SHRISTI RESIDENCY - PHASE 1
by RANBIR REAL ESTATE AND DEVELOPERS LLP · Jogeshwari East, MumbaiAlso near Andheri East, Jvlr, Andheri West
Possession: SHRISTI RESIDENCY - PHASE 1 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800031167. Status: Completed. 38 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHRISTI RESIDENCY - PHASE 1?
How the possession date of SHRISTI RESIDENCY - PHASE 1 has moved
31 December 2024
Completion date given when the project was registered
30 December 2025
Extended at the builder's request (MahaRERA application EXT51800025256)
Reason the builder gave MahaRERA: “UNFORESEEN CIRCUMSTANCES THE PROJECT WAS NOT ABLE TO GET COMPLETED IN TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENTION TILL 31ST DECEMBER 2025.”
31 December 2026
Extended at the builder's request (MahaRERA application EA28112518461)
Reason the builder gave MahaRERA:
“The project was delayed due to an unavoidable reason that was beyond our control. Maily the road work process and other work was hampered. We requested the extension as per order 40 and got the extension order from Maharera. We have now sub…” Read the full reason
“The project was delayed due to an unavoidable reason that was beyond our control. Maily the road work process and other work was hampered. We requested the extension as per order 40 and got the extension order from Maharera. We have now submitted the order and requesting to grant us the extension as per order 40. Date of extension requested 31.12.2026”
Source: SHRISTI RESIDENCY - PHASE 1’s extension records on MahaRERA (P51800031167), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHRISTI RESIDENCY - PHASE 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 38 complaints, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800031167
- Status
- Completed
- Builder
- RANBIR REAL ESTATE AND DEVELOPERS LLP
- Location
- Jogeshwari East, Mumbai · 400060
- Project type
- Others
- Registered on
- 11 Oct 2021
- Completion date at registration
- December 2024
- Latest completion date
- December 2026
- Delay so far
- 24 months
- Homes
- 215
- Sold or booked
- 77%
- Towers
- 3
- Complaints on MahaRERA
- 38
- Court cases listed
- 0
- Appeals at the tribunal
- 16
- Title report on file
- Not found
Construction progress of SHRISTI RESIDENCY - PHASE 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHRISTI RESIDENCY - WING A | 100% | 100% | 100% | 100% |
| SHRISTI RESIDENCY - WING B | 100% | 100% | 100% | 100% |
| SHRISTI RESIDENCY - WING C | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- SHRISTI RESIDENCY - WING A: covers full cc
- SHRISTI RESIDENCY - WING B: covers 19 floors
- SHRISTI RESIDENCY - WING C: covers 19 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHRISTI RESIDENCY - PHASE 1 every month.
SHRISTI RESIDENCY - PHASE 1: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 435 – 615 | 144 |
| 1 BHK | 435 | 69 |
| Shops | 114 – 235 | 6 |
| 3 BHK | 691 – 733 | 2 |
- Buildings: SHRISTI RESIDENCY - WING A (19 floors, 76 units) · SHRISTI RESIDENCY - WING B (19 floors, 71 units) · SHRISTI RESIDENCY - WING C (19 floors, 74 units)
- Car parking: 105 covered
- Land: 2,009 sq m (about 0.5 acres) · sanctioned built-up 12,968 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SHRISTI RESIDENCY - PHASE 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHRISTI RESIDENCY - PHASE 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHRISTI RESIDENCY - PHASE 1
What is the possession date of SHRISTI RESIDENCY - PHASE 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHRISTI RESIDENCY - PHASE 1 in Jogeshwari East, Mumbai is 31 December 2026 — 24 months later than 31 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SHRISTI RESIDENCY - PHASE 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHRISTI RESIDENCY - PHASE 1's builder has filed on MahaRERA, the official one, is 31 December 2026, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHRISTI RESIDENCY - PHASE 1 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRISTI RESIDENCY - PHASE 1's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2025, giving the reason "UNFORESEEN CIRCUMSTANCES THE PROJECT WAS NOT ABLE TO GET COMPLETED IN TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENTION TILL 31ST DECEMBER 2025."; to 31 December 2026, giving the reason "The project was delayed due to an unavoidable reason that was beyond our control. Maily the road work process and other work was hampered. We requested the extension as per order 40 and got the extension order from Maharera. We have now submitted the order and requesting to grant us the extension as per order 40. Date of extension requested 31.12.2026".
