HBS Marineview
by HBS Seaview Pvt Ltd · Worli, MumbaiAlso near Girgaum, Neral, Grant Road
Possession date of HBS Marineview: 30 December 2025. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900009287. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2025) has passed.
On MahaRERA's insolvency (NCLT) list
MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about HBS Marineview?
GharKundli’s full report on HBS Marineview
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints and 1 court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900009287
- Status
- Lapsed (registration period ended)
- Builder
- HBS Seaview Pvt Ltd
- Location
- Worli, Mumbai · 400002
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- December 2025
- Latest completion date
- December 2025
- Homes
- 77
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 1
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of HBS Marineview, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| HBS Marineview - Phase - I | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on HBS Marineview every month.
HBS Marineview: buildings, flats and land, as filed on MahaRERA
- Buildings: HBS Marineview - Phase - I (33 floors)
- Land: 977 sq m (about 0.2 acres) · sanctioned built-up 2,853 sq m · recreational space 281 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of HBS Marineview →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
HBS Marineview: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about HBS Marineview
What is the possession date of HBS Marineview?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for HBS Marineview in Worli, Mumbai is 30 December 2025. That date has already passed.
Is the builder's possession date different from the MahaRERA date for HBS Marineview?
Builders and listing sites often quote an earlier "target" date for handover. The completion date HBS Marineview's builder has filed on MahaRERA, the official one, is 30 December 2025, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of HBS Marineview?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of HBS Marineview in Worli, Mumbai is P51900009287.
Is HBS Marineview registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), HBS Marineview is registered as P51900009287 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
What is the construction status of HBS Marineview?
According to GharKundli's check of MahaRERA records (updated November 2026), HBS Marineview's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on HBS Marineview - Phase - I is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does HBS Marineview have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is HBS Marineview safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), HBS Marineview is registered on MahaRERA as P51900009287, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder, 3 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if HBS Marineview's possession date changes?
The latest dates are on HBS Marineview's MahaRERA page (P51900009287). GharKundli's Kundli Watch sends a free WhatsApp update on HBS Marineview every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does HBS Marineview have?
According to GharKundli's check of MahaRERA records (updated November 2026), HBS Marineview has one building filed: HBS Marineview - Phase - I with 33 floors.
How big is the land of HBS Marineview?
According to GharKundli's check of MahaRERA records (updated November 2026), HBS Marineview stands on 977 sq m of land (about 0.2 acres), with 2,853 sq m of sanctioned built-up area and 281 sq m of recreational open space.
Where can I read reviews of HBS Marineview?
Google Maps has reviews of HBS Marineview written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is HBS Marineview?
HBS Marineview by HBS Seaview Pvt Ltd is in Worli, Mumbai (pincode 400002), near Girgaum, Neral, Grant Road, Maharashtra, and is registered on MahaRERA as P51900009287, per GharKundli's check of MahaRERA records.
How many homes are in HBS Marineview?
According to GharKundli's check of MahaRERA records (updated November 2026), HBS Marineview has 77 homes in 1 tower registered on MahaRERA.
When was HBS Marineview registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), HBS Marineview was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on HBS Marineview?
1 court case is listed for HBS Marineview on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of HBS Marineview?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is HBS Seaview Pvt Ltd.
Check it yourself on MahaRERA
- How to check the possession date of HBS Marineview
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Worli
- Lodha Promina
- AKSHAY
- Prestige Nautilus
- Birla Niyaara Phase-2
- Lodha Adrina
- Mahindra Marina64 - Phase 1
- Mahindra Marina64 - Phase 2
- Lodha Worli Residential Project
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.