THE VIEWS II
by AGNEL DEVELOPERS · Ghatkopar, Mumbai
Possession date of THE VIEWS II: 31 December 2026, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900033194, and currently active. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about THE VIEWS II?
How the possession date of THE VIEWS II has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA18122518753)
Reason the builder gave MahaRERA:
“The Authority had issued Certificate of Registration dated 09.02.2022 which is valid for a period commencing from 09.02.2022 and ending with 31.12.2025. The Real Estate Project is substantially completed except for some amenities and some u…” Read the full reason
“The Authority had issued Certificate of Registration dated 09.02.2022 which is valid for a period commencing from 09.02.2022 and ending with 31.12.2025. The Real Estate Project is substantially completed except for some amenities and some units which are not yet ready for occupation. We are under the process of completing the balance finishing work of the Real Estate Project and accordingly, we have applied for part Occupation Certificate. The commencement certificate which we have obtained is valid upto 19.09.2026. In view of the above, we are seeking an extension of the registration of th…”
Source: THE VIEWS II’s extension records on MahaRERA (P51900033194), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on THE VIEWS II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints and 7 court cases, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- THE VIEWSP51900031165 · possession 30 Apr 2027
- MahaRERA registration
- P51900033194
- Status
- Registered and active
- Builder
- AGNEL DEVELOPERS
- Location
- Ghatkopar, Mumbai · 400075
- Project type
- Residential / Group Housing
- Registered on
- 9 Feb 2022
- Completion date at registration
- December 2025
- Latest completion date
- December 2026
- Delay so far
- 12 months
- Homes
- 282
- Sold or booked
- 52%
- Towers
- 2
- Complaints on MahaRERA
- 2
- Court cases listed
- 7
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of THE VIEWS II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| TOWER C | 100% | 100% | 100% | 100% |
| TOWER D | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- TOWER C: covers 21 floors
- TOWER D: covers 21 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on THE VIEWS II every month.
THE VIEWS II: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 601 – 827 | 155 |
| Other | 556 – 924 | 118 |
| 4 BHK | 1,376 – 1,473 | 6 |
| Shops | 353 – 646 | 4 |
| 1 BHK | 495 – 515 | 2 |
| 6 BHK | 2,093 | 1 |
- Buildings: TOWER C (26 floors, 145 units) · TOWER D (26 floors, 141 units)
- Land: 18,280 sq m (about 4.5 acres) · sanctioned built-up 7,413 sq m
- Boundaries filed include: PANTNAGAR MHADA COLONY, EASTERN EXPRESS HIGHWAY
The builder’s record and reviews
Adani Estates (a group of 7 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 12 months); 16 still being built, 2 past the promised date (typically 8 months late). 43 complaints on MahaRERA across 10 projects.
Read Google reviews of THE VIEWS II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
THE VIEWS II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about THE VIEWS II
What is the possession date of THE VIEWS II?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for THE VIEWS II in Ghatkopar, Mumbai is 31 December 2026 — 12 months later than 31 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for THE VIEWS II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date THE VIEWS II's builder has filed on MahaRERA, the official one, is 31 December 2026, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of THE VIEWS II extended?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS II's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The Authority had issued Certificate of Registration dated 09.02.2022 which is valid for a period commencing from 09.02.2022 and ending with 31.12.2025. The Real Estate Project is substantially completed except for some amenities and some units which are not yet ready for occupation. We are under the process of completing the balance finishing work of the Real Estate Project and accordingly, we have applied for part Occupation Certificate. The commencement certificate which we have obtained is valid upto 19.09.2026. In view of the above, we are seeking an extension of the registration of th…".
What is the RERA number of THE VIEWS II?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of THE VIEWS II in Ghatkopar, Mumbai is P51900033194.
Is THE VIEWS II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS II is registered as P51900033194 and its status is "Registered and active".
What is the construction status of THE VIEWS II?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS II's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does THE VIEWS II have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is THE VIEWS II safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS II is registered on MahaRERA as P51900033194, its completion date has moved 12 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does THE VIEWS II have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: THE VIEWS (P51900031165, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.
How can I get updates if THE VIEWS II's possession date changes?
The latest dates are on THE VIEWS II's MahaRERA page (P51900033194). GharKundli's Kundli Watch sends a free WhatsApp update on THE VIEWS II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does THE VIEWS II have?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS II has 2 buildings filed: TOWER C with 26 floors and 145 units; TOWER D with 26 floors and 141 units.
What are the flat sizes (carpet area) in THE VIEWS II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for THE VIEWS II: 2 BHK: 601 to 827 sq ft carpet (155 homes); Other: 556 to 924 sq ft carpet (118 homes); 4 BHK: 1376 to 1473 sq ft carpet (6 homes); 1 BHK: 495 to 515 sq ft carpet (2 homes); 6 BHK: 2093 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of THE VIEWS II?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS II stands on 18,280 sq m of land (about 4.5 acres), with 7,413 sq m of sanctioned built-up area.
What is the track record of THE VIEWS II's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Adani Estates (a group of 7 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 12 months); 16 still being built, 2 past the promised date (typically 8 months late). 43 complaints on MahaRERA across 10 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of THE VIEWS II?
Google Maps has reviews of THE VIEWS II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is THE VIEWS II?
THE VIEWS II by AGNEL DEVELOPERS is in Ghatkopar, Mumbai (pincode 400075), Maharashtra, and is registered on MahaRERA as P51900033194, per GharKundli's check of MahaRERA records. Its boundaries filed there include PANTNAGAR MHADA COLONY, EASTERN EXPRESS HIGHWAY.
How many homes are in THE VIEWS II?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS II has 282 homes in 2 towers registered on MahaRERA, and 52% of them are sold or booked.
When was THE VIEWS II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), THE VIEWS II was registered on MahaRERA on 9 February 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on THE VIEWS II?
7 court cases are listed for THE VIEWS II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of THE VIEWS II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AGNEL DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of THE VIEWS II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Ghatkopar
- THE VIEWS
- CRYSTAL PRIME MERIDIAN
- AVEER YOG
- YOG MATRU BHOOMI
- MAHAVIR ZEN
- PARK VIEW
- VAIBHAV SEASONS
- SHREE GANESH CHS
Other projects by AGNEL DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.