SAFAL GANGA SMRUTI
by VARUN HOMES PVT LTD · Ghatkoper Mahul Road, MumbaiAlso near Fci
Possession date of SAFAL GANGA SMRUTI: 30 November 2026, moved from 30 March 2024 (32 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800024417, and currently active. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SAFAL GANGA SMRUTI?
How the possession date of SAFAL GANGA SMRUTI has moved
30 March 2024
Completion date given when the project was registered
30 September 2024
Extended at the builder's request (MahaRERA application EXT51800017542)
Reason the builder gave MahaRERA: “DUE TO SHORTAGE OF TDR IN MARKET , WE ARE UNABLE TO BUY THE SAME. SO 6 MONTHS EXTENSION IS REQUIRED FOR PURCHASE OF TDR AND CONSTRUCTION OF ADDITIONAL 9 FLOOR OF THE BUILDING.”
31 March 2025
Extended at the builder's request (MahaRERA application EXT51800024141)
Reason the builder gave MahaRERA:
“Building work is completed up to 12 th floor and internal work is in progress, earlier developer had taken extension up to September 2024, extension was received in November 2023, Developer took TDR upto 17th floor and taken approval from c…” Read the full reason
“Building work is completed up to 12 th floor and internal work is in progress, earlier developer had taken extension up to September 2024, extension was received in November 2023, Developer took TDR upto 17th floor and taken approval from commissioner which took 8 months. Now Developer is waiting for fund allocation from Bank, as Developer have taken construction finance. Therefore, developer require additional 6 months i.e. by 31 st March 2025 to complete the construction of project.”31 March 2026
Extended at the builder's request (MahaRERA application EXT51800028049)
Reason the builder gave MahaRERA:
“Due to financial constraints faced ,construction work of the building are not yet completed. Therefore, the we Require additional time i.e. extension upto 31st March 2026 to complete the construction of project. We request you to do the nee…” Read the full reason
“Due to financial constraints faced ,construction work of the building are not yet completed. Therefore, the we Require additional time i.e. extension upto 31st March 2026 to complete the construction of project. We request you to do the needful.”30 November 2026
Extended at the builder's request (MahaRERA application EA24042620729)
Reason the builder gave MahaRERA:
“Due to financial issue progress was slow , now all the financial issues have been fully resolved, and construction work has recommenced in full swing with adequate manpower, machinery, and materials deployed at site. Considering the present…” Read the full reason
“Due to financial issue progress was slow , now all the financial issues have been fully resolved, and construction work has recommenced in full swing with adequate manpower, machinery, and materials deployed at site. Considering the present progress and the revised construction schedule, we requires an additional 8 months (up to November 2026) to complete the project in all respects.”
Source: SAFAL GANGA SMRUTI’s extension records on MahaRERA (P51800024417), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAFAL GANGA SMRUTI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the November 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800024417
- Status
- Registered and active
- Builder
- VARUN HOMES PVT LTD
- Location
- Ghatkoper Mahul Road, Mumbai · 400074
- Project type
- Residential / Group Housing
- Registered on
- 12 Feb 2020
- Completion date at registration
- March 2024
- Latest completion date
- November 2026
- Delay so far
- 32 months
- Homes
- 63
- Sold or booked
- 85%
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of SAFAL GANGA SMRUTI, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAFAL GANGA SMRUTI | 100% | 61% | 40% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SAFAL GANGA SMRUTI: covers 12 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAFAL GANGA SMRUTI every month.
SAFAL GANGA SMRUTI: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 623 – 728 | 33 |
| 1 BHK | 400 – 460 | 30 |
- Buildings: SAFAL GANGA SMRUTI (19 floors, 63 units)
- Land: 1,278 sq m (about 0.3 acres) · sanctioned built-up 2,549 sq m · recreational space 217 sq m
The builder’s record and reviews
NAV Durga Construction (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 3 months); 6 still being built, 6 past the promised date (typically 18 months late); 1 lapsed. 59 complaints on MahaRERA across 6 projects.
