by DHIRAJ narayandas JADHWANI · FCI, Mumbai 400074Also near Chembur

What’s in the report? →

Possession: DJ Amore2 (MahaRERA P51800048275) is marked completed on MahaRERA. It has 22 homes (1 BHK, 2 BHK and 3 BHK, 415–839 sq ft carpet), 55% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800048275. Status: Completed.

Source: MahaRERA website — records for P51800048275, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about DJ Amore2?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of DJ Amore2 has moved

  1. 1 April 2025

    Completion date given when the project was registered

  2. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT51800027911)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-03-2026. to complete the project and fulfil all regulatory requirements.”

Source: DJ Amore2’s extension records on MahaRERA (P51800048275), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DJ Amore2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800048275
Status
Completed
Builder
DHIRAJ narayandas JADHWANI
Location
FCI, Mumbai · 400074
Project type
Residential / Group Housing
Registered on
22 Dec 2022
Completion date at registration
April 2025
Latest completion date
March 2026
Delay so far
11 months
Homes
22
Sold or booked
55%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of DJ Amore2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DJ AMORE2100%72%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on DJ Amore2 every 1–2 months.

DJ Amore2: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK415 – 42514
2 BHK6677
3 BHK8391
  • Buildings: DJ AMORE2 (9 floors)
  • Land: 429 sq m (about 0.1 acres) · sanctioned built-up 1,158 sq m
  • Land, as filed: 359,360
  • Map: Get directions

The builder’s record and reviews

Dhiraj Narayandas Jadhwani has 3 projects on MahaRERA since 2020, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 11 months); 1 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA.

Read Google reviews of DJ Amore2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DJ Amore2: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about DJ Amore2

What is the possession date of DJ Amore2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DJ Amore2 in FCI, Mumbai is 31 March 2026 — 11 months later than 1 April 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for DJ Amore2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DJ Amore2's builder has filed on MahaRERA, the official one, is 31 March 2026, already 11 months later than the 1 April 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of DJ Amore2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), DJ Amore2's builder applied to MahaRERA to extend the completion date once: to 31 March 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-03-2026. to complete the project and fulfil all regulatory requirements.".

What is the RERA number of DJ Amore2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DJ Amore2 in FCI, Mumbai is P51800048275.

Is DJ Amore2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DJ Amore2 is registered as P51800048275 and its status is "Completed".

What is the current construction status of DJ Amore2? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), DJ Amore2's status on MahaRERA is "Completed". As filed by the builder, slab work on DJ AMORE2 is 72% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does DJ Amore2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is DJ Amore2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), DJ Amore2 is registered on MahaRERA as P51800048275, its MahaRERA status is "Completed", its completion date has moved 11 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in DJ Amore2?

According to GharKundli's check of MahaRERA records (updated October 2026), DJ Amore2 is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in DJ Amore2?

For a flat in DJ Amore2 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has DJ Amore2 received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated October 2026), DJ Amore2 is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was DJ Amore2 completed?

According to GharKundli's check of MahaRERA records (updated October 2026), DJ Amore2 is marked completed on MahaRERA, and the completion date filed there is 31 March 2026. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has DJ Amore2 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for DJ Amore2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if DJ Amore2's possession date changes?

The latest dates are on DJ Amore2's MahaRERA page (P51800048275). GharKundli's Kundli Watch sends a free WhatsApp update on DJ Amore2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does DJ Amore2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), DJ Amore2 has one building filed: DJ AMORE2 with 9 floors.

What are the flat sizes (carpet area) in DJ Amore2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for DJ Amore2: 1 BHK: 415 to 425 sq ft carpet (14 homes); 2 BHK: 667 sq ft carpet (7 homes); 3 BHK: 839 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of DJ Amore2?

According to GharKundli's check of MahaRERA records (updated October 2026), DJ Amore2 stands on 429 sq m of land (about 0.1 acres), with 1,158 sq m of sanctioned built-up area.

What is the track record of DJ Amore2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Dhiraj Narayandas Jadhwani has 3 projects on MahaRERA since 2020, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 11 months); 1 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of DJ Amore2?

Google Maps has reviews of DJ Amore2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of DJ Amore2?

DJ Amore2 by DHIRAJ narayandas JADHWANI is in FCI, Mumbai, pincode 400074 (near Chembur), Maharashtra, and is registered on MahaRERA as P51800048275, per GharKundli's check of MahaRERA records. Its land is filed as 359,360. GharKundli lists all 36 MahaRERA projects in FCI (400074).

How many flats are in DJ Amore2, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), DJ Amore2 has 22 homes in 1 tower registered on MahaRERA, and 55% of them are sold or booked.

When was DJ Amore2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DJ Amore2 was registered on MahaRERA on 22 December 2022. GharKundli did not find a title report on the land on file there.

Does DJ Amore2 have any legal issues or court cases?

No court cases are listed for DJ Amore2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of DJ Amore2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DHIRAJ narayandas JADHWANI, which has 2 other projects registered on MahaRERA.