by Venus Housing Enterprise · Agar Bazaar Prabhadevi, Mumbai 400028Also near Dadar West, Shivaji Park, MahimRegistered on MahaRERA as “KENIWADI ANNAPURNA”

What’s in the report? →

Possession date of Venus Keniwadi Annapurna (MahaRERA P51900008800): 30 June 2025, moved from 31 December 2018 (78 months later), and it has already passed. It has 13 homes (1 BHK and 2 BHK, 435–830 sq ft carpet), 75% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900008800. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51900008800, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2025) has passed.

What do you want to know about Venus Keniwadi Annapurna?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Venus Keniwadi Annapurna has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT51900001040)

    Reason the builder gave MahaRERA:
    “• Project building comprises of 17 premises, out of which 5 premises are to be handed over to the owners, 3 shops and 1 office to be handed over to the old tenants/occupants, free of cost. • None out of 8 sale component premises have yet be…” Read the full reason“• Project building comprises of 17 premises, out of which 5 premises are to be handed over to the owners, 3 shops and 1 office to be handed over to the old tenants/occupants, free of cost. • None out of 8 sale component premises have yet been booked for sale. • Project building was almost complete in all respects in November, 2017. • Since the redevelopment project consisting of ‘A’ & ‘B’ wing is being carried out u/s. 33(7), NOC from MHADA is mandatory prior to applying for O. C. from MCGM. • For granting NOC, MHADA insisted on execution and registration of ownership agreements with old te…”
  3. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT51900005136)

    Reason the builder gave MahaRERA:
    “• Construction of Project building is complete in all respects upto 7th floor i. e. the top floor. • Since this redevelopment project is being carried out u/s. 33(7), NOC from MHADA is mandatory prior to applying for O. C. from MCGM. • Howe…” Read the full reason“• Construction of Project building is complete in all respects upto 7th floor i. e. the top floor. • Since this redevelopment project is being carried out u/s. 33(7), NOC from MHADA is mandatory prior to applying for O. C. from MCGM. • However, MHADA has granted part NOC and as per said NOC dated 8th October, 2018, we have obtained part Occupancy Certificate dated 5th April, 2019 from MCGM upto 6th upper floor. • None out of 8 sale component premises have yet been booked for sale. • The reason for granting part NOC is that as per MHADA’s version, part of the project plot was acquired by MHA…”
  4. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51900009758)

    Reason the builder gave MahaRERA:
    “Construction of Project building is complete in all respects upto 7th floor i. e. the top floor and as per MHADA’s part NOC dated 8th October, 2018, we have obtained part Occupancy Certificate dated 5th April, 2019 from MCGM upto 6th upper…” Read the full reason“Construction of Project building is complete in all respects upto 7th floor i. e. the top floor and as per MHADA’s part NOC dated 8th October, 2018, we have obtained part Occupancy Certificate dated 5th April, 2019 from MCGM upto 6th upper floor. Due to lack of minimum required numbers as per the provisions of the Maharashtra Co-operative Societies Act, no Association of Allottees could yet been formed. A detailed explanation for non-formation of Association of Allottees is attached herewith in a separate sheet.”
  5. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51900025291)

    Reason the builder gave MahaRERA: “As per Attachment”

Source: Venus Keniwadi Annapurna’s extension records on MahaRERA (P51900008800), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Venus Keniwadi Annapurna

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900008800
Status
Lapsed (registration period ended)
Builder
Venus Housing Enterprise
Location
Agar Bazaar Prabhadevi, Mumbai · 400028
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
December 2018
Latest completion date
June 2025
Delay so far
78 months
Homes
13
Sold or booked
75%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

Construction progress of Venus Keniwadi Annapurna, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ANNAPURNA WING B100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • ANNAPURNA WING B: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Venus Keniwadi Annapurna every 1–2 months.

Venus Keniwadi Annapurna: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK631 – 8308
1 BHK435 – 4875
Shops52 – 553
Office Space3091

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Venus Keniwadi Annapurna →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Venus Keniwadi Annapurna: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Venus Keniwadi Annapurna

What is the possession date of Venus Keniwadi Annapurna?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Venus Keniwadi Annapurna in Agar Bazaar Prabhadevi, Mumbai is 30 June 2025 — 78 months later than 31 December 2018, the date given at registration. That date has already passed.

