SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD

by VARUN HOMES PVT LTD · Chembur, MumbaiAlso near Deonar, Ghatla, Gowandi

Possession date of SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD: 31 December 2025, moved from 31 August 2020 (64 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800004137. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800004137
Status
Lapsed (registration period ended)
Builder
VARUN HOMES PVT LTD
Location
Chembur, Mumbai · 400071
Project type
Residential / Group Housing
Registered on
8 Aug 2017
Completion date at registration
August 2020
Latest completion date
December 2025
Delay so far
64 months
Homes
81
Sold or booked
71%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAFAL SKY WING A AND WING B100%90%75%0%

Commencement certificate (CC), as filed on MahaRERA

  • SAFAL SKY WING A AND WING B: covers 11 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD every month.

SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK851 – 1,25852
2 BHK623 – 75224
1 Room Kitchen279 – 3325

The builder’s record and reviews

NAV Durga Construction (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 3 months); 6 still being built, 6 past the promised date (typically 18 months late); 1 lapsed. 59 complaints on MahaRERA across 6 projects.

Read Google reviews of SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD

What is the possession date of SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD in Chembur, Mumbai is 31 December 2025 — 64 months later than 31 August 2020, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD's builder has filed on MahaRERA, the official one, is 31 December 2025, already 64 months later than the 31 August 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD in Chembur, Mumbai is P51800004137.

Is SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD is registered as P51800004137 and its status is "Lapsed (registration period ended)".

What is the construction status of SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SAFAL SKY WING A AND WING B is 90% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.

Does SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD is registered on MahaRERA as P51800004137, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 64 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD's possession date changes?

The latest dates are on SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD's MahaRERA page (P51800004137). GharKundli's Kundli Watch sends a free WhatsApp update on SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD have?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD has one building filed: SAFAL SKY WING A AND WING B with 16 floors and 81 units.

What are the flat sizes (carpet area) in SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD: 3 BHK: 851 to 1258 sq ft carpet (52 homes); 2 BHK: 623 to 752 sq ft carpet (24 homes); 1 Room Kitchen: 279 to 332 sq ft carpet (5 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD stands on 2,177 sq m of land (about 0.5 acres), with 3,175 sq m of sanctioned built-up area and 735 sq m of recreational open space.

What is the track record of SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), NAV Durga Construction (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 3 months); 6 still being built, 6 past the promised date (typically 18 months late); 1 lapsed. 59 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?

Google Maps has reviews of SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?

SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD by VARUN HOMES PVT LTD is in Chembur, Mumbai (pincode 400071), near Deonar, Ghatla, Gowandi, Maharashtra, and is registered on MahaRERA as P51800004137, per GharKundli's check of MahaRERA records.

How many homes are in SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD has 81 homes in 1 tower registered on MahaRERA, and 71% of them are sold or booked.

When was SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD was registered on MahaRERA on 8 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?

No court cases are listed for SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VARUN HOMES PVT LTD, which has 1 other project registered on MahaRERA.