ANANTAYA APARTMENTS
by Sanskriti Developers · Girgaon, MumbaiAlso near Khetwadi, Bhuleshwar, Grant Road
Possession date of ANANTAYA APARTMENTS: 30 April 2027, moved from 30 December 2021 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900011221, and currently active. Its completion date has moved from December 2021 to April 2027: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ANANTAYA APARTMENTS?
How the possession date of ANANTAYA APARTMENTS has moved
30 December 2021
Completion date given when the project was registered
29 December 2022
Extended at the builder's request (MahaRERA application EXT51900011150)
Reason the builder gave MahaRERA:
“The reason for delay in completion of project is due to delay caused by supply of materials and services by contractors, market conditions of the Real Estate sector and Prolonged delay in obtaining necessary delay from the Authority. Howeve…” Read the full reason
“The reason for delay in completion of project is due to delay caused by supply of materials and services by contractors, market conditions of the Real Estate sector and Prolonged delay in obtaining necessary delay from the Authority. However, we shall endeavor completion of project within extended duration of 12 months.”31 December 2024
Extended at the builder's request (MahaRERA application EXT51900015225)
Reason the builder gave MahaRERA: “Detailed reasons are provided in the other attachment.”
31 December 2026
Extended at the builder's request (MahaRERA application EXT51900024804)
Reason the builder gave MahaRERA:
“The delay has been caused by a combination of procurement issues, site conditions, temporary funding constraints, and delays in obtaining the final Occupancy Certificate (OC). However, we have received the Part Occupancy Certificate (OC) fo…” Read the full reason
“The delay has been caused by a combination of procurement issues, site conditions, temporary funding constraints, and delays in obtaining the final Occupancy Certificate (OC). However, we have received the Part Occupancy Certificate (OC) for the floors up to the 13th level, and possession letters have been issued to the allottees of these floors. For flats beyond the 13th floor, we have obtained consents from the allottees and submitted the required consents to the authorities. We kindly request an extension until 31st December 2026 to finalize the construction, secure the final OC, and ens…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ANANTAYA APARTMENTS’s extension records on MahaRERA (P51900011221), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ANANTAYA APARTMENTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900011221
- Status
- Registered and active
- Builder
- Sanskriti Developers
- Location
- Girgaon, Mumbai · 400004
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- April 2027
- Delay so far
- 60 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 70
- Sold or booked
- 92%
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Appeals at the tribunal
- 3
- Title report on file
- Not found
Construction progress of ANANTAYA APARTMENTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ANANTAYA | 100% | 100% | 98% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- ANANTAYA: covers 20(Ground+19 Upper Floors)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ANANTAYA APARTMENTS every month.
ANANTAYA APARTMENTS: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 396 – 584 | 54 |
| Shops | 47 – 838 | 17 |
| 2 BHK | 515 – 741 | 11 |
| 1 Room Kitchen | 234 – 300 | 2 |
| 3 BHK | 901 – 1,085 | 2 |
- Buildings: ANANTAYA (38 floors, 86 units)
- Land: 1,037 sq m (about 0.3 acres) · sanctioned built-up 3,994 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ANANTAYA APARTMENTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ANANTAYA APARTMENTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ANANTAYA APARTMENTS
What is the possession date of ANANTAYA APARTMENTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ANANTAYA APARTMENTS in Girgaon, Mumbai is 30 April 2027 — 60 months later than 30 December 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ANANTAYA APARTMENTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ANANTAYA APARTMENTS's builder has filed on MahaRERA, the official one, is 30 April 2027, already 60 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ANANTAYA APARTMENTS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTAYA APARTMENTS's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2022, giving the reason "The reason for delay in completion of project is due to delay caused by supply of materials and services by contractors, market conditions of the Real Estate sector and Prolonged delay in obtaining necessary delay from the Authority. However, we shall endeavor completion of project within extended duration of 12 months."; to 31 December 2024, giving the reason "Detailed reasons are provided in the other attachment."; to 31 December 2026, giving the reason "The delay has been caused by a combination of procurement issues, site conditions, temporary funding constraints, and delays in obtaining the final Occupancy Certificate (OC). However, we have received the Part Occupancy Certificate (OC) for the floors up to the 13th level, and possession letters have been issued to the allottees of these floors. For flats beyond the 13th floor, we have obtained consents from the allottees and submitted the required consents to the authorities. We kindly request an extension until 31st December 2026 to finalize the construction, secure the final OC, and ens…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of ANANTAYA APARTMENTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ANANTAYA APARTMENTS in Girgaon, Mumbai is P51900011221.
Is ANANTAYA APARTMENTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTAYA APARTMENTS is registered as P51900011221 and its status is "Registered and active".
What is the construction status of ANANTAYA APARTMENTS?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTAYA APARTMENTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ANANTAYA is 100% done and internal work 98%. GharKundli's full report compares construction progress with the deadline.
Does ANANTAYA APARTMENTS have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ANANTAYA APARTMENTS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTAYA APARTMENTS is registered on MahaRERA as P51900011221, its completion date has moved 60 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ANANTAYA APARTMENTS's possession date changes?
The latest dates are on ANANTAYA APARTMENTS's MahaRERA page (P51900011221). GharKundli's Kundli Watch sends a free WhatsApp update on ANANTAYA APARTMENTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ANANTAYA APARTMENTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTAYA APARTMENTS has one building filed: ANANTAYA with 38 floors and 86 units.
What are the flat sizes (carpet area) in ANANTAYA APARTMENTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ANANTAYA APARTMENTS: 1 BHK: 396 to 584 sq ft carpet (54 homes); 2 BHK: 515 to 741 sq ft carpet (11 homes); 1 Room Kitchen: 234 to 300 sq ft carpet (2 homes); 3 BHK: 901 to 1085 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of ANANTAYA APARTMENTS?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTAYA APARTMENTS stands on 1,037 sq m of land (about 0.3 acres), with 3,994 sq m of sanctioned built-up area.
Where can I read reviews of ANANTAYA APARTMENTS?
Google Maps has reviews of ANANTAYA APARTMENTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ANANTAYA APARTMENTS?
ANANTAYA APARTMENTS by Sanskriti Developers is in Girgaon, Mumbai (pincode 400004), near Khetwadi, Bhuleshwar, Grant Road, Maharashtra, and is registered on MahaRERA as P51900011221, per GharKundli's check of MahaRERA records.
How many homes are in ANANTAYA APARTMENTS?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTAYA APARTMENTS has 70 homes in 1 tower registered on MahaRERA, and 92% of them are sold or booked.
When was ANANTAYA APARTMENTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTAYA APARTMENTS was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on ANANTAYA APARTMENTS?
No court cases are listed for ANANTAYA APARTMENTS on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of ANANTAYA APARTMENTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sanskriti Developers.
Check it yourself on MahaRERA
- How to check the possession date of ANANTAYA APARTMENTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in pincode 400004
- AADITYA LUXURIA
- MEHTA SUNSHINE HEIGHTS B WING
- Annapurna Sadan
- ONYX
- DREAM RESIDENCY
- Meadows
- Shakuntala Sadan
- MAHAJAN WADI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.