Aakash Sapphire
by AAKASH REALORS PRIVATE LIMITED · Mahim Sub Division, Mumbai 400016Also near Dharavi, Matunga, Bhawani ShankarRegistered on MahaRERA as “SAPPHIRE”
What’s in the report? →Possession date of Aakash Sapphire (MahaRERA P51800031268): 30 April 2027, moved from 30 April 2025 (20 months later). It has 107 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800031268, and currently active. Its completion date has moved from April 2025 to April 2027: 20 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800031268, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Aakash Sapphire?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Aakash Sapphire has moved
30 April 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT51800019519)
Reason the builder gave MahaRERA: “DUE TO REVISE PLAN WE ARE NOT ABLE TO COMPLETE PROJECT ON TIME”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Aakash Sapphire’s extension records on MahaRERA (P51800031268), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Aakash Sapphire
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800031268
- Status
- Registered and active
- Builder
- AAKASH REALORS PRIVATE LIMITED
- Location
- Mahim Sub Division, Mumbai · 400016
- Project type
- Residential / Group Housing
- Registered on
- 15 Oct 2021
- Completion date at registration
- April 2025
- Latest completion date
- April 2027
- Delay so far
- 20 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 107
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Aakash Sapphire, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAPPHIRE | 100% | 2% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aakash Sapphire every 1–2 months.
Aakash Sapphire: buildings, flats and land, as filed on MahaRERA
- Buildings: SAPPHIRE (22 floors)
- Land: 638 sq m (about 0.2 acres) · sanctioned built-up 1,917 sq m
- Land, as filed: F.P NO-548, T.P NO-3 MAHIM DIVISION
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Aakash Sapphire →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Aakash Sapphire: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Aakash Sapphire
What is the possession date of Aakash Sapphire?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aakash Sapphire in Mahim Sub Division, Mumbai is 30 April 2027 — 20 months later than 30 April 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 20 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Aakash Sapphire?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Aakash Sapphire's builder has filed on MahaRERA, the official one, is 30 April 2027, already 20 months later than the 30 April 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Aakash Sapphire extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Sapphire's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "DUE TO REVISE PLAN WE ARE NOT ABLE TO COMPLETE PROJECT ON TIME". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Aakash Sapphire?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aakash Sapphire in Mahim Sub Division, Mumbai is P51800031268.
Is Aakash Sapphire registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Sapphire is registered as P51800031268 and its status is "Registered and active".
What is the current construction status of Aakash Sapphire? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Sapphire's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAPPHIRE is 2% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Aakash Sapphire have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Aakash Sapphire safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Sapphire is registered on MahaRERA as P51800031268, its completion date has moved 20 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Aakash Sapphire?
Aakash Sapphire is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Aakash Sapphire?
For a flat in Aakash Sapphire (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Aakash Sapphire received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Sapphire is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Aakash Sapphire uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Aakash Sapphire was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Aakash Sapphire's possession date changes?
The latest dates are on Aakash Sapphire's MahaRERA page (P51800031268). GharKundli's Kundli Watch sends a free WhatsApp update on Aakash Sapphire every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Aakash Sapphire have?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Sapphire has one building filed: SAPPHIRE with 22 floors.
How big is the land of Aakash Sapphire?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Sapphire stands on 638 sq m of land (about 0.2 acres), with 1,917 sq m of sanctioned built-up area.
What are the reviews of Aakash Sapphire?
Google Maps has reviews of Aakash Sapphire written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Aakash Sapphire?
Aakash Sapphire by AAKASH REALORS PRIVATE LIMITED is in Mahim Sub Division, Mumbai, pincode 400016 (near Dharavi, Matunga, Bhawani Shankar), Maharashtra, and is registered on MahaRERA as P51800031268, per GharKundli's check of MahaRERA records. Its land is filed as F.P NO-548, T.P NO-3 MAHIM DIVISION. GharKundli lists all 84 MahaRERA projects in Mahim (400016).
How many flats are in Aakash Sapphire?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Sapphire has 107 homes in 1 tower registered on MahaRERA.
When was Aakash Sapphire registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Sapphire was registered on MahaRERA on 15 October 2021. GharKundli did not find a title report on the land on file there.
Does Aakash Sapphire have any legal issues or court cases?
No court cases are listed for Aakash Sapphire on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Aakash Sapphire?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AAKASH REALORS PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of Aakash Sapphire
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Mahim (400016)
All 84 projects in Mahim (400016) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.