Possession: LUMIERE is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900005337. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about LUMIERE?
How the possession date of LUMIERE has moved
30 December 2020
Completion date given when the project was registered
29 September 2022
Extended at the builder's request (MahaRERA application EXT51900016485)
Reason the builder gave MahaRERA: “We have obtained occupation certificate for the entire building save & except for 17th & 18th part floor on 30th,December 2020.The full occupation certificate was received on 29th September 2022.”
Source: LUMIERE’s extension records on MahaRERA (P51900005337), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on LUMIERE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the September 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900005337
- Status
- Completed
- Builder
- NEW SIDDHARTH ENTERPRISES
- Location
- Dadar West, Mumbai · 400028
- Project type
- Others
- Registered on
- 11 Aug 2017
- Completion date at registration
- December 2020
- Latest completion date
- September 2022
- Delay so far
- 21 months
- Homes
- 56
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of LUMIERE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| LUMIERE | 100% | 80% | 50% | 10% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on LUMIERE every month.
LUMIERE: buildings, flats and land, as filed on MahaRERA
- Buildings: LUMIERE (20 floors)
- Land: 1,875 sq m (about 0.5 acres) · sanctioned built-up 2,211 sq m · recreational space 150 sq m
- Boundaries filed include: BABREKAR ROAD, GOKHALE ROAD NORTH
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
NEW Siddharth Enterprises (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 22 months). 1 complaint on MahaRERA across 1 project.
Read Google reviews of LUMIERE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
LUMIERE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about LUMIERE
What is the possession date of LUMIERE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for LUMIERE in Dadar West, Mumbai is 29 September 2022 — 21 months later than 30 December 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for LUMIERE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date LUMIERE's builder has filed on MahaRERA, the official one, is 29 September 2022, already 21 months later than the 30 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of LUMIERE extended?
According to GharKundli's check of MahaRERA records (updated November 2026), LUMIERE's builder applied to MahaRERA to extend the completion date once: to 29 September 2022, giving the reason "We have obtained occupation certificate for the entire building save & except for 17th & 18th part floor on 30th,December 2020.The full occupation certificate was received on 29th September 2022.".
What is the RERA number of LUMIERE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of LUMIERE in Dadar West, Mumbai is P51900005337.
Is LUMIERE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), LUMIERE is registered as P51900005337 and its status is "Completed".
What is the construction status of LUMIERE?
According to GharKundli's check of MahaRERA records (updated November 2026), LUMIERE's status on MahaRERA is "Completed". As filed by the builder, slab work on LUMIERE is 80% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does LUMIERE have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is LUMIERE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), LUMIERE is registered on MahaRERA as P51900005337, its MahaRERA status is "Completed", its completion date has moved 21 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if LUMIERE's possession date changes?
The latest dates are on LUMIERE's MahaRERA page (P51900005337). GharKundli's Kundli Watch sends a free WhatsApp update on LUMIERE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does LUMIERE have?
According to GharKundli's check of MahaRERA records (updated November 2026), LUMIERE has one building filed: LUMIERE with 20 floors.
How big is the land of LUMIERE?
According to GharKundli's check of MahaRERA records (updated November 2026), LUMIERE stands on 1,875 sq m of land (about 0.5 acres), with 2,211 sq m of sanctioned built-up area and 150 sq m of recreational open space.
What is the track record of LUMIERE's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), NEW Siddharth Enterprises (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 22 months). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of LUMIERE?
Google Maps has reviews of LUMIERE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is LUMIERE?
LUMIERE by NEW SIDDHARTH ENTERPRISES is in Dadar West, Mumbai (pincode 400028), near Shivaji Park, Matunga, Mahim, Maharashtra, and is registered on MahaRERA as P51900005337, per GharKundli's check of MahaRERA records. Its boundaries filed there include BABREKAR ROAD, GOKHALE ROAD NORTH.
How many homes are in LUMIERE?
According to GharKundli's check of MahaRERA records (updated November 2026), LUMIERE has 56 homes in 1 tower registered on MahaRERA.
When was LUMIERE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), LUMIERE was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on LUMIERE?
No court cases are listed for LUMIERE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of LUMIERE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NEW SIDDHARTH ENTERPRISES.
Check it yourself on MahaRERA
- How to check the possession date of LUMIERE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Dadar West
- ARYAVRAT PROJECT
- YASH TRINITY
- Sigma Garnet
- AHILYA
- VASANT PRABHA
- SAI ARADHYA
- BUILDARCH SAKURA
- SAMARTHA HEIGHTS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.