The date has already moved 78 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Venus Keniwadi Annapurna?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Venus Keniwadi Annapurna's builder has filed on MahaRERA, the official one, is 30 June 2025, already 78 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Venus Keniwadi Annapurna extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Venus Keniwadi Annapurna's builder applied to MahaRERA to extend the completion date 4 times: to 31 December 2020, giving the reason "• Project building comprises of 17 premises, out of which 5 premises are to be handed over to the owners, 3 shops and 1 office to be handed over to the old tenants/occupants, free of cost. • None out of 8 sale component premises have yet been booked for sale. • Project building was almost complete in all respects in November, 2017. • Since the redevelopment project consisting of ‘A’ & ‘B’ wing is being carried out u/s. 33(7), NOC from MHADA is mandatory prior to applying for O. C. from MCGM. • For granting NOC, MHADA insisted on execution and registration of ownership agreements with old te…"; to 31 December 2020, giving the reason "• Construction of Project building is complete in all respects upto 7th floor i. e. the top floor. • Since this redevelopment project is being carried out u/s. 33(7), NOC from MHADA is mandatory prior to applying for O. C. from MCGM. • However, MHADA has granted part NOC and as per said NOC dated 8th October, 2018, we have obtained part Occupancy Certificate dated 5th April, 2019 from MCGM upto 6th upper floor. • None out of 8 sale component premises have yet been booked for sale. • The reason for granting part NOC is that as per MHADA’s version, part of the project plot was acquired by MHA…"; to 30 June 2024, giving the reason "Construction of Project building is complete in all respects upto 7th floor i. e. the top floor and as per MHADA’s part NOC dated 8th October, 2018, we have obtained part Occupancy Certificate dated 5th April, 2019 from MCGM upto 6th upper floor. Due to lack of minimum required numbers as per the provisions of the Maharashtra Co-operative Societies Act, no Association of Allottees could yet been formed. A detailed explanation for non-formation of Association of Allottees is attached herewith in a separate sheet."; to 30 June 2025, giving the reason "As per Attachment".

What is the RERA number of Venus Keniwadi Annapurna?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Venus Keniwadi Annapurna in Agar Bazaar Prabhadevi, Mumbai is P51900008800.

Is Venus Keniwadi Annapurna registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Venus Keniwadi Annapurna is registered as P51900008800 and its status is "Lapsed (registration period ended)".

What is the current construction status of Venus Keniwadi Annapurna? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Venus Keniwadi Annapurna's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ANNAPURNA WING B is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Venus Keniwadi Annapurna have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Venus Keniwadi Annapurna safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Venus Keniwadi Annapurna is registered on MahaRERA as P51900008800, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 78 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Venus Keniwadi Annapurna?

Venus Keniwadi Annapurna isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Venus Keniwadi Annapurna are 435 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Venus Keniwadi Annapurna?

For a flat in Venus Keniwadi Annapurna (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Venus Keniwadi Annapurna received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Venus Keniwadi Annapurna isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Venus Keniwadi Annapurna?

According to GharKundli's check of MahaRERA records (updated October 2026), Venus Keniwadi Annapurna's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Is Venus Keniwadi Annapurna a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Venus Keniwadi Annapurna is a redevelopment: 9 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Venus Keniwadi Annapurna uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Venus Keniwadi Annapurna was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Venus Keniwadi Annapurna's possession date changes?

The latest dates are on Venus Keniwadi Annapurna's MahaRERA page (P51900008800). GharKundli's Kundli Watch sends a free WhatsApp update on Venus Keniwadi Annapurna every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Venus Keniwadi Annapurna have?

According to GharKundli's check of MahaRERA records (updated October 2026), Venus Keniwadi Annapurna has one building filed: ANNAPURNA WING B with 9 floors and 17 units.

What are the flat sizes (carpet area) in Venus Keniwadi Annapurna?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Venus Keniwadi Annapurna: 2 BHK: 631 to 830 sq ft carpet (8 homes); 1 BHK: 435 to 487 sq ft carpet (5 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Venus Keniwadi Annapurna?

According to GharKundli's check of MahaRERA records (updated October 2026), Venus Keniwadi Annapurna stands on 561 sq m of land (about 0.1 acres), with 751 sq m of sanctioned built-up area.

What are the reviews of Venus Keniwadi Annapurna?

Google Maps has reviews of Venus Keniwadi Annapurna written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Venus Keniwadi Annapurna?

Venus Keniwadi Annapurna by Venus Housing Enterprise is in Agar Bazaar Prabhadevi, Mumbai, pincode 400028 (near Dadar West, Shivaji Park, Mahim), Maharashtra, and is registered on MahaRERA as P51900008800, per GharKundli's check of MahaRERA records. Its boundaries filed there include S K BOLE ROAD. Its land is filed as FINAL PLOT NO 872. GharKundli lists all 148 MahaRERA projects in Dadar West (400028).

How many flats are in Venus Keniwadi Annapurna, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Venus Keniwadi Annapurna has 13 homes in 1 tower registered on MahaRERA, and 75% of them are sold or booked.

When was Venus Keniwadi Annapurna registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Venus Keniwadi Annapurna was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Does Venus Keniwadi Annapurna have any legal issues or court cases?

1 court case is listed for Venus Keniwadi Annapurna on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Venus Keniwadi Annapurna?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Venus Housing Enterprise.

Other projects in Mumbai City

All 148 projects in Dadar West (400028) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.