Read Google reviews of SAFAL GANGA SMRUTI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAFAL GANGA SMRUTI: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAFAL GANGA SMRUTI
What is the possession date of SAFAL GANGA SMRUTI?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAFAL GANGA SMRUTI in Ghatkoper Mahul Road, Mumbai is 30 November 2026 — 32 months later than 30 March 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SAFAL GANGA SMRUTI?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAFAL GANGA SMRUTI's builder has filed on MahaRERA, the official one, is 30 November 2026, already 32 months later than the 30 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAFAL GANGA SMRUTI extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GANGA SMRUTI's builder applied to MahaRERA to extend the completion date 4 times: to 30 September 2024, giving the reason "DUE TO SHORTAGE OF TDR IN MARKET , WE ARE UNABLE TO BUY THE SAME. SO 6 MONTHS EXTENSION IS REQUIRED FOR PURCHASE OF TDR AND CONSTRUCTION OF ADDITIONAL 9 FLOOR OF THE BUILDING."; to 31 March 2025, giving the reason "Building work is completed up to 12 th floor and internal work is in progress, earlier developer had taken extension up to September 2024, extension was received in November 2023, Developer took TDR upto 17th floor and taken approval from commissioner which took 8 months. Now Developer is waiting for fund allocation from Bank, as Developer have taken construction finance. Therefore, developer require additional 6 months i.e. by 31 st March 2025 to complete the construction of project."; to 31 March 2026, giving the reason "Due to financial constraints faced ,construction work of the building are not yet completed. Therefore, the we Require additional time i.e. extension upto 31st March 2026 to complete the construction of project. We request you to do the needful."; to 30 November 2026, giving the reason "Due to financial issue progress was slow , now all the financial issues have been fully resolved, and construction work has recommenced in full swing with adequate manpower, machinery, and materials deployed at site. Considering the present progress and the revised construction schedule, we requires an additional 8 months (up to November 2026) to complete the project in all respects.".
What is the RERA number of SAFAL GANGA SMRUTI?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAFAL GANGA SMRUTI in Ghatkoper Mahul Road, Mumbai is P51800024417.
Is SAFAL GANGA SMRUTI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GANGA SMRUTI is registered as P51800024417 and its status is "Registered and active".
What is the construction status of SAFAL GANGA SMRUTI?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GANGA SMRUTI's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAFAL GANGA SMRUTI is 61% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.
Does SAFAL GANGA SMRUTI have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SAFAL GANGA SMRUTI safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GANGA SMRUTI is registered on MahaRERA as P51800024417, its completion date has moved 32 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAFAL GANGA SMRUTI's possession date changes?
The latest dates are on SAFAL GANGA SMRUTI's MahaRERA page (P51800024417). GharKundli's Kundli Watch sends a free WhatsApp update on SAFAL GANGA SMRUTI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAFAL GANGA SMRUTI have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GANGA SMRUTI has one building filed: SAFAL GANGA SMRUTI with 19 floors and 63 units.
What are the flat sizes (carpet area) in SAFAL GANGA SMRUTI?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SAFAL GANGA SMRUTI: 2 BHK: 623 to 728 sq ft carpet (33 homes); 1 BHK: 400 to 460 sq ft carpet (30 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of SAFAL GANGA SMRUTI?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GANGA SMRUTI stands on 1,278 sq m of land (about 0.3 acres), with 2,549 sq m of sanctioned built-up area and 217 sq m of recreational open space.
What is the track record of SAFAL GANGA SMRUTI's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), NAV Durga Construction (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 3 months); 6 still being built, 6 past the promised date (typically 18 months late); 1 lapsed. 59 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SAFAL GANGA SMRUTI?
Google Maps has reviews of SAFAL GANGA SMRUTI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAFAL GANGA SMRUTI?
SAFAL GANGA SMRUTI by VARUN HOMES PVT LTD is in Ghatkoper Mahul Road, Mumbai (pincode 400074), near Fci, Maharashtra, and is registered on MahaRERA as P51800024417, per GharKundli's check of MahaRERA records.
How many homes are in SAFAL GANGA SMRUTI?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GANGA SMRUTI has 63 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.
When was SAFAL GANGA SMRUTI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GANGA SMRUTI was registered on MahaRERA on 12 February 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on SAFAL GANGA SMRUTI?
No court cases are listed for SAFAL GANGA SMRUTI on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SAFAL GANGA SMRUTI?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VARUN HOMES PVT LTD, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SAFAL GANGA SMRUTI
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Kurla
- Saptashringi
- Jai Arihant
- SUDHANSHU HEIGHTS
- Privilon
- Kanakdhara
- Kalyan Kutir Co-operative Housing Society Limited
- Heritage Lakeside
- SAYBA TULIP
Other projects by VARUN HOMES PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.