by NATASHA DEVELOPERS PVT LTD · Hariyali, Vikhroli East, Mumbai

Registered on MahaRERA under P51800047526, and currently active. Its completion date has moved from December 2028 to April 2029, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on NATASHA ATLANTIS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800047526
Status
Registered and active
Builder
NATASHA DEVELOPERS PVT LTD
Location
Hariyali, Vikhroli East, Mumbai · 400083
Project type
Others
Registered on
7 Nov 2022
Completion date at registration
December 2028
Latest completion date
April 2029
Delay so far
4 months
Homes
244
Sold or booked
45%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Kundli Watch

NATASHA ATLANTIS: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about NATASHA ATLANTIS

Is NATASHA ATLANTIS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NATASHA ATLANTIS is registered as P51800047526 and its status is "Registered and active".

Where is NATASHA ATLANTIS?

NATASHA ATLANTIS by NATASHA DEVELOPERS PVT LTD is in Hariyali, Vikhroli East, Mumbai (pincode 400083), Maharashtra, and is registered on MahaRERA as P51800047526, per GharKundli's check of MahaRERA records.

When is possession of NATASHA ATLANTIS due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NATASHA ATLANTIS in Hariyali, Vikhroli East, Mumbai is 30 April 2029 — 4 months later than 31 December 2028, the date given at registration.

Does NATASHA ATLANTIS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of NATASHA ATLANTIS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NATASHA DEVELOPERS PVT LTD, which has 2 other projects registered on MahaRERA.

Other projects in pincode 400083

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.