What is the RERA number of SHRISTI RESIDENCY - PHASE 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHRISTI RESIDENCY - PHASE 1 in Jogeshwari East, Mumbai is P51800031167.
Is SHRISTI RESIDENCY - PHASE 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRISTI RESIDENCY - PHASE 1 is registered as P51800031167 and its status is "Completed".
What is the construction status of SHRISTI RESIDENCY - PHASE 1?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRISTI RESIDENCY - PHASE 1's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does SHRISTI RESIDENCY - PHASE 1 have complaints on MahaRERA?
38 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHRISTI RESIDENCY - PHASE 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRISTI RESIDENCY - PHASE 1 is registered on MahaRERA as P51800031167, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and 38 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHRISTI RESIDENCY - PHASE 1's possession date changes?
The latest dates are on SHRISTI RESIDENCY - PHASE 1's MahaRERA page (P51800031167). GharKundli's Kundli Watch sends a free WhatsApp update on SHRISTI RESIDENCY - PHASE 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHRISTI RESIDENCY - PHASE 1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRISTI RESIDENCY - PHASE 1 has 3 buildings filed: SHRISTI RESIDENCY - WING A with 19 floors and 76 units; SHRISTI RESIDENCY - WING B with 19 floors and 71 units; SHRISTI RESIDENCY - WING C with 19 floors and 74 units.
What are the flat sizes (carpet area) in SHRISTI RESIDENCY - PHASE 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SHRISTI RESIDENCY - PHASE 1: 2 BHK: 435 to 615 sq ft carpet (144 homes); 1 BHK: 435 sq ft carpet (69 homes); 3 BHK: 691 to 733 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does SHRISTI RESIDENCY - PHASE 1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 105 covered car parking spaces for SHRISTI RESIDENCY - PHASE 1.
How big is the land of SHRISTI RESIDENCY - PHASE 1?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRISTI RESIDENCY - PHASE 1 stands on 2,009 sq m of land (about 0.5 acres), with 12,968 sq m of sanctioned built-up area.
Where can I read reviews of SHRISTI RESIDENCY - PHASE 1?
Google Maps has reviews of SHRISTI RESIDENCY - PHASE 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 38 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHRISTI RESIDENCY - PHASE 1?
SHRISTI RESIDENCY - PHASE 1 by RANBIR REAL ESTATE AND DEVELOPERS LLP is in Jogeshwari East, Mumbai (pincode 400060), near Andheri East, Jvlr, Andheri West, Maharashtra, and is registered on MahaRERA as P51800031167, per GharKundli's check of MahaRERA records.
How many homes are in SHRISTI RESIDENCY - PHASE 1?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRISTI RESIDENCY - PHASE 1 has 215 homes in 3 towers registered on MahaRERA, and 77% of them are sold or booked.
When was SHRISTI RESIDENCY - PHASE 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRISTI RESIDENCY - PHASE 1 was registered on MahaRERA on 11 October 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on SHRISTI RESIDENCY - PHASE 1?
No court cases are listed for SHRISTI RESIDENCY - PHASE 1 on MahaRERA, and 16 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SHRISTI RESIDENCY - PHASE 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RANBIR REAL ESTATE AND DEVELOPERS LLP.
Check it yourself on MahaRERA
- How to check the possession date of SHRISTI RESIDENCY - PHASE 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400060
- SHIVSOLITAIRE
- BHAWANI HEIGHTS
- Vraj Bhumi Heights
- SHIVKUNJ
- AVANT HERITAGE - III
- SHRADDHA WEST RESIDENCY
- ROSE BLOSSOM CHSL
- DATTARAM TOWER
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.