Crescent Heights

by Harshmaan Spaces LLP · Borivali West, MumbaiAlso near Dahisar West, I C Colony, Dahisar East

Possession date of Crescent Heights: 31 December 2026, moved from 31 March 2025 (21 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800045723, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Crescent Heights?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Crescent Heights has moved

  1. 31 March 2025

    Completion date given when the project was registered

  2. 31 July 2025

    Extended at the builder's request (MahaRERA application EXT51800027888)

    Reason the builder gave MahaRERA:
    “Reason for requirement of extension: We are requesting for extension of only 4 months i.e. up to 31st July, 2025 only due to the below mentioned critical and important reasons for delay: • Environmental restrictions were imposed due to whic…” Read the full reason“Reason for requirement of extension: We are requesting for extension of only 4 months i.e. up to 31st July, 2025 only due to the below mentioned critical and important reasons for delay: • Environmental restrictions were imposed due to which work was on halt for almost 24-25 days and then starting the site again took few more days. • Another important reason to note was, Concrete cement road work was going in front of entrance of the project due to which entry of material at site was all stopped for almost stopped for 22-23 days and after lot of complains and request little kaccha road was…”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA21072621824)

    Reason the builder gave MahaRERA:
    “Reason for Extension: We have received part Occupation cum completion certificate UNDER REG. 11(6) OF DCPR 2034 AND PART OCCUPATION UNDER REG. 11(7) /11(8) OF DCPR 2034 no P-8268/2021/(1069E)/R/N WARD/EKSAR (S) R/N/OCC/1/NEW of 31 August 20…” Read the full reason“Reason for Extension: We have received part Occupation cum completion certificate UNDER REG. 11(6) OF DCPR 2034 AND PART OCCUPATION UNDER REG. 11(7) /11(8) OF DCPR 2034 no P-8268/2021/(1069E)/R/N WARD/EKSAR (S) R/N/OCC/1/NEW of 31 August 2025 for The Part 1 development work of Residential building comprising of Basement for pump room + Ground floor for Entrance lobby, Letter box panel, Fire panel & parking + Mezzanine floor for Double height entrance lobby & meter room + 1st to 18th upper floor + 19th (part) upper floor except flat no 1901 + LMR and OHT along with Puzzle Parking on 31st Aug…”

Source: Crescent Heights’s extension records on MahaRERA (P51800045723), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Crescent Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800045723
Status
Registered and active
Builder
Harshmaan Spaces LLP
Location
Borivali West, Mumbai · 400103
Project type
Residential / Group Housing
Registered on
6 Jun 2022
Completion date at registration
March 2025
Latest completion date
December 2026
Delay so far
21 months
Homes
74
Sold or booked
98%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Crescent Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
CRESCENT HEIGHTS100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • CRESCENT HEIGHTS: covers 19 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Crescent Heights every month.

Crescent Heights: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK154 – 1,41841
2 BHK130 – 1,52127
1 BHK119 – 5216

The builder’s record and reviews

Harshmaan Spaces (a group of 2 linked companies) has 4 projects on MahaRERA since 2021, this one included. Of the 4 GharKundli has checked: 4 still being built, 1 past the promised date (typically 19 months late). No complaints on MahaRERA.

Read Google reviews of Crescent Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Crescent Heights: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Crescent Heights

What is the possession date of Crescent Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Crescent Heights in Borivali West, Mumbai is 31 December 2026 — 21 months later than 31 March 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Crescent Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Crescent Heights's builder has filed on MahaRERA, the official one, is 31 December 2026, already 21 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Crescent Heights extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Heights's builder applied to MahaRERA to extend the completion date 2 times: to 31 July 2025, giving the reason "Reason for requirement of extension: We are requesting for extension of only 4 months i.e. up to 31st July, 2025 only due to the below mentioned critical and important reasons for delay: • Environmental restrictions were imposed due to which work was on halt for almost 24-25 days and then starting the site again took few more days. • Another important reason to note was, Concrete cement road work was going in front of entrance of the project due to which entry of material at site was all stopped for almost stopped for 22-23 days and after lot of complains and request little kaccha road was…"; to 31 December 2026, giving the reason "Reason for Extension: We have received part Occupation cum completion certificate UNDER REG. 11(6) OF DCPR 2034 AND PART OCCUPATION UNDER REG. 11(7) /11(8) OF DCPR 2034 no P-8268/2021/(1069E)/R/N WARD/EKSAR (S) R/N/OCC/1/NEW of 31 August 2025 for The Part 1 development work of Residential building comprising of Basement for pump room + Ground floor for Entrance lobby, Letter box panel, Fire panel & parking + Mezzanine floor for Double height entrance lobby & meter room + 1st to 18th upper floor + 19th (part) upper floor except flat no 1901 + LMR and OHT along with Puzzle Parking on 31st Aug…".

What is the RERA number of Crescent Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Crescent Heights in Borivali West, Mumbai is P51800045723.

Is Crescent Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Heights is registered as P51800045723 and its status is "Registered and active".

What is the construction status of Crescent Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on CRESCENT HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Crescent Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Crescent Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Heights is registered on MahaRERA as P51800045723, its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Crescent Heights's possession date changes?

The latest dates are on Crescent Heights's MahaRERA page (P51800045723). GharKundli's Kundli Watch sends a free WhatsApp update on Crescent Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Crescent Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Heights has one building filed: CRESCENT HEIGHTS with 20 floors and 74 units.

What are the flat sizes (carpet area) in Crescent Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Crescent Heights: 3 BHK: 154 to 1418 sq ft carpet (41 homes); 2 BHK: 130 to 1521 sq ft carpet (27 homes); 1 BHK: 119 to 521 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Crescent Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 75 covered car parking spaces for Crescent Heights.

How big is the land of Crescent Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Heights stands on 1,705 sq m of land (about 0.4 acres), with 5,707 sq m of sanctioned built-up area.

What is the track record of Crescent Heights's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Harshmaan Spaces (a group of 2 linked companies) has 4 projects on MahaRERA since 2021, this one included. Of the 4 GharKundli has checked: 4 still being built, 1 past the promised date (typically 19 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Crescent Heights?

Google Maps has reviews of Crescent Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Crescent Heights?

Crescent Heights by Harshmaan Spaces LLP is in Borivali West, Mumbai (pincode 400103), near Dahisar West, I C Colony, Dahisar East, Maharashtra, and is registered on MahaRERA as P51800045723, per GharKundli's check of MahaRERA records.

How many homes are in Crescent Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Heights has 74 homes in 1 tower registered on MahaRERA, and 98% of them are sold or booked.

When was Crescent Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Heights was registered on MahaRERA on 6 June 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Crescent Heights?

No court cases are listed for Crescent Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Crescent Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Harshmaan Spaces LLP, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Borivali West

All 93 projects in Borivali West (400103) →

Other projects by Harshmaan Spaces LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.