Shraddha Presidency
by Shraddha Landmark Private Limited · Hariyali, Vikhroli East, MumbaiAlso near Tagore Nagar, vikroli, kanamwar Nagar
Possession date of Shraddha Presidency: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800050356, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Shraddha Presidency?
How the possession date of Shraddha Presidency has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shraddha Presidency’s extension records on MahaRERA (P51800050356), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shraddha Presidency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800050356
- Status
- Registered and active
- Builder
- Shraddha Landmark Private Limited
- Location
- Hariyali, Vikhroli East, Mumbai · 400083
- Project type
- Residential / Group Housing
- Registered on
- 5 Apr 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 303
- Sold or booked
- 91%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 20
Construction progress of Shraddha Presidency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A, B and C | 100% | 46% | 5% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Wing A, B and C: covers Top of 19th floor of Wing A & B & upto top of 18th floor of Wing C (20 Floors)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shraddha Presidency every month.
Shraddha Presidency: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing A, B and C (19 floors, 303 units)
- Land: 2,310 sq m (about 0.6 acres)
- Boundaries filed include: 18M Wide External Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects.
Read Google reviews of Shraddha Presidency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shraddha Presidency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Shraddha Presidency
What is the possession date of Shraddha Presidency?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shraddha Presidency in Hariyali, Vikhroli East, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Shraddha Presidency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shraddha Presidency's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Shraddha Presidency?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shraddha Presidency in Hariyali, Vikhroli East, Mumbai is P51800050356.
Is Shraddha Presidency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shraddha Presidency is registered as P51800050356 and its status is "Registered and active".
What is the construction status of Shraddha Presidency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shraddha Presidency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing A, B and C is 46% done and internal work 5%. GharKundli's full report compares construction progress with the deadline.
Does Shraddha Presidency have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Shraddha Presidency safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Shraddha Presidency is registered on MahaRERA as P51800050356, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Shraddha Presidency's possession date changes?
The latest dates are on Shraddha Presidency's MahaRERA page (P51800050356). GharKundli's Kundli Watch sends a free WhatsApp update on Shraddha Presidency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shraddha Presidency have?
According to GharKundli's check of MahaRERA records (updated November 2026), Shraddha Presidency has one building filed: Wing A, B and C with 19 floors and 303 units.
How big is the land of Shraddha Presidency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shraddha Presidency stands on 2,310 sq m of land (about 0.6 acres).
What is the track record of Shraddha Presidency's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Shraddha Presidency?
Google Maps has reviews of Shraddha Presidency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Shraddha Presidency?
Shraddha Presidency by Shraddha Landmark Private Limited is in Hariyali, Vikhroli East, Mumbai (pincode 400083), near Tagore Nagar, vikroli, kanamwar Nagar, Maharashtra, and is registered on MahaRERA as P51800050356, per GharKundli's check of MahaRERA records. Its boundaries filed there include 18M Wide External Road.
How many homes are in Shraddha Presidency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shraddha Presidency has 303 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.
When was Shraddha Presidency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shraddha Presidency was registered on MahaRERA on 5 April 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Shraddha Presidency?
No court cases are listed for Shraddha Presidency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Shraddha Presidency?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shraddha Landmark Private Limited, which has 20 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Shraddha Presidency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Hariyali, Vikhroli East
All 176 projects in Vikhroli East (400083) →Other projects by Shraddha Landmark Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.