by AGNEL DEVELOPERS · Ghatkopar, MumbaiAlso near Pant Nagar, Pantnagar, Rajawadi
Possession date of THE VIEWS: 30 April 2027, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900031165, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about THE VIEWS?
How the possession date of THE VIEWS has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA18122518752)
Reason the builder gave MahaRERA:
“The Authority had issued Certificate of Registration dated 11.10.2021 which is valid for a period commencing from 11.10.2021 and ending with 31.12.2025. The Real Estate Project is substantially completed except for some amenities and some u…” Read the full reason
“The Authority had issued Certificate of Registration dated 11.10.2021 which is valid for a period commencing from 11.10.2021 and ending with 31.12.2025. The Real Estate Project is substantially completed except for some amenities and some units which are not yet ready for occupation. We are under the process of completing the balance finishing work of the Real Estate Project and accordingly, we have applied for part Occupation Certificate. The commencement certificate which we have obtained is valid upto 19.09.2026. In view of the above, we are seeking an extension of the registration of th…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: THE VIEWS’s extension records on MahaRERA (P51900031165), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on THE VIEWS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints and 7 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- THE VIEWS IIP51900033194 · possession 31 Dec 2026
- MahaRERA registration
- P51900031165
- Status
- Registered and active
- Builder
- AGNEL DEVELOPERS
- Location
- Ghatkopar, Mumbai · 400075
- Project type
- Residential / Group Housing
- Registered on
- 11 Oct 2021
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 282
- Sold or booked
- 74%
- Towers
- 2
- Complaints on MahaRERA
- 3
- Court cases listed
- 7
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of THE VIEWS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| TOWER B | 100% | 100% | 100% | 100% |
| TOWER A | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- TOWER B: covers 21 floors
- TOWER A: covers 21 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on THE VIEWS every month.
THE VIEWS: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 556 – 827 | 240 |
| 3 BHK | 908 – 924 | 42 |
| Shops | 353 – 754 | 4 |
- Buildings: TOWER B (26 floors, 145 units) · TOWER A (26 floors, 141 units)
- Land: 18,280 sq m (about 4.5 acres) · sanctioned built-up 6,996 sq m
- Boundaries filed include: PANTNAGAR MHADA COLONY, EASTERN EXPRESS HIGHWAY
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Adani Estates (a group of 7 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 12 months); 16 still being built, 2 past the promised date (typically 8 months late). 43 complaints on MahaRERA across 10 projects.
Read Google reviews of THE VIEWS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
THE VIEWS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about THE VIEWS
What is the possession date of THE VIEWS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for THE VIEWS in Ghatkopar, Mumbai is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for THE VIEWS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date THE VIEWS's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of THE VIEWS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The Authority had issued Certificate of Registration dated 11.10.2021 which is valid for a period commencing from 11.10.2021 and ending with 31.12.2025. The Real Estate Project is substantially completed except for some amenities and some units which are not yet ready for occupation. We are under the process of completing the balance finishing work of the Real Estate Project and accordingly, we have applied for part Occupation Certificate. The commencement certificate which we have obtained is valid upto 19.09.2026. In view of the above, we are seeking an extension of the registration of th…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of THE VIEWS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of THE VIEWS in Ghatkopar, Mumbai is P51900031165.
Is THE VIEWS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS is registered as P51900031165 and its status is "Registered and active".
What is the construction status of THE VIEWS?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does THE VIEWS have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is THE VIEWS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS is registered on MahaRERA as P51900031165, its completion date has moved 12 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does THE VIEWS have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: THE VIEWS II (P51900033194, possession 31 Dec 2026). Check that your agreement names the registration of your own wing.
How can I get updates if THE VIEWS's possession date changes?
The latest dates are on THE VIEWS's MahaRERA page (P51900031165). GharKundli's Kundli Watch sends a free WhatsApp update on THE VIEWS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does THE VIEWS have?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS has 2 buildings filed: TOWER B with 26 floors and 145 units; TOWER A with 26 floors and 141 units.
What are the flat sizes (carpet area) in THE VIEWS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for THE VIEWS: 2 BHK: 556 to 827 sq ft carpet (240 homes); 3 BHK: 908 to 924 sq ft carpet (42 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of THE VIEWS?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS stands on 18,280 sq m of land (about 4.5 acres), with 6,996 sq m of sanctioned built-up area.
What is the track record of THE VIEWS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Adani Estates (a group of 7 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 12 months); 16 still being built, 2 past the promised date (typically 8 months late). 43 complaints on MahaRERA across 10 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of THE VIEWS?
Google Maps has reviews of THE VIEWS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is THE VIEWS?
THE VIEWS by AGNEL DEVELOPERS is in Ghatkopar, Mumbai (pincode 400075), near Pant Nagar, Pantnagar, Rajawadi, Maharashtra, and is registered on MahaRERA as P51900031165, per GharKundli's check of MahaRERA records. Its boundaries filed there include PANTNAGAR MHADA COLONY, EASTERN EXPRESS HIGHWAY.
How many homes are in THE VIEWS?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS has 282 homes in 2 towers registered on MahaRERA, and 74% of them are sold or booked.
When was THE VIEWS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS was registered on MahaRERA on 11 October 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on THE VIEWS?
7 court cases are listed for THE VIEWS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of THE VIEWS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AGNEL DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of THE VIEWS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Ghatkopar
- THE VIEWS II
- CRYSTAL PRIME MERIDIAN
- AVEER YOG
- YOG MATRU BHOOMI
- MAHAVIR ZEN
- PARK VIEW
- VAIBHAV SEASONS
- SHREE GANESH CHS
Other projects by AGNEL DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.