GharKundli

Jangid Elysium

by IMPRINT CONSTRUCTION PRIVATE LIMITED (Jangid) · Borivali East, Mumbai 400066Also near Borivali West, Mandapeshwar, Dahisar

What’s in the report? →

Possession date of Jangid Elysium (MahaRERA P51800034600): 31 December 2026, moved from 31 December 2025 (12 months later). No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800034600, and currently active.

Source: MahaRERA website — records for P51800034600, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Jangid Elysium?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Jangid Elysium has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA15012619462)

    Reason the builder gave MahaRERA:
    “We, Amrit Leelaram Jangid Director of M/s. Imprint Construction Private Limited, are the promoters of the real estate project known as "Jangid Elysium" bearing Maha RERA Registration No. P51800034600. We would like to respectfully bring to…” Read the full reason“We, Amrit Leelaram Jangid Director of M/s. Imprint Construction Private Limited, are the promoters of the real estate project known as "Jangid Elysium" bearing Maha RERA Registration No. P51800034600. We would like to respectfully bring to your attention that the project has encountered certain unforeseen that have adversely impacted the originally proposed timelines for completion. We wish to place on record that due to poor AQI during winters there were blanket stay on construction activity for entire Borivali and adjoining areas. These stays were enforced in the year 2024 & 2025 aid even…”

Source: Jangid Elysium’s extension records on MahaRERA (P51800034600), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Jangid Elysium

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800034600
Status
Registered and active
Builder
IMPRINT CONSTRUCTION PRIVATE LIMITED
Location
Borivali East, Mumbai · 400066
Project type
Commercial
Registered on
11 Apr 2022
Completion date at registration
December 2025
Latest completion date
December 2026
Delay so far
12 months
Homes
0
Sold or booked
97%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Jangid Elysium, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
JANGID ELYSUIM100%100%70%0%

Commencement certificate (CC), as filed on MahaRERA

  • JANGID ELYSUIM: covers PLINTH LEVEL

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Jangid Elysium every 1–2 months.

Jangid Elysium: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space410 – 750451
  • Buildings: JANGID ELYSUIM (35 floors, 451 units)
  • Land: 2,519 sq m (about 0.6 acres) · sanctioned built-up 20,759 sq m
  • Land, as filed: CTS NO 179/A & 179/B
  • Map: Get directions

The builder’s record and reviews

Jangid Developers (a group of 6 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 3 finished, 0 within the promised date and 3 needed more time (typically 35 months); 3 still being built, 1 past the promised date (typically 10 months late); 5 lapsed. 76 complaints on MahaRERA across 5 projects.

Read Google reviews of Jangid Elysium →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Jangid Elysium: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Jangid Elysium

What is the possession date of Jangid Elysium?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Jangid Elysium in Borivali East, Mumbai is 31 December 2026 — 12 months later than 31 December 2025, the date given at registration.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Jangid Elysium?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Jangid Elysium's builder has filed on MahaRERA, the official one, is 31 December 2026, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Jangid Elysium extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Jangid Elysium's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We, Amrit Leelaram Jangid Director of M/s. Imprint Construction Private Limited, are the promoters of the real estate project known as "Jangid Elysium" bearing Maha RERA Registration No. P51800034600. We would like to respectfully bring to your attention that the project has encountered certain unforeseen that have adversely impacted the originally proposed timelines for completion. We wish to place on record that due to poor AQI during winters there were blanket stay on construction activity for entire Borivali and adjoining areas. These stays were enforced in the year 2024 & 2025 aid even…".

What is the RERA number of Jangid Elysium?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Jangid Elysium in Borivali East, Mumbai is P51800034600.

Is Jangid Elysium registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Jangid Elysium is registered as P51800034600 and its status is "Registered and active".

What is the current construction status of Jangid Elysium? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Jangid Elysium's status on MahaRERA is "Registered and active". As filed by the builder, slab work on JANGID ELYSUIM is 100% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does Jangid Elysium have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Jangid Elysium safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Jangid Elysium is registered on MahaRERA as P51800034600, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Jangid Elysium?

Jangid Elysium is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Jangid Elysium?

For a flat in Jangid Elysium (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Jangid Elysium received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Jangid Elysium is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Jangid Elysium uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Jangid Elysium was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Jangid Elysium's possession date changes?

The latest dates are on Jangid Elysium's MahaRERA page (P51800034600). GharKundli's Kundli Watch sends a free WhatsApp update on Jangid Elysium every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Jangid Elysium have?

According to GharKundli's check of MahaRERA records (updated October 2026), Jangid Elysium has one building filed: JANGID ELYSUIM with 35 floors and 451 units.

How big is the land of Jangid Elysium?

According to GharKundli's check of MahaRERA records (updated October 2026), Jangid Elysium stands on 2,519 sq m of land (about 0.6 acres), with 20,759 sq m of sanctioned built-up area.

What is the track record of Jangid Elysium's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Jangid Developers (a group of 6 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 3 finished, 0 within the promised date and 3 needed more time (typically 35 months); 3 still being built, 1 past the promised date (typically 10 months late); 5 lapsed. 76 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Jangid Elysium?

Google Maps has reviews of Jangid Elysium written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Jangid Elysium?

Jangid Elysium by IMPRINT CONSTRUCTION PRIVATE LIMITED (Jangid) is in Borivali East, Mumbai, pincode 400066 (near Borivali West, Mandapeshwar, Dahisar), Maharashtra, and is registered on MahaRERA as P51800034600, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO 179/A & 179/B. GharKundli lists all 228 MahaRERA projects in Borivali East (400066).

How many flats are in Jangid Elysium, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Jangid Elysium has 0 homes in 1 tower registered on MahaRERA, and 97% of them are sold or booked.

When was Jangid Elysium registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Jangid Elysium was registered on MahaRERA on 11 April 2022. GharKundli did not find a title report on the land on file there.

Does Jangid Elysium have any legal issues or court cases?

No court cases are listed for Jangid Elysium on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Jangid Elysium?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is IMPRINT CONSTRUCTION PRIVATE LIMITED, the company Jangid files this project under.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Borivali East (400066)

All 228 projects in Borivali East (400066) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.