Skip to content
GharKundli

Gagan 138

by GAGANGIRI CONSTRUCTION · Kurla East, MumbaiAlso near Nehru Nagar, Chembur, Bhandup West

Possession: Gagan 138 is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800033983. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Gagan 138?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Gagan 138

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

  • Gagan 45P51800033764 · possession 31 Dec 2025
  • Gagan 52PM1180002600783 · possession 30 Aug 2031
  • Gagan 139P51800029662 · possession 30 Nov 2024
MahaRERA registration
P51800033983
Status
Completed
Builder
GAGANGIRI CONSTRUCTION
Location
Kurla East, Mumbai · 400024
Project type
Residential / Group Housing
Registered on
14 Mar 2022
Completion date at registration
December 2025
Homes
139
Sold or booked
99%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Gagan 138, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Gagan 138100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Gagan 138: covers 19 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gagan 138 every month.

Gagan 138: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Gagangiri Construction (a group of 15 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 7 within the promised date and 1 needed more time (typically 15 months); 14 still being built, none past the promised date yet; 1 lapsed. 7 complaints on MahaRERA across 3 projects.

Read Google reviews of Gagan 138 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Gagan 138: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Gagan 138

What is the possession date of Gagan 138?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Gagan 138 in Kurla East, Mumbai is 31 December 2025.

Is the builder's possession date different from the MahaRERA date for Gagan 138?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Gagan 138's builder has filed on MahaRERA, the official one, is 31 December 2025, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Gagan 138?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Gagan 138 in Kurla East, Mumbai is P51800033983.

Is Gagan 138 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Gagan 138 is registered as P51800033983 and its status is "Completed".

What is the construction status of Gagan 138?

According to GharKundli's check of MahaRERA records (updated November 2026), Gagan 138's status on MahaRERA is "Completed". As filed by the builder, slab work on Gagan 138 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Gagan 138 have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Gagan 138 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Gagan 138 is registered on MahaRERA as P51800033983, its MahaRERA status is "Completed", its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Gagan 138 have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Gagan 45 (P51800033764, possession 31 Dec 2025); Gagan 52 (PM1180002600783, possession 30 Aug 2031); Gagan 139 (P51800029662, possession 30 Nov 2024). Check that your agreement names the registration of your own wing.

How can I get updates if Gagan 138's possession date changes?

The latest dates are on Gagan 138's MahaRERA page (P51800033983). GharKundli's Kundli Watch sends a free WhatsApp update on Gagan 138 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Gagan 138 have?

According to GharKundli's check of MahaRERA records (updated November 2026), Gagan 138 has one building filed: Gagan 138 with 19 floors and 141 units.

How much parking does Gagan 138 have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 39 covered car parking spaces for Gagan 138.

How big is the land of Gagan 138?

According to GharKundli's check of MahaRERA records (updated November 2026), Gagan 138 stands on 1,038 sq m of land (about 0.3 acres), with 8,233 sq m of sanctioned built-up area.

What is the track record of Gagan 138's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Gagangiri Construction (a group of 15 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 7 within the promised date and 1 needed more time (typically 15 months); 14 still being built, none past the promised date yet; 1 lapsed. 7 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Gagan 138?

Google Maps has reviews of Gagan 138 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Gagan 138?

Gagan 138 by GAGANGIRI CONSTRUCTION is in Kurla East, Mumbai (pincode 400024), near Nehru Nagar, Chembur, Bhandup West, Maharashtra, and is registered on MahaRERA as P51800033983, per GharKundli's check of MahaRERA records.

How many homes are in Gagan 138?

According to GharKundli's check of MahaRERA records (updated November 2026), Gagan 138 has 139 homes in 1 tower registered on MahaRERA, and 99% of them are sold or booked.

When was Gagan 138 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Gagan 138 was registered on MahaRERA on 14 March 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Gagan 138?

No court cases are listed for Gagan 138 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Gagan 138?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GAGANGIRI CONSTRUCTION, which has 4 other projects registered on MahaRERA.

Other projects in Kurla East

All 85 projects in Kurla East (400024) →

Other projects by GAGANGIRI CONSTRUCTION

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.