Om Gautam Residency
by ATHARVA RISE · Malad East, Mumbai 400097Also near Malad West, Borivali West, Goregaon West
What’s in the report? →Possession date of Om Gautam Residency (MahaRERA P51800046074): 29 June 2025, moved from 30 June 2024 (12 months later), and it has already passed. It has 64 homes (1 BHK and 2 BHK, 320–507 sq ft carpet), 100% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800046074. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800046074, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2025) has passed.
What do you want to know about Om Gautam Residency?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Om Gautam Residency has moved
30 June 2024
Completion date given when the project was registered
29 June 2025
Extended at the builder's request (MahaRERA application EXT51800019777)
Reason the builder gave MahaRERA: “Due to shortage of material and labour not able to complete project please grant us extension till 29/06/2025”
Source: Om Gautam Residency’s extension records on MahaRERA (P51800046074), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Om Gautam Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800046074
- Status
- Lapsed (registration period ended)
- Builder
- ATHARVA RISE
- Location
- Malad East, Mumbai · 400097
- Project type
- Residential / Group Housing
- Registered on
- 15 Jun 2022
- Completion date at registration
- June 2024
- Latest completion date
- June 2025
- Delay so far
- 12 months
- Homes
- 64
- Sold or booked
- 100%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Om Gautam Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| OM GAUTAM RESIDENCY WING A | 100% | 100% | 100% | 80% |
| OM GAUTAM RESIDENCY WING B | 100% | 100% | 100% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- OM GAUTAM RESIDENCY WING A: covers GROUND + 9TH FLOOR
- OM GAUTAM RESIDENCY WING B: covers GROUND + 9TH FLOOR
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Om Gautam Residency every 1–2 months.
Om Gautam Residency: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 368 | 32 |
| 2 BHK | 320 – 507 | 32 |
- Buildings: OM GAUTAM RESIDENCY WING A (11 floors, 32 units) · OM GAUTAM RESIDENCY WING B (11 floors, 32 units)
- Land: 983 sq m (about 0.2 acres) · sanctioned built-up 2,906 sq m
- Land, as filed: 12A/A/1A/1/2
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Atharva Rise has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Om Gautam Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Om Gautam Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Om Gautam Residency
What is the possession date of Om Gautam Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Om Gautam Residency in Malad East, Mumbai is 29 June 2025 — 12 months later than 30 June 2024, the date given at registration. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Om Gautam Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Om Gautam Residency's builder has filed on MahaRERA, the official one, is 29 June 2025, already 12 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Om Gautam Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Gautam Residency's builder applied to MahaRERA to extend the completion date once: to 29 June 2025, giving the reason "Due to shortage of material and labour not able to complete project please grant us extension till 29/06/2025".
What is the RERA number of Om Gautam Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Om Gautam Residency in Malad East, Mumbai is P51800046074.
Is Om Gautam Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Gautam Residency is registered as P51800046074 and its status is "Lapsed (registration period ended)".
What is the current construction status of Om Gautam Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Gautam Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Om Gautam Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Om Gautam Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Gautam Residency is registered on MahaRERA as P51800046074, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Om Gautam Residency?
Om Gautam Residency isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Om Gautam Residency are 320 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Om Gautam Residency?
For a flat in Om Gautam Residency (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Om Gautam Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Om Gautam Residency isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 29 June 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Om Gautam Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Gautam Residency's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (29 June 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is Om Gautam Residency a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Gautam Residency is a redevelopment: 28 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Om Gautam Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Om Gautam Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Om Gautam Residency's possession date changes?
The latest dates are on Om Gautam Residency's MahaRERA page (P51800046074). GharKundli's Kundli Watch sends a free WhatsApp update on Om Gautam Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Om Gautam Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Gautam Residency has 2 buildings filed: OM GAUTAM RESIDENCY WING A with 11 floors and 32 units; OM GAUTAM RESIDENCY WING B with 11 floors and 32 units.
What are the flat sizes (carpet area) in Om Gautam Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Om Gautam Residency: 1 BHK: 368 sq ft carpet (32 homes); 2 BHK: 320 to 507 sq ft carpet (32 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Om Gautam Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Gautam Residency stands on 983 sq m of land (about 0.2 acres), with 2,906 sq m of sanctioned built-up area.
What is the track record of Om Gautam Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Atharva Rise has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Om Gautam Residency?
Google Maps has reviews of Om Gautam Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Om Gautam Residency?
Om Gautam Residency by ATHARVA RISE is in Malad East, Mumbai, pincode 400097 (near Malad West, Borivali West, Goregaon West), Maharashtra, and is registered on MahaRERA as P51800046074, per GharKundli's check of MahaRERA records. Its land is filed as 12A/A/1A/1/2. GharKundli lists all 195 MahaRERA projects in Malad East (400097).
How many flats are in Om Gautam Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Gautam Residency has 64 homes in 2 towers registered on MahaRERA, and 100% of them are sold or booked.
When was Om Gautam Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Gautam Residency was registered on MahaRERA on 15 June 2022. GharKundli did not find a title report on the land on file there.
Does Om Gautam Residency have any legal issues or court cases?
No court cases are listed for Om Gautam Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Om Gautam Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ATHARVA RISE, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Om Gautam Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Malad East (400097)
- L&T Realty Ahana Tower A
- Aarambh Phase III by group Satellite
- L&T Realty Ahana Tower B
- Pearl Solitaire
- Namo Whispering Bliss
- Upper East 97
- Nivetia Heights
- Vardhan Royale
Other projects by ATHARVA RISE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.