapes Arihant?

According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Arihant stands on 1,406 sq m of land (about 0.3 acres), with 9,183 sq m of sanctioned built-up area and 92 sq m of recreational open space.

What is the track record of Lifescapes Arihant's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Rohan Developers (a group of 3 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 18 months); 3 lapsed. 26 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Lifescapes Arihant?

Google Maps has reviews of Lifescapes Arihant written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Lifescapes Arihant?

Lifescapes Arihant by Rohan Developers Pvt Ltd is in Prarthna Samaj, Mumbai (pincode 400004), near Girgaon, Khetwadi, Grant Road, Maharashtra, and is registered on MahaRERA as P51900005185, per GharKundli's check of MahaRERA records. Its boundaries filed there include Vithalbhai Patel Road.

How many homes are in Lifescapes Arihant?

According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Arihant has 61 homes in 1 tower registered on MahaRERA.

When was Lifescapes Arihant registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Arihant was registered on MahaRERA on 10 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Lifescapes Arihant?

No court cases are listed for Lifescapes Arihant on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Lifescapes Arihant?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Rohan Developers Pvt Ltd, which has 2 other projects registered on MahaRERA.