New Abhiram CHS LTD

by Peerless Constructions Pvt. Ltd. (Goyal) · Kastur Park, Mumbai 400092Also near Borivali West, Kandivali West, Shimpoli

What’s in the report? →

Possession: New Abhiram CHS LTD (MahaRERA P51800045965) is marked completed on MahaRERA. It has 31 homes (1 BHK and 2 BHK, 375–1060 sq ft carpet), 94% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800045965. Status: Completed.

Source: MahaRERA website — records for P51800045965, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about New Abhiram CHS LTD?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of New Abhiram CHS LTD has moved

  1. 30 June 2025

    Completion date given when the project was registered

  2. 25 September 2025

    Extended at the builder's request (MahaRERA application EA27092517959)

    Reason the builder gave MahaRERA: “OC RECEVIED”

Source: New Abhiram CHS LTD’s extension records on MahaRERA (P51800045965), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on New Abhiram CHS LTD

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800045965
Status
Completed
Builder
Peerless Constructions Pvt. Ltd.
Location
Kastur Park, Mumbai · 400092
Project type
Others
Registered on
15 Jun 2022
Completion date at registration
June 2025
Latest completion date
September 2025
Delay so far
3 months
Homes
31
Sold or booked
94%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of New Abhiram CHS LTD, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
New Abhiram CHS LTD100%10%100%95%

Commencement certificate (CC), as filed on MahaRERA

  • New Abhiram CHS LTD: covers ground + 9 upper floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on New Abhiram CHS LTD every 1–2 months.

New Abhiram CHS LTD: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK510 – 1,06030
Shops204 – 3334
Office Space608 – 6252
1 BHK3751

The builder’s record and reviews

Goyal Wedevelopment (a group of 6 linked companies) has 8 projects on MahaRERA since 2020, this one included. Of the 8 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 3 months); 6 still being built, 3 past the promised date (typically 9 months late). No complaints on MahaRERA.

Read Google reviews of New Abhiram CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

New Abhiram CHS LTD: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about New Abhiram CHS LTD

What is the possession date of New Abhiram CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for New Abhiram CHS LTD in Kastur Park, Mumbai is 25 September 2025 — 3 months later than 30 June 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for New Abhiram CHS LTD?

Builders and listing sites often quote an earlier "target" date for handover. The completion date New Abhiram CHS LTD's builder has filed on MahaRERA, the official one, is 25 September 2025, already 3 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of New Abhiram CHS LTD extended?

According to GharKundli's check of MahaRERA records (updated October 2026), New Abhiram CHS LTD's builder applied to MahaRERA to extend the completion date once: to 25 September 2025, giving the reason "OC RECEVIED".

What is the RERA number of New Abhiram CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of New Abhiram CHS LTD in Kastur Park, Mumbai is P51800045965.

Is New Abhiram CHS LTD registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), New Abhiram CHS LTD is registered as P51800045965 and its status is "Completed".

What is the current construction status of New Abhiram CHS LTD? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), New Abhiram CHS LTD's status on MahaRERA is "Completed". As filed by the builder, slab work on New Abhiram CHS LTD is 10% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does New Abhiram CHS LTD have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is New Abhiram CHS LTD safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), New Abhiram CHS LTD is registered on MahaRERA as P51800045965, its MahaRERA status is "Completed", its completion date has moved 3 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in New Abhiram CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), New Abhiram CHS LTD is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in New Abhiram CHS LTD?

For a flat in New Abhiram CHS LTD (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has New Abhiram CHS LTD received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated October 2026), New Abhiram CHS LTD is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was New Abhiram CHS LTD completed?

According to GharKundli's check of MahaRERA records (updated October 2026), New Abhiram CHS LTD is marked completed on MahaRERA, and the completion date filed there is 25 September 2025. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Is New Abhiram CHS LTD a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), New Abhiram CHS LTD is a redevelopment: 20 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has New Abhiram CHS LTD uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for New Abhiram CHS LTD was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if New Abhiram CHS LTD's possession date changes?

The latest dates are on New Abhiram CHS LTD's MahaRERA page (P51800045965). GharKundli's Kundli Watch sends a free WhatsApp update on New Abhiram CHS LTD every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does New Abhiram CHS LTD have?

According to GharKundli's check of MahaRERA records (updated October 2026), New Abhiram CHS LTD has one building filed: New Abhiram CHS LTD with 10 floors and 37 units.

What are the flat sizes (carpet area) in New Abhiram CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for New Abhiram CHS LTD: 2 BHK: 510 to 1060 sq ft carpet (30 homes); 1 BHK: 375 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of New Abhiram CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), New Abhiram CHS LTD stands on 693 sq m of land (about 0.2 acres), with 1,448 sq m of sanctioned built-up area.

What is the track record of New Abhiram CHS LTD's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Goyal Wedevelopment (a group of 6 linked companies) has 8 projects on MahaRERA since 2020, this one included. Of the 8 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 3 months); 6 still being built, 3 past the promised date (typically 9 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of New Abhiram CHS LTD?

Google Maps has reviews of New Abhiram CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of New Abhiram CHS LTD?

New Abhiram CHS LTD by Peerless Constructions Pvt. Ltd. (Goyal) is in Kastur Park, Mumbai, pincode 400092 (near Borivali West, Kandivali West, Shimpoli), Maharashtra, and is registered on MahaRERA as P51800045965, per GharKundli's check of MahaRERA records. Its boundaries filed there include 18 point 30 mtrs Road. Its land is filed as 620. GharKundli lists all 362 MahaRERA projects in Borivali West (400092).

How many flats are in New Abhiram CHS LTD, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), New Abhiram CHS LTD has 31 homes in 1 tower registered on MahaRERA, and 94% of them are sold or booked.

When was New Abhiram CHS LTD registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), New Abhiram CHS LTD was registered on MahaRERA on 15 June 2022. GharKundli did not find a title report on the land on file there.

Does New Abhiram CHS LTD have any legal issues or court cases?

No court cases are listed for New Abhiram CHS LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of New Abhiram CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Peerless Constructions Pvt. Ltd., the company Goyal files this project under.

Other projects in Borivali

All 362 projects in Borivali West (400092) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.