JPV Pratap Royale

by JPV PEARL LLP · Jogeshwari west, Mumbai 400102Also near Oshiwara, Goregaon West, Andheri WestRegistered on MahaRERA as “Pratap Royale”

What’s in the report? →

Possession date of JPV Pratap Royale (MahaRERA P51800029504): 30 June 2025, moved from 31 December 2024 (6 months later), and it has already passed. It has 21 homes (2 BHK and 3 BHK, 527–932 sq ft carpet), 89% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800029504. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800029504, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2025) has passed.

What do you want to know about JPV Pratap Royale?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of JPV Pratap Royale has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800027247)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints.…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 30-06-2025 t…”

Source: JPV Pratap Royale’s extension records on MahaRERA (P51800029504), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on JPV Pratap Royale

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800029504
Status
Lapsed (registration period ended)
Builder
JPV PEARL LLP
Location
Jogeshwari west, Mumbai · 400102
Project type
Residential / Group Housing
Registered on
4 Jun 2021
Completion date at registration
December 2024
Latest completion date
June 2025
Delay so far
6 months
Homes
21
Sold or booked
89%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of JPV Pratap Royale, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Pratap Royale100%100%100%90%

Commencement certificate (CC), as filed on MahaRERA

  • Pratap Royale: covers 12 (Ground + 12 Upper Floors)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on JPV Pratap Royale every 1–2 months.

JPV Pratap Royale: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK527 – 69120
3 BHK9321

The builder’s record and reviews

JPV Pearl has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 15 months late). No complaints on MahaRERA.

Read Google reviews of JPV Pratap Royale →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

JPV Pratap Royale: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about JPV Pratap Royale

What is the possession date of JPV Pratap Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for JPV Pratap Royale in Jogeshwari west, Mumbai is 30 June 2025 — 6 months later than 31 December 2024, the date given at registration. That date has already passed.

The date has already moved 6 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for JPV Pratap Royale?

Builders and listing sites often quote an earlier "target" date for handover. The completion date JPV Pratap Royale's builder has filed on MahaRERA, the official one, is 30 June 2025, already 6 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of JPV Pratap Royale extended?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Royale's builder applied to MahaRERA to extend the completion date once: to 30 June 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 30-06-2025 t…".

What is the RERA number of JPV Pratap Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of JPV Pratap Royale in Jogeshwari west, Mumbai is P51800029504.

Is JPV Pratap Royale registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Royale is registered as P51800029504 and its status is "Lapsed (registration period ended)".

What is the current construction status of JPV Pratap Royale? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Royale's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Pratap Royale is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does JPV Pratap Royale have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is JPV Pratap Royale safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Royale is registered on MahaRERA as P51800029504, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in JPV Pratap Royale?

JPV Pratap Royale isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in JPV Pratap Royale are 527 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in JPV Pratap Royale?

For a flat in JPV Pratap Royale (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has JPV Pratap Royale received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Royale isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for JPV Pratap Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Royale's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Is JPV Pratap Royale a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Royale is a redevelopment: 12 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has JPV Pratap Royale uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for JPV Pratap Royale was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if JPV Pratap Royale's possession date changes?

The latest dates are on JPV Pratap Royale's MahaRERA page (P51800029504). GharKundli's Kundli Watch sends a free WhatsApp update on JPV Pratap Royale every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does JPV Pratap Royale have?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Royale has one building filed: Pratap Royale with 13 floors and 21 units.

What are the flat sizes (carpet area) in JPV Pratap Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for JPV Pratap Royale: 2 BHK: 527 to 691 sq ft carpet (20 homes); 3 BHK: 932 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of JPV Pratap Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Royale stands on 507 sq m of land (about 0.1 acres), with 616 sq m of sanctioned built-up area.

What is the track record of JPV Pratap Royale's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pearl has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 15 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of JPV Pratap Royale?

Google Maps has reviews of JPV Pratap Royale written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of JPV Pratap Royale?

JPV Pratap Royale by JPV PEARL LLP is in Jogeshwari west, Mumbai, pincode 400102 (near Oshiwara, Goregaon West, Andheri West), Maharashtra, and is registered on MahaRERA as P51800029504, per GharKundli's check of MahaRERA records. Its land is filed as 248-2. GharKundli lists all 117 MahaRERA projects in Jogeshwari West (400102).

How many flats are in JPV Pratap Royale, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Royale has 21 homes in 1 tower registered on MahaRERA, and 89% of them are sold or booked.

When was JPV Pratap Royale registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Royale was registered on MahaRERA on 4 June 2021. GharKundli did not find a title report on the land on file there.

Does JPV Pratap Royale have any legal issues or court cases?

No court cases are listed for JPV Pratap Royale on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of JPV Pratap Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JPV PEARL LLP, which has 1 other project registered on MahaRERA.

Other projects in Jogeshwari West (400102)

All 117 projects in Jogeshwari West (400102) →

Other projects by JPV PEARL LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.