Shagun Krishvi Heights
by M/s Shagun Associates · Girgaum, Mumbai 400004Also near Khetwadi, Grant Road, BhuleshwarRegistered on MahaRERA as “Krishvi Heights”
What’s in the report? →Possession date of Shagun Krishvi Heights (MahaRERA P51900004674): 31 August 2026, moved from 31 December 2019 (80 months later), and it has already passed. It has 109 homes (1 BHK, 2 BHK and 3 BHK, 385–1862 sq ft carpet), 87% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900004674. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51900004674, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (August 2026) has passed.
What do you want to know about Shagun Krishvi Heights?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shagun Krishvi Heights has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51900005893)
Reason the builder gave MahaRERA: “We have applied for change of name in PROPERTY CARD, the same is pending before the concerned authorities till date.”
31 December 2022
Extended at the builder's request (MahaRERA application EXT51900011991)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 76% allottees for purpose of extension of RERA registration period of the said project.”31 August 2026
Extended at the builder's request (MahaRERA application EA05062621253)
Reason the builder gave MahaRERA: “The project has received OC on 21-11-2025. The delay was due to various reason as given in application”
Source: Shagun Krishvi Heights’s extension records on MahaRERA (P51900004674), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shagun Krishvi Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900004674
- Status
- Lapsed (registration period ended)
- Builder
- M/s Shagun Associates
- Location
- Girgaum, Mumbai · 400004
- Project type
- Others
- Registered on
- 9 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- August 2026
- Delay so far
- 80 months
- Homes
- 109
- Sold or booked
- 87%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shagun Krishvi Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Krishvi Heights | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Krishvi Heights: covers 44 floors
Latest CC order on MahaRERA: dated 29/10/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shagun Krishvi Heights every 1–2 months.
Shagun Krishvi Heights: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 385 – 632 | 63 |
| 2 BHK | 546 – 922 | 24 |
| 3 BHK | 746 – 1,677 | 19 |
| Shops | 76 – 1,127 | 13 |
| Office Space | 182 – 618 | 8 |
| 4 BHK | 1,295 – 1,862 | 3 |
- Buildings: Krishvi Heights (44 floors, 130 units)
- Car parking: 69 covered
- Land: 1,105 sq m (about 0.3 acres) · sanctioned built-up 8,504 sq m
- Land, as filed: 592, 1-592
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Shagun Associates (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 79 months); 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Shagun Krishvi Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shagun Krishvi Heights: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shagun Krishvi Heights
What is the possession date of Shagun Krishvi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shagun Krishvi Heights in Girgaum, Mumbai is 31 August 2026 — 80 months later than 31 December 2019, the date given at registration. That date has already passed.
The date has already moved 80 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shagun Krishvi Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shagun Krishvi Heights's builder has filed on MahaRERA, the official one, is 31 August 2026, already 80 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shagun Krishvi Heights extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Heights's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "We have applied for change of name in PROPERTY CARD, the same is pending before the concerned authorities till date."; to 31 December 2022, giving the reason "In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 76% allottees for purpose of extension of RERA registration period of the said project."; to 31 August 2026, giving the reason "The project has received OC on 21-11-2025. The delay was due to various reason as given in application".
What is the RERA number of Shagun Krishvi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shagun Krishvi Heights in Girgaum, Mumbai is P51900004674.
Is Shagun Krishvi Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Heights is registered as P51900004674 and its status is "Lapsed (registration period ended)".
What is the current construction status of Shagun Krishvi Heights? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Heights's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Krishvi Heights is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Shagun Krishvi Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shagun Krishvi Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Heights is registered on MahaRERA as P51900004674, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 80 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shagun Krishvi Heights?
Shagun Krishvi Heights isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shagun Krishvi Heights are 385 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shagun Krishvi Heights?
For a flat in Shagun Krishvi Heights (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shagun Krishvi Heights received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Heights isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 August 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Shagun Krishvi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Heights's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 August 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is Shagun Krishvi Heights a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Heights is a redevelopment: 99 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Shagun Krishvi Heights uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shagun Krishvi Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shagun Krishvi Heights's possession date changes?
The latest dates are on Shagun Krishvi Heights's MahaRERA page (P51900004674). GharKundli's Kundli Watch sends a free WhatsApp update on Shagun Krishvi Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shagun Krishvi Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Heights has one building filed: Krishvi Heights with 44 floors and 130 units.
What are the flat sizes (carpet area) in Shagun Krishvi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shagun Krishvi Heights: 1 BHK: 385 to 632 sq ft carpet (63 homes); 2 BHK: 546 to 922 sq ft carpet (24 homes); 3 BHK: 746 to 1677 sq ft carpet (19 homes); 4 BHK: 1295 to 1862 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Shagun Krishvi Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 69 covered car parking spaces for Shagun Krishvi Heights.
How big is the land of Shagun Krishvi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Heights stands on 1,105 sq m of land (about 0.3 acres), with 8,504 sq m of sanctioned built-up area.
What is the track record of Shagun Krishvi Heights's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Associates (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 79 months); 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Shagun Krishvi Heights?
Google Maps has reviews of Shagun Krishvi Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shagun Krishvi Heights?
Shagun Krishvi Heights by M/s Shagun Associates is in Girgaum, Mumbai, pincode 400004 (near Khetwadi, Grant Road, Bhuleshwar), Maharashtra, and is registered on MahaRERA as P51900004674, per GharKundli's check of MahaRERA records. Its land is filed as 592, 1-592. GharKundli lists all 79 MahaRERA projects in Girgaon (400004).
How many flats are in Shagun Krishvi Heights, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Heights has 109 homes in 1 tower registered on MahaRERA, and 87% of them are sold or booked.
When was Shagun Krishvi Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shagun Krishvi Heights was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Does Shagun Krishvi Heights have any legal issues or court cases?
No court cases are listed for Shagun Krishvi Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shagun Krishvi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s Shagun Associates.
Check it yourself on MahaRERA
- How to check the possession date of Shagun Krishvi Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai City →
Other projects in Girgaon (400004)
- Mehta Sunshine Heights B Wing
- Annapurna Sadan
- Shakuntala Sadan
- Dream Residency
- Meadows
- Onyx
- Aaditya Luxuria
- Mahajan Wadi
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.